Many useful tools and techniques are used in developing schedule. ( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource.

A.PERT
B.Resource levelling
C.Schedule compression
D.Critical chain methoD.

参考答案

参考解析
解析:PERT方法能协调整个计划的各道工序,通过描绘出项目包含的各种活动的先后次序,标明每项活动的时间或相关的成本,合理安排人力、物力、时间、资金,加速计划的完成。A. PERT B. 资源平衡C. 进度压缩 D. 关键链法
更多 “Many useful tools and techniques are used in developing schedule. ( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource.A.PERT B.Resource levelling C.Schedule compression D.Critical chain methoD.” 相关考题
考题 Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource. A.PERTB.ResourcelevelingC.SchedulecompressionD.Critical chain method

考题 Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order. A.activity duration estimating, schedule developing, activity resource estimatingB.activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating

考题 ● (73) is one of the techniques used for estimating activity durations.(73)A.Analogous EstimatingB.Precedence Diagramming Method (PDM)C.Dependency DeterminationD.Schedule network Templates

考题 Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.A.analyzeB.trackC.levelD.extend

考题 ●Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.(75)A. analyzeB. trackC. levelD. extend

考题 ● Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( 71) , and schedule control by order.(71)A.activity duration estimating, schedule developing, activity resource estimatingB . activity resource estimating, activity duration estimating, schedule developmentC.schedule developing, activity resource estimating, activity duration estimatingD.activity resource estimating, schedule developing, activity duration estimating

考题 ● Many useful tools and techniques are used in developing schedule. (72) is a schedule network analysis technique that modifies the project schedule to account for limited resource.(72)A.PERTB.Resource levellingC.Schedule compressionD.Critical chain method

考题 ______is one of the techniques used for estimating activity durations.A.Analogous EstimatingB.Precedence Diagramming Method(PDM)C.Dependency DeterminationD.Schedule network Templates

考题 The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned

考题 Difficult _____ the project was, I managed to finish it on schedule. A: no matterB: asC: despiteD: though

考题 A()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.A.gantt chartB.project histogramC.milestone chartD.project flowchart

考题 Many useful tools techniques are used in developing schedule. ( )s a schedule network analysis technique that modifies the project schedule to account for limited resource.A.PERT B.Resource levelling C.Schedule compression D.Critical chain method

考题 ??Many useful tools and techniques are used in developing schedule.( 73) is a schedulenetwork analysis technique that modifies the project schedule to account for limited resource??A.PERTB. Resource levellingC.Schedule compressionD.Critical chain method

考题 Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and ( )A.fast trackingB.what-if scenario analysisC.resource levelingD.critical chain method

考题 ( )techniques are used to find ways to bring project activities that are alignment with the plan by fast tracking or crashing the schedule for the remaining work.A.Schedule forecasts B.Schedule compression C.Change requests D.Data analysis

考题 A variety of tools is available to help the analyst to discover the users' true needs.These tools are grouped into three broad techniques that are based on the degree of change anticipated in the to-be system . Business process(71) is used when the basic business Requirements outlined in the system request focus on employing computer technology in some aspect of the business process. Two popular activities used in the technique are(72). Business process(73)means that the basic business requirements target moderate changes to the organization' s operations. (74)are three popular activities in the technique. Business process (75)means changing the current way of doing business and making major changes to take advantage of new ideas and new technology.A. Duration analysis,activity-baseD.costing anD.informal bench marking B.Outcome analysis, technology analysis anD.activity elimination C.Problem analysis, root cause analysis anD.critical path analysis D.Cost-benefit analysis, schedule analysis anD.risk analysis

考题 Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order. A.activity duration estimating, schedule developing, activity resource estimating B.activity resource estimating, activity duration estimating, schedule development C.schedule developing, activity resource estimating, activity duration estimating D.activity resource estimating, schedule developing, activity duration estimating

考题 Schedule compression shortens the project schedule without changing the project scope,to meet schedule constraints,imposed dates,or other schedule objectives.Schedule compression techniques include crashing and( ). A.fast tracking B.what-if scenario analysis C.resource leveling D.critical chain methoD.

考题 Many useful tools and techniques are used in developing schedule. ( ) is a schedule network analysis technique that modifies the project schedule to account for limited resource. A.PERT B.Resource levelling C.Schedule compression D.Critical chain methoD.

考题 ()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.A、gantt chartB、project histogramC、milestone chartD、project flowchart

考题 The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate Quality Management technique to implement?()A、Evaluate phase exit milestones using sufficiency criteriaB、Flexible entry and exit criteria to minimize schedule delaysC、Quality measures reported only to the project steering committeeD、Many work teams with few members to maximize the number of deliverable hand-offs

考题 Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.A、activity duration estimating, schedule developing, activity resource estimatingB、activity resource estimating, activity duration estimating, schedule developmentC、schedule developing, activity resource estimating, activity duration estimatingD、activity resource estimating, schedule developing, activity duration estimating

考题 Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource.A、PERTB、ResourcelevelingC、SchedulecompressionD、Critical chain method

考题 The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()A、Data flow modelB、The project critical pathC、Resource loading chartD、WBS (Work Breakdown Structure)

考题 Which of the following techniques is used for tracking the project risks?()A、Probability-Impact matrixB、Pareto chartC、R-ChartD、PERT (Program Evaluation and Review Technique) analysis

考题 单选题Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.A analyzeB trackC levelD extend

考题 单选题Project schedule management is made up of six management processes including: activity definition, activity sequencing()and schedule control by order.A activity duration estimating, schedule developing, activity resource estimatingB activity resource estimating, activity duration estimating, schedule developmentC schedule developing, activity resource estimating, activity duration estimatingD activity resource estimating, schedule developing, activity duration estimating