The project manager must maintain an effective communication link with the customer'ssatisfaction with the progress of the project.The project manager maintains this link through( ).

A.periodic project reports,periodic visits to the customer,and telephonic exchanges
B.subordinates,project team members,and the project sponsor
C.one-time reports,weekly reports,and monthly reports
D.the telephone,facsimile,and data transmission

参考答案

参考解析
解析:项目经理必须保持一个有效的沟通,项目经理保持这个环节,通过与客户的项目定期报告,定期走访客户和电话交流。
更多 “The project manager must maintain an effective communication link with the customer'ssatisfaction with the progress of the project.The project manager maintains this link through( ).A.periodic project reports,periodic visits to the customer,and telephonic exchanges B.subordinates,project team members,and the project sponsor C.one-time reports,weekly reports,and monthly reports D.the telephone,facsimile,and data transmission” 相关考题
考题 The scope baseline/project charter is prepared by the:AProject managerBProject manager and project officeCProject manager, project office and functional teamDProject manager, project office, functional team and project sponsorEProject manager, project sponsor and customer/user

考题 Documented work authorization provide:A.a means of effective internal coordination of the project's activities.B.an audit trail of all work authorized from project initiation to completion.C.a means for communication of work activity between the project manager and the performing activities.D.All of the aboveE.A and B only.

考题 In the project environment, the individual ultimately responsible for quality control is:A . The line workers who must strive "to do things right the first time" to avoid quality problems.B . the company's quality control manager who must work with the project members to ensure the quality control program is effective.C . The head of the production department who retains ultimate quality control responsibility for all the company's projects.D . The project manager who has ultimate responsibility for the entire project.E . the customer who must ensure that he is receiving a quality product from the vendor.

考题 The project manager must be concerned with building a closely knit team. During the project kickoff meeting, the project manager can get a good start at team building by providing the team with:A . Proposed salary increases if the project is successfulB . Bonuses for early completion dateC . A promise of future assignmentsD . Well-defined project objectivesE . Linear responsibility charts

考题 An effective Project Manager does not share project _____ with the team members.A VisionB responsibilityC solution to problemsD accountabilityE status

考题 The project manager must receive reports and briefings from engineers, contracting officers, procurement personnel and marketing people. The project manager's communication dilemma is one of:A encodingB decodingC choice of a mediumD one-way communicationE All of the above.

考题 114 The project manager must receive reports and briefings from engineers, contracting officers, procurement personnel and marketing people. The project manager's communication dilemma is one of:A. encodingB. decodingC. choice of a mediumD. one-way communicationE. All of the above.

考题 41 In the project environment, the individual ultimately responsible for quality control is:A. The line workers who must strive "to do things right the first time" to avoid quality problems. B. the company's quality control manager who must work with the project members to ensure the quality control program is effective.C. The head of the production department who retains ultimate quality control responsibility for all the company's projects.D. The project manager who has ultimate responsibility for the entire project.E.the customer who must ensure that he is receiving a quality product from the vendor

考题 171 Documented work authorization provide:A. a means of effective internal coordination of the project's activities.B. an audit trail of all work authorized from project initiation to completionC.a means for communication of work activity between the project manager and the performing activities.D. All of the aboveE. A and B only

考题 66 A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:A. Change the scope baselineB. Prepare a variance reportC. Call a meeting of the configuration control boardD. Change the project's objectivesE. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

考题 123 The scope baseline/project charter is prepared by the:A. Project managerB. Project manager and project officeC. Project manager, project office and functional teamD. Project manager, project office, functional team and project sponsorE. Project manager, project sponsor and customer/user

考题 64 An effective Project Manager does not share project _____ with the team members.A. VisionB. responsibilityC. solution to problemsD. accountabilityE. status

考题 In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project‘s communication. According to Metcalfe‘s Law, a project with 10 stakeholders has()potential communication channels.A.10B.45C.50D.100

考题 196 The project manager must receive reports and briefings from engineers, contracting officers, procurement personnel and marketing people. The project manager's communication dilemma is one of:A. encodingB. decodingC. choice of a mediumD. one-way communicationE. All of the above

考题 ● The scope of a project can be expected to change if:A The project manager must provide cost estimates without having a design conceptB Oversimplification (underestimating) of the nature of the work occursC The project manager is assigned after the project is defined, and the cost and schedule are approvedD A clear objective is not providedE All of the above are possible based upon the situation

考题 ● The scope baseline/project charter is prepared by the:A Project managerB Project manager and project officeC Project manager, project office and functional teamD Project manager, project office, functional team and project sponsorE Project manager, project sponsor and customer/user

考题 ● A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:A Change the scope baselineB Prepare a variance reportC Call a meeting of the configuration control boardD Change the project's objectivesE Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

考题 ● Project manager believes that modifying the project scope may provide added value for the customer. The project manager should (73) .(73) A. change the scope baselineB. contact the customer to determine if the change adds valueC. call a meeting of the change control boardD. change the project' s objectives

考题 A project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should______.A.assign change tasks to project membersB.call a meeting of the configuration control boardC.change the scope baselineD.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

考题 ●The project manager must maintain an effective communication link with the customer's satisfaction with the progress of the project. The project manager maintains this link through (71).(71)A.periodic project reports, periodic visits to the customer, and telephonic exchangesB.subordinates, project team members, and the project sponsorC.one-time reports, weekly reports, and monthly reportsD.the telephone, facsimile, and data transmission

考题 ●A project manager is called to an informal meeting with the customer and a problem is raised. This problem has major implications for the project manager's company, but the customer wants to pursue a solution at the meeting.The project manager should (72) .(72)A. tell the customer that he will not address any problems becausethis is only an information exchange meetingB. tell the customer that the problem is not sufficiently defined to determine the appropriate actionC. collect as much information on the problem without committing his company to a solutionD. give the customer a range of solutions that might be acceptable to his Company

考题 Project manager believes that modifying the project scope may provide added value for the customer . The project manager should (73).A.change the scope baselineB.contact the customer to determine if the change adds valueC.call a meeting of the change control boardD.change the project’s objectives

考题 A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( ) A.assign change tasks to project members B.call a meeting of the configuration control board C.change the scope baseline D. postpone the modification until a separate enhancement project is fundedafter this project is completed according to the original baseline

考题 Project manager believes that modifying the project scop may provide added value for the customer.The project manager should( ) A.change the scope baseline B.contact the customer to determine if the change adds value C.call A.meeting of the change control board D.change the project's objectives

考题 A project manager is called to an informal meeting with the customer and a problem is raised. This problem has major implications for the project manager’s company, but the customer wants to pursue a solution at the meeting, The project manager should()A.Tell the customer that he will not address any problems B.Tell the customer that the problem is not sufficiently defined to company to a solution C.Collect as much information on the problem without committing his company to a solution D.Give the customer a range of solutions that might be acceptable to his company

考题 The project manager must maintain an effective communication link with the customer’s satisfaction with the progress of the project. The project manager maintains this link through()A.Periodic project reports, periodic visits to the customer, and telephonic exchanges B.Subordinates, project team members, and the project sponsor C.One-time reports, weekly reports, and monthly reports D.The telephone, facsimile, and data transmission

考题 Within Information Technology projects, communications between the project manager and the project team members should take place:()A、by written and oral communication.B、via a weekly status report.C、through the formal chain of command.D、with approved template forms.