()is the process of obtaining the stakeholders’ formal acceptance of the completed project scope.Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
A

Project acceptance

B

Scope verification

C

Scope definition

D

WBS Creation


参考答案

参考解析
解析: 范围验证是指获取项目干系人对已完成的项目范围的正式认可的过程。验证范围包括评审可交付物和工作成果,以确保这些工作都已按照范围定义中的要求完成。
更多 “单选题()is the process of obtaining the stakeholders’ formal acceptance of the completed project scope.Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A Project acceptanceB Scope verificationC Scope definitionD WBS Creation” 相关考题
考题 Which type of process involves the agency holding discussions with each of the offerors, after receipt of their proposals, in the process of arriving at an agreement prior to the award of a contract?A Sealed biddingB Competitive proposalsC Noncompetitive proposalsD Formal bidE Verbal bid

考题 87 Which type of process involves the agency holding discussions with each of the offerors, after receipt of their proposals, in the process of arriving at an agreement prior to the award of a contract?A. Sealed biddingB. Competitive proposalsC. Noncompetitive proposalsD. Formal bidE. Verbal bid

考题 In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project‘s communication. According to Metcalfe‘s Law, a project with 10 stakeholders has()potential communication channels.A.10B.45C.50D.100

考题 50 We are thus led to distinguish, within the broad educational process which we have been so far considering, a more formal kind of education -- that of direct tuition or schooling. In undeveloped social groups, we find very little formal teaching and training. These groups mainly rely for instilling needed dispositions into the young upon the same sort of association which keeps the adults loyal to their group.

考题 is the process of obtaining the stakeholdrs'formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A.WBS CreationB.Scope definitionC.Project acceptanceD.Scope verification

考题 Bonar Paint to date has had no formal strategic planning process.(d) What are the advantages and disadvantages of developing a formal mission statement to guide Bonar Paint’sfuture direction after the buyout? (10 marks)

考题 is the process of obtaining the stakeholders' formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A.Project acceptanceB.Scope verificationC.Scope definitionD.WBS Creation

考题 ● In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project' s communications. According to Metcalfe's Law, a project with 10 stakeholders has ( 73 ) potential communication channels.(73) A. 10B. 45C. 50D. 100

考题 Requirements management is the process of ( 73 ),analyzing, tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholders. It is a ( 74 ) process throughout a project. A requirement is a capability to which a project outcome (product or service) should conform.A.communicatingB.collectingC.filingD.documenting

考题 (73)A.investorsB.developersC.designersD.stakeholders

考题 ()is the process of documenting,analyzing,tracing,prioriiting on requirements and then controlling change and communicating to stakeholders it is a continuous process throughout a projectA.integratend managementB.configurationmanagemenC.scopemanagementD.requirementmanagement

考题 Which three characteristics are unique to the buying process for A small business compared with the buying process for an enterprise?() A.influenced by peersB.not constrained by formal RFPC.much fasterD.less educatedE.focused primarily on costF.technology focused

考题 (50)We are thus led to distinguish, within the broad educational process which we have been so far considering, a more formal kind of education—that of direct tuition or schooling. 此处译文为:

考题 Change control within information technology(IT)systems is a formal process used to ensure that changes to product or system are introduced in a controlled and coordinated manner.It(74)the possibility that unnecessary changes will be introduced to a systeA.Adds B.Removes C.Produces D.Reduces

考题 Besides the( ) for process and data of current system,the deliverable from this phase also includes the formal requirements definition for the proposed system. A.logical models B.physical models C.design models D.implementation models

考题 () is the process of obtaining the stakeholders\' formal acceptance of thecompleted project scope. Verifying the scope includes reviewing deliverables and work results toensure that all were completed satisfactorily. A.Project acceptance B.Scope verification C.Scope definition D.WBS Creation

考题 In the process of communication requirement analysis,the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project’s communications. According to Metcalfe’s Law,a project with 10 stakeholders has ( ) potential communication channels. A.10 B.45 C.50 D.100

考题 Requirements management is the process of (73) ,analyzing,tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholders. A.communicating B.collecting C.filing D.documenting

考题 信用证项下出口票据贴现,在正本汇票上承兑的,应注明“()”承兑字样。A、ACCEP TEDB、PER AVALC、AVAL IZEDD、CONF IRMED

考题 ( ) is the process of documenting, analyzing, tracing, prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders. It is a continuous process throughout a project.A、Integrated managementB、Configuration managementC、Scope managementD、Requirements management

考题 Which three characteristics are unique to the buying process for A small business compared with the buying process for an enterprise?()A、much fasterB、focused primarily on costC、not constrained by formal RFPD、technology focusedE、less educatedF、influenced by peers

考题 ()is the process of obtaining the stakeholders’ formal acceptance of the completed project scope.Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A、Project acceptanceB、Scope verificationC、Scope definitionD、WBS Creation

考题 单选题In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project’s communication. According to Metcalfe’s Law, a project with 10 stakeholders has ( ) potential communication channels.A 10B 45C 50D 100

考题 多选题Which three characteristics are unique to the buying process for A small business compared with the buying process for an enterprise?()Ainfluenced by peersBnot constrained by formal RFPCmuch fasterDless educatedEfocused primarily on costFtechnology focused

考题 单选题analyzing,tracing,prioritizing and agreeing on requirements and then controlling changes and communicating to relevant stakeholders. It is a()process throughout a project. A requirement is a capability to which a project outcome(product or service)should conform.A persistentB continuingC permanentD continuous

考题 单选题“The engine not obtaining the sufficient speed for firing” means that ().A the start failsB the fuel pumps will be put into operationC the fuel valves are damagedD the combustion process will take over

考题 单选题() is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.A projectacceptanceB scopeverificationC scopedefinitionD WBS Creation

考题 单选题Which of the following is the best example of a heuristic as it is described in Passage 1 ?A the rules of debate in a formal legislatureB the system by which democratic societies choose leadersC the process of deciding quickly whether or not an approaching person is friendlyD a procedure for solving complex algebraic equationsE a therapeutic method for resolving personal conflicts