( )is the approved version of the time-phased project budget,excluding any management reserves,which can only be changed through formal change control precedures and is used as a basis for comparison to actual results.

A.The control accounts

B.Funding requirement

C.The cost estimates

D.The cost baseline


参考答案

更多 “ ( )is the approved version of the time-phased project budget,excluding any management reserves,which can only be changed through formal change control precedures and is used as a basis for comparison to actual results.A.The control accountsB.Funding requirementC.The cost estimatesD.The cost baseline ” 相关考题
考题 The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.A . budget, scheduleB . quality requirements, scheduleC . size, type of industryD . nature, sizeE . project manager, sponsor

考题 A comprehensive definition of scope management would be:A.Managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.B.Approval of the scope baseline.C.Approval of the detailed project charter.D.Configuration control.E.Approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.

考题 Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.A . Increase, increase.B . Increase, decrease.C . Decrease, decrease.D . Decrease, increase.E . Remain the same, return to customer.

考题 The major difference between project and line management is that the project manager may not have any control over which basic management function?A . Decision-makingB . StaffingC . RewardingD . Tracking/monitoringE . Reviewing

考题 A negative cost variance and positive schedule variance means:A The project is under budget and ahead of scheduleB The project is over budget and behind scheduleC The project is over budget and ahead of scheduleD The project will be overrun but ahead of schedule at completion

考题 6 Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.A. Increase, increase.B. Increase, decrease.C. Decrease, decrease.D. Decrease, increase.E. Remain the same, return to customer

考题 78 The major difference between project and line management is that the project manager may not have any control over which basic management function?A. Decision-makingB. StaffingC. RewardingD. Tracking/monitoringE. Reviewing

考题 69 The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.A. budget, scheduleB. quality requirements, scheduleC. size, type of industryD. nature, sizeE. project manager, sponsor

考题 96 A negative cost variance and positive schedule variance means:A. The project is under budget and ahead of scheduleB. The project is over budget and behind scheduleC. The project is over budget and ahead of scheduleD. The project will be overrun but ahead of schedule at completion

考题 Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool. A.RationalClearcaseB.QualityFunctionDeploymentC.VisualSourceSafeD.ConcurrentVersions System

考题 ● A comprehensive definition of scope management would be:A Managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.B Approval of the scope baseline.C Approval of the detailed project charter.D Configuration control.E Approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.

考题 ●The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope.(74) could provide the fund to cover the newly discovered work item.(74) A. Contingency reserveB. Project profitC. Management reserveD. Special fund

考题 Murphys Law suggests, If anything can go wrong, it will. Murphy has motivated numerous pearls of wisdom about projects; machines, people, and why things go wrong. A project is a [temporary] sequence of unique, complex, and connected( )having one goal or purpose and that must be completed by a specific time, within budget, and according to ( ).Project management is the( )of scoping, planning, staffing, organizing, directing, and controlling the development of an acceptable information system at a minimum cost within a specified time frame. Project management is a cross life cycle activity because it overlaps all phases of any systems development methodology. For any systems development project, effective project management is necessary to ensure that the project meets the deadline, is developed within a (an) ( )budget, and fulfills customer expectations and specifications. Corporate rightsizing has changed the structure and culture of most organizations, and hence, project management. More flexible and temporary interdepartmental(不同部门间)teams that are given greater responsibility and authority for the success of organizations have replaced rigid hierarchical command structures and permanent teams. Contemporary system development methodologies depend on having teams that include both technical and nontechnical users, managers, and information technologists all directed to the project goal. These( )teams require leadership and project management.A.activities B.tasks C.services D.softwareA.document B.order C.specification D.authorityA.process B.activity C.step D.taskA.predefined B.acceptable C.rigid D.StrictA.invariable B.fixed C.permanent D.dynamic

考题 In project management , a (1) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (2) ,budget and duration, linked by dependencies and scheduled events.A.scheduleB.activityC.planD.contractor@@@SXB@@@A.findingB.balanceC.allocationD.distribution

考题 If the approved change requests have an effect on the project scope, then the corresponding component documents and cost baselines, and( ) of the project management plan. Are revised and reissued to reflect the approved changesA.developing baselinesB.testing baselinesC.schedule baselinesD.ending baselines

考题 The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope. (74) could provide the fund to cover the newly discovered work item.A.Contingency reserve B.Project profit C.Management reserve D.Special fund

考题 The key benefit of( )is that it provides guidance and direction on how the project costs will be managed throughout the project.A.Plan Cost Management B.Control Cost C. Estimate Cost D. Determine Budget

考题 Every documented change request needs to be either approved or rejected by a responsible individual sually( ).A.the project sponsor B.an individual C.any stakeholeder D.quality controller

考题 The project management plan defines how the project is executed,monitored and controlled,and closed.It is progressively elaborated by updates,and controlled and approved through the perform integrated( )process.A.Cost control B.Schedule control C.Change control D.Risk control

考题 A project is a[temporary](请作答此空)of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)( )system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to( )project(s).A.task B.work C.sequence D.activity

考题 If the approved change requests have an effect on the project scope,then the corresponding component documents and cost baselines,and( )of the project management plan are revised and reissued to reflect the approved changes. A.developing baselines B.testing baselines C.schedule base lines D.ending baselines

考题 Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes. ( ) is not a project configuration management tool.A.Rational Clearcase B.Quality Function Deployment C.Visual SourceSafe D.Concurrent Versions System

考题 The scope management plan is how the team will prepare the( )a document that includes descriptions of create the WBS,verify completion of the project deliverables,and control requests for changes to the project scope. A.project charter B.project scope goal C.project budget D.project scope statement

考题 The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false. A、The communication management plan is contained in or is a subsidiary plan of, the project management plan.B、The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the project.C、The communication manamgement plan organize and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.D、The communication management plan can include guidelines project status meetings,project team meetings,e-meetines,and e-mail

考题 In project management, a ( )is a list of a project’s milestones, activities, and deliverables, usually with intended start and finish date. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies and scheduled events. A、scheduleB、WBSC、SOWD、charter

考题 单选题In project management , a (73) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (74) ,budget and duration, linked by dependencies and scheduled events.A scheduleB activityC planD contractor

考题 单选题Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.A RationalClearcaseB QualityFunctionDeploymentC VisualSourceSafeD ConcurrentVersions System