网友您好, 请在下方输入框内输入要搜索的题目:

题目内容 (请给出正确答案)

2 The Work Breakdown Structure (WBS) is the basis for communicating:

A. Project scope, cost control, schedule, quality

B. Project objectives, dependencies, plan, cost control

C. Project scope, schedule, staffing, cost control

D. Project scope, quality, schedule, dependencies

E. Project budget, schedule, risk factors, work assignments


参考答案

更多 “ 2 The Work Breakdown Structure (WBS) is the basis for communicating:A. Project scope, cost control, schedule, qualityB. Project objectives, dependencies, plan, cost controlC. Project scope, schedule, staffing, cost controlD. Project scope, quality, schedule, dependenciesE. Project budget, schedule, risk factors, work assignments ” 相关考题
考题 Project trade-offs vary betweenA . risk, cost and schedule.B . direct cost, indirect cost, and resource availabilityC . quality, schedule and timeD . cost, quality and scheduleE . contract terms, scope and budget

考题 The scope of a project can be expected to change if:A.The project manager must provide cost estimates without having a design conceptB.Oversimplification (underestimating) of the nature of the work occursC.The project manager is assigned after the project is defined, and the cost and schedule are approvedD.A clear objective is not providedE.All of the above are possible based upon the situation

考题 The Work Breakdown Structure (WBS) is the basis for communicating:A.Project scope, cost control, schedule, qualityB.Project objectives, dependencies, plan, cost controlC.Project scope, schedule, staffing, cost controlD.Project scope, quality, schedule, dependenciesE.Project budget, schedule, risk factors, work assignments.

考题 Scope management is:A.a project control function.B.employs change control.C.a work authorization process.D.considers Cost, Quality and Schedule.E.All of the above.

考题 The most effective means of determining the cost of a project is to price out the _____.A . Work breakdown structure.B . Linear responsibility chart.C . Project charter.D . Scope statement.E . Management plan.

考题 198 The most effective means of determining the cost of a project is to price out the _____.A. Work breakdown structure.B. Linear responsibility chart.C. Project charter.D. Scope statement.E. Management plan

考题 99 Scope management is:A. a project control function.B. employs change control.C. a work authorization process.D. considers Cost, Quality and Schedule.E. All of the above

考题 120 The Work Breakdown Structure (WBS) is the basis for communicating:A. Project scope, cost control, schedule, qualityB. Project objectives, dependencies, plan, cost controlC. Project scope, schedule, staffing, cost controlD. Project scope, quality, schedule, dependenciesE. Project budget, schedule, risk factors, work assignments

考题 130 What is the relative priority of project Cost, Schedule and Quality?A. 1)Cost - 2)Schedule - 3)QualityB. 1)Quality - 2)Schedule - 3)CostC. 1)Quality - 2)Cost - 3)ScheduleD. 1)Schedule - 2)Quality - 3)CostE. All are of equal priority

考题 41 The scope of a project can be expected to change if:A. The project manager must provide cost estimates without having a design concept B. Oversimplification (underestimating) of the nature of the work occursC. The project manager is assigned after the project is defined, and the cost and schedule are approvedD. A clear objective is not providedE. All of the above are possible based upon the situation

考题 72 Project trade-offs vary betweenA. risk, cost and schedule.B. direct cost, indirect cost, and resource availabilityC. quality, schedule and timeD. cost, quality and scheduleE. contract terms, scope and budget

考题 123 The scope of a project can be expected to change if:A. The project manager must provide cost estimates without having a design concept B. Oversimplification (underestimating) of the nature of the work occursC. The project manager is assigned after the project is defined, and the cost and schedule are approved D. A clear objective is not providedE. All of the above are possible based upon the situation

考题 ● The scope of a project can be expected to change if:A The project manager must provide cost estimates without having a design conceptB Oversimplification (underestimating) of the nature of the work occursC The project manager is assigned after the project is defined, and the cost and schedule are approvedD A clear objective is not providedE All of the above are possible based upon the situation

考题 ● The Work Breakdown Structure (WBS) is the basis for communicating:A Project scope, cost control, schedule, qualityB Project objectives, dependencies, plan, cost controlC Project scope, schedule, staffing, cost controlD Project scope, quality, schedule, dependenciesE Project budget, schedule, risk factors, work assignments.

考题 ● Scope management is:A a project control function.B employs change control.C a work authorization process.D considers Cost, Quality and Schedule.E All of the above.

考题 ●(71)assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame. and risk tolerance of the project constraints of cost, schedule, scope, and quality.(71)A. Quantitative Risk AnalysisB. Qualitative Risk AnalysisC. Enterprise Environmental FactorsD. Risk Management Plan

考题 ______assesses the priority of identified ri sks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame. and risk tolerance of the project constraints of cost,schedule,scope,and quality.A.Quantitative Risk AnalysisB.Qualitative Risk AnalysisC.Enterprise Environmental FactorsD.Risk Management Plan

考题 The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned

考题 The( )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables. A、project scope statementB、work packageC、WBSD、project scope plan

考题 The earned value technique is a commonlyused method of performance measurement. It integrates project scope, cost, andschedule measures to help the project management team assess projectperformance.If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, itmeans that (74).A.the project is ahead of its planned scheduleB.less work was completed than was plannedC.the cost overrun for work completedD.the cost under-run of performance to date

考题 The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than1.0, it means that_().A.the project is a head of its planned schedule B.less work was completed than was planned C.the cost overrun for work completed D.the cost under-run of performance to date

考题 ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.A:Create scopE B:Project stakeholder management C:Project scope management D:Project cost management

考题 An example of scope verification is ( ).A.review the performance of an installed software module B.managing changes to the project schedule C.decomposing the WBS to a work package level D.performing a benefit/cost analysis to determine if we should proceeD.with the project

考题 Estimating schedule activity costs involves developing an approximation of the costs of theresources needed to complete each schedule activity. Cost estimating includes identifying andconsidering various costing alternatives. For example, in most application areas, additional workduring a design phase is widely held to have the potential for reducing the cost of the executionphase and product operations. The cost estimating process considers whether the expectedsavings can offset the cost of the A.project scope statement B.statement of work C.project management plan D.project policy

考题 The()is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.A.Project scope statement B.Work package C.WBS D.Project scope plan

考题 ( ) Assesses the priority of identified risks using their probability of occurring,the corresponding impact on project objectives if the risks do occur,as well as other factors such as the time frame and risk tolerance of the project constraints of cost,schedule,scope,and quality. A.Quantitative Risk Analysis B.Qualitative Risk Analysis C.Enterprise Environmental Factors D.Risk Management Plan

考题 ()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.A、Quantitative Risk AnalysisB、Qualitative Risk AnalysisC、Enterprise Environmental FactorsD、Risk Management Plan