An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?
A

Total float for the activity is 9 days.

B

The early finish date ofthe activity is the end ofthe day on the 14th.

C

The late finish date is the 25th.

D

The activity can be completed in 2 days ifthe resources devoted to it are doubled.


参考答案

参考解析
解析: 暂无解析
更多 “单选题An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?A Total float for the activity is 9 days.B The early finish date ofthe activity is the end ofthe day on the 14th.C The late finish date is the 25th.D The activity can be completed in 2 days ifthe resources devoted to it are doubled.” 相关考题
考题 Which of the following is indicative of negative float?A.The late start date is earlier than the early start date.B.The critical path supports the imposed end date.C.The early finish date is equal to the late finish date.D.When leads are employed in the schedule.E.The project is sinking.

考题 Free float is the amount of time that an activity may be delayed with out affecting the _____.A.Early start of the succeeding activities.B.Late start of the succeeding activities.C.Project finish.D.Cost of the project.E.None of the above.

考题 The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as:A.SlackB.Free float.C.Restricted float.D.Level float.E.Lag

考题 Using the figure in the Special window, Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks.A . 2, 10B . 4, 12C . 6, 14D . 7, 15E . 9, 17

考题 Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.A . 11, 13B . 12, 14C . 13, 15D . 14, 16E . 15, 17

考题 22 The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as:A. SlackB. Free float.C. Restricted float.D. Level float.E. Lag

考题 An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?A.Total float for the activity is 9 days.B.The early finish date ofthe activity is the end ofthe day on the 14th.C.The late finish date is the 25th.D.The activity can be completed in 2 days ifthe resources devoted to it are doubled.

考题 PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity. A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

考题 117 Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.A. 11, 13B. 12, 14C. 13, 15D. 14, 16E. 15, 17

考题 119 Using the figure in the Special window, Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks.A. 2, 10B. 4, 12C. 6, 14D. 7, 15E. 9, 17

考题 PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity. A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

考题 ● Which of the following is indicative of negative float?A The late start date is earlier than the early start date.B The critical path supports the imposed end date.C The early finish date is equal to the late finish date.D When leads are employed in the schedule.E The project is sinking.

考题 ● Free float is the amount of time that an activity may be delayed with out affecting the _____.A Early start of the succeeding activities.B Late start of the succeeding activities.C Project finish.D Cost of the project.E None of the above.

考题 一旦为一个完整网络计算出活动历时,顺推法(forwardpass)与逆推法(backwardpass)就会提供() A.活动的总时差(float)B.只有最早开始(early start)与最晚开始时间(late Start)C.关键路径(critical path)D.A和C

考题 PDM includes four types of dependencies or precedence relationships.( ),the initiation of the successor activity,depends upon the initiation ofthe predecessor activity. A.Start-to-Start B.Finish-to-Finish C.Start-to-Finish D.Finish-to—Start

考题 It's my advice that she ____ right now, or she might be late for the plane. A.startB.startsC.would startD.will start

考题 Why is she ( )lunch so early? It's only 10 now.A. havingB. haveC. has

考题 A rite of passage is an activity that ___ a change in a person’s life. A. signalsB. givesC. marksD. has

考题 ● Precedence Diagramming Method (PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called __(75)__.(75)A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

考题 Recent federal regulatory activity has been _______ to protect the privacy of consumer’s personal information.A.implementing B.implement C.implemented D.implements

考题 资料:People differ greatly in their readiness to try new products. In each product area,there are“consumption pioneers”and early adopters. Other individuals adopt new products much later. After a slow start,an increasing number of people adopt the new product. The five-adopter groups have different values. Innovators are venturesome-they try new ideas at risk. Early adopters are guided by respect-they are opinion leaders in their communities and adopt new ideas early but carefully. The early majority are deliberate-although they rarely are leaders,they adopt new ideas before the average person. The late majority skeptical-they adopt an innovation only after a majority of people have tried it. Finally,laggards are tradition bound-they are suspicious of changes and adopt the innovation only when it has become something of a tradition itself. Which group adopts new ideas before the average person?A.Early adopters B.Innovators C.The early majority D.All above

考题 Precedence Diagramming Method(PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called ( ). A.Finish-to-Start B.Finish-to-Finish C.Start-to-Start D.Start-to-Finish

考题 PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.A、Finish-to-StartB、Finish-to-FinishC、Start-to-StartD、Start-to-Finish

考题 一旦为一个完整网络计算出活动历时,顺推法(forwardpass)与逆推法(backwardpass)就会提供()A、活动的总时差(float)B、只有最早开始(early start)与最晚开始时间(late Start)C、关键路径(critical path)D、A和C

考题 单选题According to the passage, cell phones were launched _____.A in the late 1970sB between 1980 and 1985C in the late 1980sD in the early 1990s

考题 单选题一旦为一个完整网络计算出活动历时,顺推法(forwardpass)与逆推法(backwardpass)就会提供()A 活动的总时差(float)B 只有最早开始(early start)与最晚开始时间(late Start)C 关键路径(critical path)D A和C

考题 单选题It’s the second time that Dick has been late, _____?A hasn’t heB isn’t itC isn’t heD hasn’t