网友您好, 请在下方输入框内输入要搜索的题目:

题目内容 (请给出正确答案)
Much of the effort cost control involves analyzing the relationship between the consumption of project funds and the work being accomplished for such expenditures . The key to effective cost control is the management of the approved ( ) .

A.Schedule baseline
B.Cost baseline
C.Cost output
D.Cost input

参考答案

参考解析
解析:解析:翻译:成本控制的大部分工作涉及分析项目资金消耗与这些支出所完成工作之间的关系。有效成本控制的关键是管理批准的( )。A.进度基准B.成本基准C.成本输出D.成本输入
更多 “Much of the effort cost control involves analyzing the relationship between the consumption of project funds and the work being accomplished for such expenditures . The key to effective cost control is the management of the approved ( ) .A.Schedule baseline B.Cost baseline C.Cost output D.Cost input ” 相关考题
考题 The Work Breakdown Structure (WBS) is the basis for communicating:A.Project scope, cost control, schedule, qualityB.Project objectives, dependencies, plan, cost controlC.Project scope, schedule, staffing, cost controlD.Project scope, quality, schedule, dependenciesE.Project budget, schedule, risk factors, work assignments.

考题 Scope management is:A.a project control function.B.employs change control.C.a work authorization process.D.considers Cost, Quality and Schedule.E.All of the above.

考题 The most effective means of determining the cost of a project is to price out the _____.A . Work breakdown structure.B . Linear responsibility chart.C . Project charter.D . Scope statement.E . Management plan.

考题 Cost management includes:A . Cost estimating/forecasting.B . Cost budgeting/cost control.C . Cost applications.D . All of the above.E . A and B only.

考题 In performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:A Work breakdown structureB milestone review and schedule techniqueC cost/schedule control systemD planning programming budget systemE program and evaluation review technique

考题 By which means is a contractor able to control cost overruns due to changing requirements?A Project data reviewB Change orderC Purchase order amendmentD Change controlE None of the above.

考题 198 The most effective means of determining the cost of a project is to price out the _____.A. Work breakdown structure.B. Linear responsibility chart.C. Project charter.D. Scope statement.E. Management plan

考题 178 In performing an impact analysis, the most effective tool to ensure all risks are identified on large projects is the:A. Work breakdown structureB. milestone review and schedule techniqueC. cost/schedule control systemD. planning programming budget systemE. program and evaluation review technique

考题 ● The Work Breakdown Structure (WBS) is the basis for communicating:A Project scope, cost control, schedule, qualityB Project objectives, dependencies, plan, cost controlC Project scope, schedule, staffing, cost controlD Project scope, quality, schedule, dependenciesE Project budget, schedule, risk factors, work assignments.

考题 ● Scope management is:A a project control function.B employs change control.C a work authorization process.D considers Cost, Quality and Schedule.E All of the above.

考题 Estimating schedule activity costs involves developing an(69)of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estimates are generally expressed in units of(70)to facilitate comparisons both within and across projects.The(71 )describes the business need, justification, requirements, and current boundaries for the project. It provides important information about project requirements that is considered during cost estimating.A.accuracyB.approximationC.specificationD.summary

考题 The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned

考题 “Cost of quality”is a project management concept that includes cost of( 73)A.exceedings requirementsB.Changes to the requirementsC.Ensuring conformance to requirementsD.The quality control requirements

考题 The key benefit of ( )is that it provides guidance and direction on how the project costs will be managed throughout the project.A.Plan Cost ManagementB.Control CostC.Estimate CostD.Determine Budget

考题 Estimating schedule activity costs involves developing an(4)of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in mostapplication areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estmates are generally expressed in units of(5)to facilitate comparisions both within and across projects. The(6)describes important information about project requirement that is considered during cost estimating.A.accuracyB.approxinationC.specificationD.summary

考题 The (74) technique involves using project characteristics in a mathematical model to predict total project cost models Can be simple or complex.A.reserve analysisB.cost aggregationC.parametric estimatingD.funding limit reconciliation

考题 The difference value between Budgeted Cost for work Performed and Actual Cost for Work Performed is( ).A.Cost Variance B.Schedule Variance C.Earned Value D.Cost Performed Index

考题 ( )is the approved version of the time-phased project budget,excluding any management reserves,which can only be changed through formal change control precedures and is used as a basis for comparison to actual results.A.The control accountsB.Funding requirementC.The cost estimatesD.The cost baseline

考题 ( )is a process of monitoring the status of the project to update the project costs and manage changes is the cost baseline.A.Plan Cost Management B.Estimate Costs C.Determine Budget D.Control costs

考题 The key benefit of( )is that it provides guidance and direction on how the project costs will be managed throughout the project.A.Plan Cost Management B.Control Cost C. Estimate Cost D. Determine Budget

考题 Estimating schedule activity costs involves developing an approximation of the costs of theresources needed to complete each schedule activity. Cost estimating includes identifying andconsidering various costing alternatives. For example, in most application areas, additional workduring a design phase is widely held to have the potential for reducing the cost of the executionphase and product operations. The cost estimating process considers whether the expectedsavings can offset the cost of the A.project scope statement B.statement of work C.project management plan D.project policy

考题 The difference value between Budgeted Cost for Work Performed and Actual Cost for Work Performed is ( ). A.Cost Variance B.Schedule Variance C.EarneD.Value D.Cost PerformeD.Index

考题 Estimating schedule activity costs involves developing an (1) of the cost of theresources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in most application areas, additionalwork during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estimates are generally expressed in units of (2) to facilitate comparisons both within and across projects.the (3) describes important information about project requirement that is considered during cost estimating. 空白(3)处填()A、project scope statementB、statement of workC、project management planD、projectpolicy

考题 Saving or reducing expenditure in business is () A、Save money B、Increase costC、cost planningD、cost control

考题 英译中:Cost control

考题 Saving or reducing expenditure in business is()A、save moneyB、increase costC、cost planningD、cost control

考题 Zero stock is the best way for()A、cost controlB、inventory controlC、storage cost controlD、warehouse cost control