If reefer spaces are not properly cleaned prior to loading cargo,it will most likely cause().
A

mold to develop on commodities

B

malfunction of the refrigeration equipment

C

contamination of the insulation in the space

D

All of the above


参考答案

参考解析
解析: 暂无解析
更多 “单选题If reefer spaces are not properly cleaned prior to loading cargo,it will most likely cause().A mold to develop on commoditiesB malfunction of the refrigeration equipmentC contamination of the insulation in the spaceD All of the above” 相关考题
考题 ______ the children have cleaned up, you can let them go. A、Prior toB、Now thatC、But thenD、In total

考题 Cargo contaminated due to failure to provide clean holds prior to loading is an example of ________ .A.Lack of due diligenceB.Restraint of princesC.Inherent viceD.Latent defect

考题 Said cargo spaces having been cleaned in accordance with the Regulations of the United States Coast Guard and the Code of Federal Regulations so far as applicable,and in accordance with the recommendations of the National Cargo Bureau,Inc. This wording is likely to appear in ______.A.CERTIFICATE OF CLEANLINESSB.FUMIGATION AND GAS FREE CERTIFICATEC.CERTIFICATE OF CLASSD.INTERNATIONAL OIL POLLUTION PREVENTION CERTIFICATE

考题 Said cargo spaces having been cleaned in accordance with the Regulations and the recommendations of the (US) National Cargo Bureau,Inc. This wording is likely to appear in ______.A.CERTIFICATE OF CLEANLINESSB.FUMIGATION AND GAS FREE CERTIFICATEC.CERTIFICATE OF CLASSD.INTERNATIONAL OIL POLLUTION PREVENTION CERTIFICATE

考题 If you are loading fruit in reefer spaces and you notice that the fruit is beginning to mold,you should ______.A.carry the cargo at a cooler temperature than originally plannedB.write up exceptions on the cargoC.refuse to carry the cargoD.discharge CO2 into the compartment after loading

考题 Refrigeration machinery is often surveyed before loading reefer cargo. This survey is usually performed by the ______.A.MSAB.CCSC.CCIQD.local port authority

考题 Which organization would conduct a survey of the insulation in a reefer compartment prior to loading cargo?A.PRC Customs ServiceB.OSHAC.CCSD.CCIQ

考题 After a seaman is discharged,at the end of the voyage,the final payment of wages due must be made at the earlier of within 24 hours after the cargo has been discharged or______.A.within 4 days after the seaman's dischargeB.prior to the vessel's departure on the next voyageC.prior to loading any out-bound cargoD.prior to any change of Master

考题 The final inspection responsibility for seeing that a tank barge is provided with the required equipment and fittings in good and serviceable condition prior to loading cargo rests with the ______.A.terminal operatorB.owner of the bargeC.tankerman or person in charge of loadingD.charterer through the Master of the towing vessel

考题 All dunnage planks and mats must be sent on board ______ commencement of loading.A.Prior toB.DuringC.In the period ofD.Afterwards

考题 If reefer spaces are not properly cleaned prior to loading cargo,it will most likely cause ______.A.mold to develop on commoditiesB.malfunction of the refrigeration equipmentC.contamination of the insulation in the spaceD.All of the above

考题 Prior to loading barges over the stern of a LASH vessel,the vessel should be trimmed in what manner ________.A.Two to four feet by the bowB.Slightly by the bowC.No trim should be permittedD.Slightly by the stern

考题 All the holds to be loaded with grain must be swept ______ commencement of loading.A.Cleanly/duringB.Clear/meanwhileC.Clean/betweenD.Clean/prior to

考题 Which narrative regarding loading software is incorrect?()A、The approved Loading Program could substituted the approved Loading Manual and/or Trim and Stability BookletB、A Loading Program is required to have General Approval by classification Society prior to being considered for use on a specific shipC、Following a satisfactory installation test on board the ship the Surveyor will issue a Program Installation TestD、A Loading Program may be provided as a classification requirement or as an Owner’s option

考题 单选题Prior to being able to sail in a US port,each vessel that carries grain in bulk must have a certificate of loading issued by the().A American Bureau of ShippingB Lloyds of LondonC National Cargo BureauD US Salvage

考题 单选题You are transporting dangerous cargo on your vessel.You must inspect this cargo().A DailyB Daily,at sea onlyC After encountering rough weatherD After loading and prior to arrival in port only

考题 单选题Prior to loading barges over the stern of a LASH vessel,the vessel should be trimmed in what manner?().A Two to four feet by the bowB Slightly by the bowC No trim should be permittedD Slightly by the stern

考题 单选题The final inspection responsibility for seeing that a tank barge is provided with the required equipment and fittings in good and serviceable condition prior to loading cargo rests with the ().A terminal operatorB owner of the bargeC tankerman or person in charge of loadingD charterer through the Master of the towing vessel

考题 单选题Refrigeration machinery is often surveyed before loading reefer cargo. This survey is usually performed by the().A MSAB CCSC CCIQD local port authority

考题 单选题Cargo contaminated due to failure to provide clean holds prior to loading is an example of().A lack of due diligenceB restraint of princesC inherent viceD latent defect

考题 单选题Said cargo spaces having been cleaned in accordance with the Regulations and the recommendations of the (US) National Cargo Bureau,Inc. This wording is likely to appear in ().A CERTIFICATE OF CLEANLINESSB FUMIGATION AND GAS FREE CERTIFICATEC CERTIFICATE OF CLASSD INTERNATIONAL OIL POLLUTION PREVENTION CERTIFICATE

考题 单选题If you are loading fruit in reefer spaces and you notice that the fruit is beginning to mold, you should().A carry the cargo at a cooler temperature than originally plannedB write up exception on the cargoC refuse to carry the cargoD discharge CO2 into the compartment after loading

考题 单选题The()should ensure that the holds in which chemical packages are stowed are properly supervised during the loading operations and these packages are regularly inspected for leakage or damage on the voyage.A berth operatorB harbour supervisorC master of a shipD port authority

考题 单选题Which organization would conduct a survey of the insulation in a reefer compartment prior to loading cargo? ()A PRC Customs ServiceB OSHAC CCSD CCIQ

考题 单选题Said cargo spaces having been cleaned in accordance with the Regulations of the United States Coast Guard and the Code of Federal Regulations so far as applicable,and in accordance with the recommendations of the National Cargo Bureau,Inc. This wording is likely to appear in ().A CERTIFICATE OF CLEANLINESSB FUMIGATION AND GAS FREE CERTIFICATEC CERTIFICATE OF CLASSD INTERNATIONAL OIL POLLUTION PREVENTION CERTIFICATE

考题 单选题All the holds to be loaded with grain must be swept()commencement of loading.A Cleanly/duringB Clear/meanwhileC Clean/betweenD Clean/prior to

考题 单选题Which narrative regarding loading software is incorrect?()A The approved Loading Program could substituted the approved Loading Manual and/or Trim and Stability BookletB A Loading Program is required to have General Approval by classification Society prior to being considered for use on a specific shipC Following a satisfactory installation test on board the ship the Surveyor will issue a Program Installation TestD A Loading Program may be provided as a classification requirement or as an Owner’s option