网友您好, 请在下方输入框内输入要搜索的题目:

题目内容 (请给出正确答案)
The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) .实施整体变更控制过程是从项目开始到项目结束并且是( )项目经理的最终责任。

A.Chang control board变更控制委员会
B.Project management office项目管理办公室
C.Project manager项目经理
D.Configuration management officer配置管理员

参考答案

参考解析
解析:
更多 “The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) .实施整体变更控制过程是从项目开始到项目结束并且是( )项目经理的最终责任。A.Chang control board变更控制委员会 B.Project management office项目管理办公室 C.Project manager项目经理 D.Configuration management officer配置管理员 ” 相关考题
考题 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:A . Baseline costsB . Budgeted costs.C . Estimates upon completion costsD . Scheduled costsE . None of the above

考题 In the project environment, the individual ultimately responsible for quality control is:A . The line workers who must strive "to do things right the first time" to avoid quality problems.B . the company's quality control manager who must work with the project members to ensure the quality control program is effective.C . The head of the production department who retains ultimate quality control responsibility for all the company's projects.D . The project manager who has ultimate responsibility for the entire project.E . the customer who must ensure that he is receiving a quality product from the vendor.

考题 41 In the project environment, the individual ultimately responsible for quality control is:A. The line workers who must strive "to do things right the first time" to avoid quality problems. B. the company's quality control manager who must work with the project members to ensure the quality control program is effective.C. The head of the production department who retains ultimate quality control responsibility for all the company's projects.D. The project manager who has ultimate responsibility for the entire project.E.the customer who must ensure that he is receiving a quality product from the vendor

考题 23 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:A. Baseline costsB Budgeted costs.C. Estimates upon completion costsD. Scheduled costsE. None of the above

考题 105 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:A. Baseline costsB. Budgeted costs.C. Estimates upon completion costsD. Scheduled costsE. None of the above

考题 The perform. Integrated Change Contorl process is the ultimate responsibility of the(①).Although changes may be initiated verbally,they should be recorded in writtern form. and entered into the (②)system.①A.resource managerB.division managerC.functional managerD.project manager②.A.quality managementB.configuration managementC.project managerD.scope management

考题 以下关于项目整体变更控制过程的叙述中,不正确的是:( )A.实施整体变更控制过程的目的是为了降低项目风险B.实施整体变更控制过程贯穿项目始终,并且应用于项目的各个阶段C.变更控制委员会对整体变更控制过程负最终责任D.会议是实施整体变更控制的工具与技术之一

考题 The Perform. Integrated Change Control process is conducted from project lnception through completion and is the ultimate responsibility of the(75)A.change control boardB. project management officeC.project managerD.configuration management officer

考题 The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) . A.Chang control board B.Project management office C.Project manager D.Configuration management officer

考题 、关于整体变更拉制的描述,不正确的是:( )。A.项目的任何干系人都可以提出变更请求 B.项目经理可以是变更控制委员全(CCB)的成员 C.整体变更控制过程贯穿项目始终,CCB对此负最终责任 D.整体变更控制的主要作用是降低因未考虑变更对整个项目计划的影响而产生的风险

考题 ( )is not included in Perform Integrated Change Control Process.A.Defining subsidiary plans B.Approving changes C.Managing changes to deliverables D.Reviewing all change requests

考题 The project management plan defines how the project is executed,monitored and controlled,and closed.It is progressively elaborated by updates,and controlled and approved through the perform integrated( )process.A.Cost control B.Schedule control C.Change control D.Risk control

考题 When required the perform Integrated Change Control Process includes ()Which is a formally chartered group responsible for reviewing ting approving deferring or rejecting changes to the project and for ing and communicating such decisions A.BBC] B.CCB] C.BCB] D.CBC]

考题 ( ) is the process of documenting, analyzing, tracing, prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders. It is a continuous process throughout a project.A、Integrated managementB、Configuration managementC、Scope managementD、Requirements management

考题 项目计算期是指投资项目从投资建设开始到最终清理结束整个过程的全部时间。()

考题 在项目执行阶段,一名项目相关方要求项目经理加入一个新过程的优化。项目经理应该怎么做?()A、执行实施整体变更控制过程B、与过程专家一起审查项目C、将优化项目分配给团队D、拒绝范围蔓延的尝试

考题 项目经理加入一个设计阶段接近完成的项目。虽然客户已经批准所有设计图纸,但项目经理发现包含在最终设计中的多项客户变更,这些变更尚未经过审核和批准。项目经理下一步应该怎么做?()A、向客户提交变更请求记录这些变更B、实施整体变更控制过程C、与客户一起审查变更管理计划D、停止所有工作,减轻这些变更对成本、时间和质量的影响

考题 项目发起人通知项目经理一种产品可能会对客户产生不利于健康的影响。因此,发起人要求改变生产材料。项目经理应该怎么做?()A、通过遵循实施整体变更控制过程,进一步调查该事项B、立即实施这项变更并提交正式文档的变更请求C、停止当前工作,并启动实施整体变更控制过程D、拒绝该请求,因为己超出范围

考题 对于变更请求过程的完整性以及获得准变更请求的实施跟踪,由谁来承担最终责任?()A、项目赞助人B、项目团队成员C、项目经理D、变更控制委员会

考题 项目经理刚刚被任命管理一个正在进行中的项目,了解到许多批准的变更请求还未解决。项目经理应该遵循下列哪一个流程?()A、核实范围B、控制沟通C、指导与管理项目工作D、实施整体变更控制

考题 项目实施后,项目干系人向项目经理报告缺陷超出阈值。若要避免这个问题,项目经理应该事先做什么?()A、记录质量控制措施B、执行实施整体变更控制过程C、执行过程改进D、管理项目干系人的期望

考题 客户验收测试即将结束,但是客户要求在提供批准之前进行一项变更。项目经理应该怎么做?()A、应用核实范围过程。B、通知项目发起人。C、进行变更,并获得批准。D、通过实施整体变更控制过程将该请求添加进范围当中。

考题 单选题项目经理刚刚被任命管理一个正在进行中的项目,了解到许多批准的变更请求还未解决。项目经理应该遵循下列哪一个流程?()A 核实范围B 控制沟通C 指导与管理项目工作D 实施整体变更控制

考题 单选题项目实施后,项目干系人向项目经理报告缺陷超出阈值。若要避免这个问题,项目经理应该事先做什么?()A 记录质量控制措施B 执行实施整体变更控制过程C 执行过程改进D 管理项目干系人的期望

考题 单选题对于变更请求过程的完整性以及获得准变更请求的实施跟踪,由谁来承担最终责任?()A 项目赞助人B 项目团队成员C 项目经理D 变更控制委员会

考题 单选题客户验收测试即将结束,但是客户要求在提供批准之前进行一项变更。项目经理应该怎么做?()A 应用核实范围过程。B 通知项目发起人。C 进行变更,并获得批准。D 通过实施整体变更控制过程将该请求添加进范围当中。

考题 判断题项目计算期是指投资项目从投资建设开始到最终清理结束整个过程的全部时间。()A 对B 错