An example of scope verification is ( ).

A.review the performance of an installed software module
B.managing changes to the project schedule
C.decomposing the WBS to a work package level
D.performing a benefit/cost analysis to determine if we should proceeD.with the project

参考答案

参考解析
解析:范围验证的一个示例是查看已安装的软件模块的性能。A.查看已安装的软件模块的性能 B.项目进度变更管理 C.分解到工作包级别WBS D.执行成本/效益分析,以确定是否我们应该继续进行项目
更多 “An example of scope verification is ( ).A.review the performance of an installed software module B.managing changes to the project schedule C.decomposing the WBS to a work package level D.performing a benefit/cost analysis to determine if we should proceeD.with the project ” 相关考题
考题 Which of the following is not a scope management process?A . InitiationB . Scope planningC . Scope DefinitionD . Scope change controlE . Scope verification

考题 In which of the following scope management processes is the scope management plan prepared?A . InitiationB . Scope planningC . Scope DefinitionD . Scope change controlE . Scope verification

考题 The project charter is prepared in which scope management process?A . InitiationB . Scope planningC . Scope DefinitionD . Scope change controlE . Scope verification

考题 The work breakdown structure (WBS) is first developed in which scope management process?A . InitiationB . Scope planningC . Scope change controlD . Scope DefinitionE . Scope verification

考题 In which of the following scope management processes are subject matter experts used?A . InitiationB . Scope planningC . Scope DefinitionD . Scope change controlE . Scope verification

考题 The scope statement providesA . A basis for future decisions about a project.B . A baseline to accomplish verification measures.C . A baseline to evaluate potential scope changes.D . All of the aboveE . B and C only

考题 The scope management provides:A.A basis for future decisions about the project.B.A baseline to accomplish verification measures.C.A baseline to evaluate potential scope changes.D.All of the above.E.B and C only.

考题 QUESTThe scope baseline once established and approved, is used:A.as the basis for making future decisions.B.to accomplish verification measures.C.to evaluate potential changes.D.All of the above.E.A and C only.

考题 Which of the following actions is an example of risk response:A adjust project parameters (scope, time, quality ...)B reduce the probability of potential project risk eventsC reduce the consequences of potential project risk eventsD wait until a problem actually happens, then deal with it in the most effective and efficient manner.E A, B and C only

考题 139 The scope baseline once established and approved, is used:A. as the basis for making future decisions.B. to accomplish verification measures.C. to evaluate potential changes.D. All of the above.E. A and C only

考题 105 Which of the following actions is an example of risk response:A. adjust project parameters (scope, time, quality ...)B. reduce the probability of potential project risk eventsC. reduce the consequences of potential project risk eventsD. wait until a problem actually happens, then deal with it in the most effective and efficient manner.E. A, B and C only

考题 88 The scope statement providesA. A basis for future decisions about a project.B. A baseline to accomplish verification measures.C. A baseline to evaluate potential scope changes.D. All of the aboveE. B and C only

考题 140 In which of the following scope management processes are subject matter experts used? A. InitiationB. Scope planningC. Scope DefinitionD. Scope change controlE. Scope verification

考题 141 The work breakdown structure (WBS) is first developed in which scope management process? A. InitiationB. Scope planningC. Scope change controlD. Scope DefinitionE. Scope verification

考题 142 The project charter is prepared in which scope management process?A. InitiationB. Scope planningC. Scope DefinitionD. Scope change controlE. Scope verification

考题 143 In which of the following scope management processes is the scope management plan prepared?A. InitiationB. Scope planningC. Scope DefinitionD. Scope change controlE. Scope verification

考题 144 Which of the following is not a scope management process?A. InitiationB. Scope planningC. Scope DefinitionD. Scope change controlE. Scope verification

考题 23 The work breakdown structure (WBS) is first developed in which scope management process? A. InitiationB. Scope planningC. Scope change controlD. ScopeDefinitionE. Scope verification

考题 ● The scope baseline once established and approved, is used:A as the basis for making future decisions.B to accomplish verification measures.C to evaluate potential changes.D All of the above.E A and C only.

考题 is the process of obtaining the stakeholdrs'formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A.WBS CreationB.Scope definitionC.Project acceptanceD.Scope verification

考题 An example of scope verification is __(73)__ .A.review the performance of an installed software moduleB.managing changes to the project scheduleC.decomposing the WBS to a work package levelD.performing a benefit/cost analysis to determine if we should proceed with the project

考题 Which of following is an important input to scope verification? ()A.Work results B.Historical information C.Formal acceptance D.Change request

考题 Which of the following Project Scope Management processes involves subdividing the major projectdeliverablesinto smaller, more manageable components)()A.Scope Planning B.Scope Verification C.Scope Change Control D.Scope Definition

考题 () is the process of obtaining the stakeholders\' formal acceptance of thecompleted project scope. Verifying the scope includes reviewing deliverables and work results toensure that all were completed satisfactorily. A.Project acceptance B.Scope verification C.Scope definition D.WBS Creation

考题 给定TheBean类,假设还没有创建TheBean类的实例,以下哪些JSP标准动作语句能创建这个bean的一个新实例,并把它存储在请求作用域?()A、〈jsp:useBean name="myBean" type="com.example.TheBean"/〉B、〈jsp:takeBean name="myBean" type="com.example.TheBean"/〉C、〈jsp:useBean id="myBean" class="com.example.TheBean" scope="request"/〉D、〈jsp:takeBean id="myBean" class="com.example.TheBean" scope="request"/〉

考题 单选题给定TheBean类,假设还没有创建TheBean类的实例,以下哪些JSP标准动作语句能创建这个bean的一个新实例,并把它存储在请求作用域?()A 〈jsp:useBean name=myBean type=com.example.TheBean/〉B 〈jsp:takeBean name=myBean type=com.example.TheBean/〉C 〈jsp:useBean id=myBean class=com.example.TheBean scope=request/〉D 〈jsp:takeBean id=myBean class=com.example.TheBean scope=request/〉

考题 单选题An example of scope verification is ().A review the performance ofan installed software moduleB managing changes to the project scheduleC decomposing the WBS to a work package levelD performing a benefit/cost analysis to determine if we should proceed with the project