66 A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:

A. Change the scope baseline

B. Prepare a variance report

C. Call a meeting of the configuration control board

D. Change the project's objectives

E. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline


参考答案

更多 “ 66 A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:A. Change the scope baselineB. Prepare a variance reportC. Call a meeting of the configuration control boardD. Change the project's objectivesE. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline ” 相关考题
考题 ● Project(71)is an uncertain event or condition that, if it occurs, has a positive or a negative effect on at least one project objective, such as time, cost, scope, or quality.(71)A.riskB.problemC.resultD.data

考题 在Premiere中如何导入文件。() A.直接拖拽至projeCt窗口B.File-ExportC.双击projeCt窗口D.File-OpenprojeCt

考题 Project ______is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.A.riskB.problemC.resultD.data

考题 以下关于Openstack租户Project说法错误的是()。 A、一个Project资源集合可供多个用户使用B、Project是Openstack各个服务中的一些可以访问的资源集合C、网络云各Project采用硬件共享,逻辑隔离的方式D、租户是一个有身份验证信息的API实体

考题 Project(71)is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.A.riskB.problemC.resultD.data

考题 中国青少年发展基金会在网上的主页地址是()。 A.http://project-hopE.cydF.gov.cnB.http://project-hopE.cydF.acC.http://project-hopE.cydF.edu.cnD.http://project-hopE.cydF.com.cn

考题 Project()is an uncertain event or condition that,if it occurs,has a positiveor a negative effect on at least one project objective,such as time,cost,scope, or quality.A.risk B.problem C.result D.data

考题 Project( )is an uncertain event or condition that,if it occurs,has a positive or a negative effect on at least one project objective,such as time,cost,scope,or quality.A.risk B.problem C.result D.data

考题 在对原理图进行电气规则检查前,可以()打开规则设置界面。A.design-Document OptionsB.Project-Project OptionsC.Tools-Schematic PreferencesD.Project-Configuration Manager

考题 以下选项中哪个选项是根路径的表达方法?A.D:/Program Files/.Net/Project1B./root/.Net/Project1C../home/.Net/Project1D.file://D:/Program Files/.Net/Project1