The()is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.

A.Project scope statement
B.Work package
C.WBS
D.Project scope plan

参考答案

参考解析
解析:()是项目团队为完成项目目标和创建所需可交付成果而执行的整个工作范围的分层分解。
A.项目范围说明书B.工作包C.WBS?D.项目范围计划
更多 “The()is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.A.Project scope statement B.Work package C.WBS D.Project scope plan” 相关考题
考题 The Work Breakdown Structure (WBS) is the basis for communicating:A.Project scope, cost control, schedule, qualityB.Project objectives, dependencies, plan, cost controlC.Project scope, schedule, staffing, cost controlD.Project scope, quality, schedule, dependenciesE.Project budget, schedule, risk factors, work assignments.

考题 The()describes, in detail, the project's deliverables and the work required to create those deliverables. A.project scope statementB.project requirementC.project charterD.product specification

考题 ● The Work Breakdown Structure (WBS) is the basis for communicating:A Project scope, cost control, schedule, qualityB Project objectives, dependencies, plan, cost controlC Project scope, schedule, staffing, cost controlD Project scope, quality, schedule, dependenciesE Project budget, schedule, risk factors, work assignments.

考题 ●(74) describes, in detail, the project' s deliverables and the work required to create those deliverables.(74) A. Product scope descriptionB. Project objectivesC. Product specificationD. The project scope statement

考题 ( ) describes, in detail, the project s deliverables and the work required to create those deliverables.A.Product scope description B.Project objectives C.Product specification D.The project scope statement

考题 The project()is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteriaA.work performance informationB.scope statementC.change requestsD.process analysis

考题 The(71)describes,in detail,the project's deliverables and the work required to create those deliverables.A.project scope statementB.project requirementC.project charterD.product specification

考题 A project management technique that is currently in widespread use is the(71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives. There are some special activities called(72) , which are events that signify the accomplishment or completion of major deliverables during the project. Most system development methodologies also provide(73), whose purpose is to contain the various pieces of relevant information-feasibility assessments, schedules, needs analysis, and so forth-in a single place so that they can be presented to project clients and other related parties. Several types of important network diagrams are used in project management.(74) was developed to make clear the interdependence between project tasks before those tasks are scheduled.(75) offers the advantage of clearly showing overlapping tasks.A.Structure ChartB.Organizational StructureC.Work Breakdown StructureD.Functional decomposition diagram

考题 ______describes,in detail,the project's deliverables and the work required to create those deliverables.A.Product scope descriptionB.Project objectivesC.Stakeholder AnalysisD.The project scope statement

考题 A project management technique that is currently in widespread use is the (73). The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.A.Structure ChartB.Organizational StructureC.Work Breakdown StructureD.Functional decomposition diagram

考题 The( )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables. A、project scope statementB、work packageC、WBSD、project scope plan

考题 During planning you sit down and estimate the time needed for each task and total them to come up with the project estimate This duration is what you commit to complete the project. What is wrong with the scenario? ()A.The team did not create the estimate and estimating tales too long using that methodB.The team did not create the estimate and a network diagram was not usedC.The estimate is too long and should be created by managementD.The project estimate should be the same as the customer's required completion date

考题 The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.A.project charterB.project scope goalC.project budgetD.project scope statement

考题 The ()describes, in detail, the project’s deliverables and the work required to create those deliverables.A.project scope statement B.project requirement C.project charter D.product specification

考题 A project management technique that is currently in widespread use is the ( ) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives.A.Functional decomposition diagram B.Work Breakdown Structure C.Structure Chart D.Organizational Structure

考题 ()describees,indetail,the project's deliverables and the work required to create those deliverables. A.Product scope description B.Project objectives C.Produce specification D.The project scope statement

考题 he work breakdown structure comprises several levels of decomposition of the total project. The lowest level of definition is always the()A.Planning element B.Work package C.Subtask D.Working interface

考题 The work breakdown structure comprises several levels of decomposition of the total project.The lowest level of definition is always the ( ) .A.planning B.element C.subtask D.working interface

考题 ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.A:Create scopE B:Project stakeholder management C:Project scope management D:Project cost management

考题 ( ) describes,in detail,the project’s deliverables and the work required to create those deliverables. A.Product scope description B.Project objectives C.Stakeholder Analysis D.The project scope statement

考题 The scope management plan is how the team will prepare the( )a document that includes descriptions of create the WBS,verify completion of the project deliverables,and control requests for changes to the project scope. A.project charter B.project scope goal C.project budget D.project scope statement

考题 ()includes the processes required to ensure that the project includes all the work required,and only the work required,to compete the project successfully.Managing the project scope is primarily concerned with defining and controlling what is not included in the project.A. Create scopE B. Project stakeholder management C. Project scope management D. Project cost management

考题 The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.A、work performance informationB、scope statementC、changerequestsD、process analysis

考题 ()describes, in detail, the project’s deliverables and the work required to create those deliverables.A、Product scope descriptionB、Project objectivesC、Stakeholder AnalysisD、The project scope statement

考题 The () describes, in detail, the project's deliverables and the work required to create those deliverables.A、project scope statementB、project requirementC、project charterD、product specification

考题 单选题The()describes, in detail, the project's deliverables and the work required to create those deliverables.A project scope statementB project requirementC project charterD product specification

考题 单选题()describes, in detail, the project’s deliverables and the work required to create those deliverables.A Product scope descriptionB Project objectivesC Stakeholder AnalysisD The project scope statement