网友您好, 请在下方输入框内输入要搜索的题目:

题目内容 (请给出正确答案)

123 The scope baseline/project charter is prepared by the:

A. Project manager

B. Project manager and project office

C. Project manager, project office and functional team

D. Project manager, project office, functional team and project sponsor

E. Project manager, project sponsor and customer/user


参考答案

更多 “ 123 The scope baseline/project charter is prepared by the:A. Project managerB. Project manager and project officeC. Project manager, project office and functional teamD. Project manager, project office, functional team and project sponsorE. Project manager, project sponsor and customer/user ” 相关考题
考题 The scope baseline/project charter is prepared by the:AProject managerBProject manager and project officeCProject manager, project office and functional teamDProject manager, project office, functional team and project sponsorEProject manager, project sponsor and customer/user

考题 Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:A.The project manager and project office personnel.B.The project team and functional managers.C.The project sponsor.D.All of the above.E.A and B only.

考题 The project team form. of organization confers both advantages and disadvantages. Disadvantages of the project form. include:A . Conflict in authority between project manager and functional managersB . Dual allegiance on part of team membersC . Complex prioritization of resourcesD . Loss of developed procedures on project dissolutionE . All of the above

考题 In a matrix organizational form, MBO may be difficult to implement:A . If the functional employees are supervised closely by the line manager rather than the project managerB . Unless the project manager has an input into the employee's performance reviewC . Unless the project and line managers agree on the ultimate objectiveD . Unless the project and line managers agree to the duration of the taskE . None of the above are correct answers

考题 The project manager must be concerned with building a closely knit team. During the project kickoff meeting, the project manager can get a good start at team building by providing the team with:A . Proposed salary increases if the project is successfulB . Bonuses for early completion dateC . A promise of future assignmentsD . Well-defined project objectivesE . Linear responsibility charts

考题 108 The way a project manager sends and receives information depends upon:A. How others relate to the project managerB. The project manager's level in the organizational hierarchyC. the size and nature of the projectD. the project manager's salary and ageE. the number of projects going on at one time in the company

考题 128 The project manager must be concerned with building a closely knit team. During the project kickoff meeting, the project manager can get a good start at team building by providing the team with:A. Proposed salary increases if the project is successfulB. Bonuses for early completion dateC. A promise of future assignmentsD. Well-defined project objectivesE. Linear responsibility charts

考题 145 Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:A. The project manager and project office personnel.B. The project team and functional managers.C. The project sponsor.D. All of the above.E. A and B only

考题 174 In a matrix organizational form, MBO may be difficult to implement:A. If the functional employees are supervised closely by the line manager rather than the project managerB. Unless the project manager has an input into the employee's performance review C. Unless the project and line managers agree on the ultimate objectiveD. Unless the project and line managers agree to the duration of the taskE. None of the above are correct answers

考题 66 A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:A. Change the scope baselineB. Prepare a variance reportC. Call a meeting of the configuration control boardD. Change the project's objectivesE. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

考题 131 The project team form. of organization confers both advantages and disadvantages. Disadvantages of the project form. include:A. Conflict in authority between project manager and functional managersB. Dual allegiance on part of team membersC. Complex prioritization of resourcesD. Loss of developed procedures on project dissolutionE. All of the above

考题 139 The project charter is a document designed to tell _____ exactly what the project entails.A. The project managerB. The project officeC. The project teamD. The project sponsorE. Anyone associated with the project

考题 5 The scope baseline/project charter is prepared by the:A. Project managerB. Project manager and project officeC. Project manager, project office and functional teamD. Project manager, project office, functional team and project sponsorE. Project manager, project sponsor and customer/user

考题 13 The project team form. of organization confers both advantages and disadvantages. Disadvantages of the project form. include:A. Conflict in authority between project manager and functional managersB. Dual allegiance on part of team members "C. Complex prioritization of resourcesD. Loss of developed procedures on project dissolutionE. All of the above

考题 ● The scope baseline/project charter is prepared by the:A Project managerB Project manager and project officeC Project manager, project office and functional teamD Project manager, project office, functional team and project sponsorE Project manager, project sponsor and customer/user

考题 ● A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:A Change the scope baselineB Prepare a variance reportC Call a meeting of the configuration control boardD Change the project's objectivesE Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

考题 ● Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by:A The project manager and project office personnel.B The project team and functional managers.C The project sponsor.D All of the above.E A and B only.

考题 ● A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should(75).(75)A.assign change tasks to project membersB.call a meeting of the configuration control boardC.change the scope baselineD.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

考题 ● Project manager believes that modifying the project scope may provide added value for the customer. The project manager should (73) .(73) A. change the scope baselineB. contact the customer to determine if the change adds valueC. call a meeting of the change control boardD. change the project' s objectives

考题 The(70)provides the project manager with the authority to apply organizational resources to project activities.A.project management planB.contractC.project human resource planD.project charter

考题 A project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should______.A.assign change tasks to project membersB.call a meeting of the configuration control boardC.change the scope baselineD.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

考题 The( )provides the project manager with the authority to apply organizational resources to project activities。 A.project management plan B.project charter C.project human resource plan D.project stakeholders

考题 A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( ) A.assign change tasks to project members B.call a meeting of the configuration control board C.change the scope baseline D. postpone the modification until a separate enhancement project is fundedafter this project is completed according to the original baseline

考题 ( )is a process developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.A.Develop Project Charter B.Manage Project Knowledge C.Monitor and Control Project work D.Close project

考题 ( ) is a process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.A.Develop Project Charter B.Manage Project Knowledge C.Monitor anD.Control Project work D.Close project

考题 A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( ) . A.assign change tasks to project members B.call A.meeting of the configuration control board C.change the scope baseline D.postpone the modification until A.separate enhancement project is fundeD.after this project is completeD.according to the original baseline

考题 The()provides the project manager with the authority to apply organizational resources to project activities.A、project management planB、contractC、project human resource planD、project charter