网友您好, 请在下方输入框内输入要搜索的题目:

题目内容 (请给出正确答案)

A contractor estimates that a project has a 0.5 probability of $200,000 profit and 0.3 probability of $50,000 loss. The expected monetary value of this project is:

A ¥200,000

B ¥150,000

C ¥85,000

D ¥50,000

E None of the above.


参考答案

更多 “ A contractor estimates that a project has a 0.5 probability of $200,000 profit and 0.3 probability of $50,000 loss. The expected monetary value of this project is:A ¥200,000B ¥150,000C ¥85,000D ¥50,000E None of the above. ” 相关考题
考题 The project charter is developed by:A.senior managementB.the customerC.the project managerD.both A and CE.None of the above.

考题 Including the customer in the process of project planning is:A.Slow and counterproductive.B.Essential in the definition and documentation of project goals.C.Necessary, but of limited value.D.Unnecessary because project goals are defined in the proposal stage.E.None of the above.

考题 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:A . Baseline costsB . Budgeted costs.C . Estimates upon completion costsD . Scheduled costsE . None of the above

考题 During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:A . The project will be completed late.B . The critical path has been lengthened.C . the costs are being overrun.D . Overtime will be required to maintain the original critical path.E . None of the above.

考题 A variance envelope has been established on a project. The envelope goes from +-30% in RD to +-5% during manufacturing. The reason for the change in thickness of the envelope is because:A . The management reserve has been used up.B . The accuracy of the estimates in manufacturing are worse than the estimates in R D.C . Tighter controls are always needed as a project begins to wind down.D . Of the personal desires of the project sponsor.E . Of none of the above

考题 Quality control is normally performed by the _____ .A . QA personnelB . project teamC . operating personnelD . project managementE . None of the above.

考题 The purpose of project Risk Management is to:A Identify those factors that will adversely impact project objectives.B Assess the impact of adverse project factors.C Assess the probability of adverse project factors.D A and CE All of the above.

考题 Using the figure in the Special Window, what is the probability of success for Project B?A 0.3B 0.2C 0.35D 0.15E 0.12

考题 In Project Risk Management, Risk Response may include actions to:A reduce the probability of risk eventsB change the scope, budget, schedule or quality specifications of the projectC reduce the consequences or severity of impacts of a potential risk eventD A and CE All of the above.

考题 Total Project Risk:A should not be calculated for small projectsB is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.C Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.D A and BE A and C

考题 The type of contract (payment mechanism) chosen for a project is often a reflection of the degree of risk associated with completing that project. For a firm fixed price contract, payment for risk _____ .A Is accomplished by paying the actual costs to the contractor.B Is accomplished by paying the contractor for his costs plus a fixed fee (profit).C Is an undisclosed contingency in the contractor's bid.D Is accomplished by paying for the budgeted costs of dealing with risks, as predicted in the project risk assessment.E B and C

考题 To calculate the expected value of an outcome:A divide the value of each outcome by its probability, then add the results.B divide the value of the desired outcome by the value all possible outcomesC multiply the value of each outcome by its probability, then add the resultsD use linear regression to assess the expected value of the outcomeE B and D only

考题 By which means is a contractor able to control cost overruns due to changing requirements?A Project data reviewB Change orderC Purchase order amendmentD Change controlE None of the above.

考题 141 To calculate the expected value of an outcome:A. divide the value of each outcome by its probability, then add the results.B. divide the value of the desired outcome by the value all possible outcomesC. multiply the value of each outcome by its probability, then add the resultsD. use linear regression to assess the expected value of the outcomeE. B and D only

考题 52 A contractor estimates that a project has a 0.5 probability of $200,000 profit and 0.3 probability of $50,000 loss. The expected monetary value of this project is:A. $200,000B. $150,000C. $85,000D. $50,000E. None of the above

考题 85 The purpose of project Risk Management is to:A. Identify those factors that will adversely impact project objectives.B. Assess the impact of adverse project factors.C. Assess the probability of adverse project factors.D. A and CE. All of the above

考题 93 The type of contract (payment mechanism) chosen for a project is often a reflection of the degree of risk associated with completing that project. For a firm fixed price contract, payment for risk _____ .A. Is accomplished by paying the actual costs to the contractor.B. Is accomplished by paying the contractor for his costs plus a fixed fee (profit).C. Is an undisclosed contingency in the contractor's bid.D. Is accomplished by paying for the budgeted costs of dealing with risks, as predicted in the project risk assessment.E. B and C

考题 122 Total Project Risk:A. should not be calculated for small projectsB. is the probability of each project risk event times the sum of the consequences of individual project risk events which could occur during the project.C. Is the cumulative sum of the probability of each individual project risk event times the consequences of occurrence of that risk event.D. A and BE. A and C

考题 You are working on the cost budget for one project. Which of the following is true() A.This process assigns cost estimates to project activities including risks and contingency plans.B.The cost baseline will be used to measure variances and future project performance.C.This process assigns cost estimates for expected future period operating costs.D.The cost baseline is the expected cost for the project.

考题 ● The project charter is developed by:A senior managementB the customerC the project managerD both A and CE None of the above.

考题 ● Including the customer in the process of project planning is:A Slow and counterproductive.B Essential in the definition and documentation of project goals.C Necessary, but of limited value.D Unnecessary because project goals are defined in the proposal stage.E None of the above.

考题 某企业“长期肌权投资--F公司”采用成本法核算。在发生投资的当年,收到F公司派发的现金股利200,000元,而当年企业应享有的F公司的投资收益为150,000元,则企业应编制的会计分录为借记“银行存款”200,000元()。A、贷记“投资收益”200,000元B、贷记“长期股权投资”200,000元C、贷记“投资收益”150,000元,“长期股权投资”50,000元D、贷记“投资收益”50,000元,“长期股权投资”150,000元

考题 You are working on the cost budget for one project. Which of the following is true()A、This process assigns cost estimates to project activities including risks and contingency plans.B、The cost baseline will be used to measure variances and future project performance.C、This process assigns cost estimates for expected future period operating costs.D、The cost baseline is the expected cost for the project.

考题 If the organizational spending plan has allocated $100,000 for a project, and the high level budget estimate for that project is $200,000; which of the following is accurate?()A、The high level budget estimates are inaccurateB、The organizational spending plan is inaccurateC、The budget is not aligned with the spending plan of the organizationD、The detailed bottom up budget will need to be adjusted

考题 单选题If the organizational spending plan has allocated $100,000 for a project, and the high level budget estimate for that project is $200,000; which of the following is accurate?()A The high level budget estimates are inaccurateB The organizational spending plan is inaccurateC The budget is not aligned with the spending plan of the organizationD The detailed bottom up budget will need to be adjusted

考题 单选题某企业“长期肌权投资--F公司”采用成本法核算。在发生投资的当年,收到F公司派发的现金股利200,000元,而当年企业应享有的F公司的投资收益为150,000元,则企业应编制的会计分录为借记“银行存款”200,000元()。A 贷记“投资收益”200,000元B 贷记“长期股权投资”200,000元C 贷记“投资收益”150,000元,“长期股权投资”50,000元D 贷记“投资收益”50,000元,“长期股权投资”150,000元

考题 单选题You are working on the cost budget for one project. Which of the following is true()A This process assigns cost estimates to project activities including risks and contingency plans.B The cost baseline will be used to measure variances and future project performance.C This process assigns cost estimates for expected future period operating costs.D The cost baseline is the expected cost for the project.