Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()

  • A、executive IT manager
  • B、projectmanger
  • C、change control board
  • D、projectsponsor

参考答案

更多 “ Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()A、executive IT managerB、projectmangerC、change control boardD、projectsponsor” 相关考题
考题 ● During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised (75)are necessary.(75)A. proceedingsB. controlsC. forecasting’sD. prelibations

考题 Hearing problems may be alleviated by changes in diet and exercise habits.A.removedB.curedC.worsenedD.relieved

考题 ● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).(73)A.executive IT managerB.project mangerC.change control boardD.project sponsor

考题 You will be informed about any subtle changes ________ .A at the first opportunityB for the first opportunityC in the first opportunityD on the first opportunity

考题 The government is asking for____ changes in both education and economy, but the people wonder whether the new changes would be of any good to them. A、superB、chimneyC、sweepingD、ruin

考题 Network management helps you to(66)the strengths and weaknesses of your network, as well as determine any configuration changes that may be necessary. Any controlled changes to your network and its components-especially configurations, software and(67), can have an effect on its overall efficiency. To maintain control, you need the tools and knowledge to manage all activity that has the potential to affect your(68).A.seeB.knowC.monitorD.control

考题 management includes negotiating the terms and conditions in contracts and ensuring compliance with the terms and conditions,as well as documenting and agreeing on any changes or amendments that may arise during its implementation or executionA.ContractB.DocumentC.CommunicationD.Risk

考题 What are the characteristics of the process of documenting the layers of an existing network? () A. begins with gathering organizational input that may be inaccurateB. begins with gathering organizational input that does not need to be supplemented by a network auditC. requires a network audit to support some upgrade decisionsD. requires a network audit to support any network restructuringE. provides reliable input for verifying network consistencyF. does not provide reliable input for designing changes

考题 During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised(75)are necessary.A.proceedingsB.controlsC.forecasting'sD.prelibations

考题 In the last paragraph,the author mainly intends toA.list the necessary changes we ought to makeB.advise US to make any necessary changesC.explain what changes can bringD. explain the process of making changes

考题 A salvor ______ the payment due thereunder to the extent that the salvage operations have become necessary or more difficult because of fault or neglect on his part.A.may be deprived of the whole or part ofB.may not be deprived of any part ofC.will only be rewardedD.will not be rewarded any part of

考题 ( ) management includes negotiating the terms and conditions in contracts and ensuring compliance with. the terms and conditions, as well as documenting and agreeing on any changes or amendments that may arise during its implementation or execution. A.Contract B.Document C.Communication D.Risk

考题 资料:From: Iris Wu To: Tim Appleby Subject: Marketing issues Date:May 3 Hi Tim,Can you schedule a conference call for all our marketing directors, me included, to discuss the launch of the new appliance line? Please note that our offices in the Philippines and France are respectively, twelve and six hours ahead of us. Threfore, kindly remind the directors that the call may have to occur outside of business hours. The meeting should be arranged before the new product presentations on May 26. I recommend scheduling the call on May 14 or 15 to allow sufficient time for the appliance information charts to be updated with any suggested changes. Should a different date be more convenient for the other directors, please check with me to confirm my availability? Thank you Iris When are presentations scheduled?A.on May 3 B.on May 14 C.on May 15 D.on May 26

考题 Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by ( ) . A.executive IT manager B.project manger C.change control board D.project sponsor

考题 Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by ( ) .A.executive IT manager B.project manger C.change control board D.project sponsor

考题 The committee is totally opposed ______any changes being made in the plans.A.of B.on C.to D.against

考题 Which the statement is true?()A、 The Error class is a Runtime Exception.B、 No exceptions are subclasses of Error.C、 Any statement that may throw an Error must be enclosed in a try block.D、 any statement that may throw an Exception must be enclosed in a try block.E、 Any statement that may throw an Runtime Exception must be enclosed in a try block.

考题 Which statement correctly describes the change tracking writer (CTWR) background process?()A、 It keeps track of changes in the background processes.B、 It records the system change number (SCN) in the control file.C、 It writes audit records for user changes to the change tracking file.D、 It records any changes to the listened configuration in the listener.ora file.E、 It records any changes to the database parameters in the change tracking file.F、 It records the physical location of all the changes that are made to the database in the change tracking file.

考题 What are the characteristics of the process of documenting the layers of an existing network? ()A、begins with gathering organizational input that may be inaccurateB、begins with gathering organizational input that does not need to be supplemented by a network auditC、requires a network audit to support some upgrade decisionsD、requires a network audit to support any network restructuringE、provides reliable input for verifying network consistencyF、does not provide reliable input for designing changes

考题 多选题What are the characteristics of the process of documenting the layers of an existing network? ()Abegins with gathering organizational input that may be inaccurateBbegins with gathering organizational input that does not need to be supplemented by a network auditCrequires a network audit to support some upgrade decisionsDrequires a network audit to support any network restructuringEprovides reliable input for verifying network consistencyFdoes not provide reliable input for designing changes

考题 单选题Which the statement is true?()A  The Error class is a Runtime Exception.B  No exceptions are subclasses of Error.C  Any statement that may throw an Error must be enclosed in a try block.D  any statement that may throw an Exception must be enclosed in a try block.E  Any statement that may throw an Runtime Exception must be enclosed in a try block.

考题 单选题Outbreak of small-arms fire along the frontier became more frequent in May but _____ officially investigated.A hardly any such incidents wereB hardly were any such incidentsC hardly were such any incidentsD hardly such any incidents were

考题 单选题Inductance is the property of an electric circuit that ()A opposes any change in the applied voltageB opposes any change in the current flow through the circuitC aids any changes in the applied voltageD aids any changes in the current through the circuit

考题 单选题Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()A executive IT managerB projectmangerC change control boardD projectsponsor

考题 单选题During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised()are necessary.A proceedingsB controlsC forecastingsD Prelibations

考题 单选题It's no use _____ any longer, He may come by any bus.A waitingB to waitC having waitedD to have waited

考题 单选题An operational amplifier, as used in todays consoles, may have a calculated gain of 5√This means that as the input changes by ()A 1 volt, the output changes 5 voltsB 5 volts, the output changes 1 voltC 5 volts, the output changes 10 voltsD 10 volts, the output changes 5 volts

考题 单选题The committee is totally opposed _____any changes being made in the plans.A ofB onC toD against