119 Using the figure in the Special window, Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks.

A. 2, 10

B. 4, 12

C. 6, 14

D. 7, 15

E. 9, 17


参考答案

更多 “ 119 Using the figure in the Special window, Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks.A. 2, 10B. 4, 12C. 6, 14D. 7, 15E. 9, 17 ” 相关考题
考题 Free float is the amount of time that an activity may be delayed with out affecting the _____.A.Early start of the succeeding activities.B.Late start of the succeeding activities.C.Project finish.D.Cost of the project.E.None of the above.

考题 Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.A . 2B . 3C . 4D . 5E . 7

考题 Using the figure in the Special window, Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks.A . 2, 10B . 4, 12C . 6, 14D . 7, 15E . 9, 17

考题 Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.A . 11, 13B . 12, 14C . 13, 15D . 14, 16E . 15, 17

考题 Using the figure in the Special window, The Critical path is _____ weeks.A . 21B . 22C . 23D . 24E . 25

考题 Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?A . PB . QC . RD . SE . T

考题 Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?A . 0B . 1C . 2D . 3E . 4

考题 A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be:A . 4 weeksB . 5 weeksC . 6 weeksD . 7 weeksE . None of the above.

考题 124 A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be:A. 4 weeksB. 5 weeksC. 6 weeksD. 7 weeksE. None of the above

考题 6 A line manager provides you with three estimates for his activity in your PERT network. His estimates are 2 weeks optimistically, 4 weeks most likely, and 12 weeks pessimistically. The expected time which would appear on the chart would be:A. 4 weeksB. 5 weeksC. 6 weeksD. 7 weeksE. None of the above

考题 An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?A.Total float for the activity is 9 days.B.The early finish date ofthe activity is the end ofthe day on the 14th.C.The late finish date is the 25th.D.The activity can be completed in 2 days ifthe resources devoted to it are doubled.

考题 111 Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?A. 0B. 1C. 2D. 3E. 4

考题 112 Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?A. PB. QC. RD. SE. T

考题 114 Using the figure in the Special window, The Critical path is _____ weeks.A. 21B. 22C. 23D. 24E. 25

考题 117 Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.A. 11, 13B. 12, 14C. 13, 15D. 14, 16E. 15, 17

考题 120 Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.A. 2B. 3C. 4D. 5E. 7

考题 1 Using the figure in the Special window, Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks.A. 2, 10B. 4, 12C. 6, 14D. 7, 15E. 9, 17

考题 2 Using the figure in the Special window, The slacktime in Activity "G" is _____ weeks.A. 2B. 3C. 4D. 5E. 7

考题 ● Free float is the amount of time that an activity may be delayed with out affecting the _____.A Early start of the succeeding activities.B Late start of the succeeding activities.C Project finish.D Cost of the project.E None of the above.

考题 PDM includes four types of dependencies or precedence relationships.( ),the initiation of the successor activity,depends upon the initiation ofthe predecessor activity. A.Start-to-Start B.Finish-to-Finish C.Start-to-Finish D.Finish-to—Start

考题 47. —_______ will you stay in Shenzhen for your holiday?—For about two weeks.A. How oftenB. How longC. How soonD. What time

考题 Precedence Diagramming Method(PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called ( ). A.Finish-to-Start B.Finish-to-Finish C.Start-to-Start D.Start-to-Finish

考题 Based on which two conditions can master Preventive Maintenance (PM) schedules be created?()A、 elapsed time since the target start date or completion date of previous work generated by PM  B、 difference between completion date of previous work and system date is equal to Lead Time  C、 elapsed time since the target start date or completion date of the latest work orders for the assetD、 metered equipment usage since the target start date or completion date of previous work generated by PME、 metered equipment usage since the target start date or completion date of the latest work order for the asset

考题 You create a table with the PERIOD FOR clause to enable the use of the Temporal Validity feature of Oracle Database 12c. Examine the table definition: Which three statements are true concerning the use of the Valid Time Temporal feature for the EMPLOYEES table?()A、The valid time columns employee_time_start and employee_time_end are automatically created.B、The same statement may filter on both transaction time and valid temporal time by using the AS OF TIMESTAMP and PERIOD FOR clauses.C、The valid time columns are not populated by the Oracle Server automatically.D、The valid time columns are visible by default when the table is described.E、Setting the session valid time using DBMS_FLASHBACK_ARCHIVE.ENABLE_AT_VALID_TIME sets the visibility for data manipulatio

考题 多选题You create a table with the PERIOD FOR clause to enable the use of the Temporal Validity feature of Oracle Database 12c. Examine the table definition: Which three statements are true concerning the use of the Valid Time Temporal feature for the EMPLOYEES table?()AThe valid time columns employee_time_start and employee_time_end are automatically created.BThe same statement may filter on both transaction time and valid temporal time by using the AS OF TIMESTAMP and PERIOD FOR clauses.CThe valid time columns are not populated by the Oracle Server automatically.DThe valid time columns are visible by default when the table is described.ESetting the session valid time using DBMS_FLASHBACK_ARCHIVE.ENABLE_AT_VALID_TIME sets the visibility for data manipulatio

考题 单选题An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?A Total float for the activity is 9 days.B The early finish date ofthe activity is the end ofthe day on the 14th.C The late finish date is the 25th.D The activity can be completed in 2 days ifthe resources devoted to it are doubled.

考题 多选题Based on which two conditions can master Preventive Maintenance (PM) schedules be created?()Aelapsed time since the target start date or completion date of previous work generated by PMBdifference between completion date of previous work and system date is equal to Lead TimeCelapsed time since the target start date or completion date of the latest work orders for the assetDmetered equipment usage since the target start date or completion date of previous work generated by PMEmetered equipment usage since the target start date or completion date of the latest work order for the asset