网友您好, 请在下方输入框内输入要搜索的题目:

题目内容 (请给出正确答案)

is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activites and connects them with arrows that arrow the dependencies.This method includes following types of dependcies orprecedence relationships: (2)the initiation of the successor activity, depends upon the completion of the predecessor activity. (3)the initiation of the successor activity, depends upon the initiation of the predecessor activity.

A.PDM

B.CPM

C.PERT

D.AOA


参考答案

更多 “ is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activites and connects them with arrows that arrow the dependencies.This method includes following types of dependcies orprecedence relationships: (2)the initiation of the successor activity, depends upon the completion of the predecessor activity. (3)the initiation of the successor activity, depends upon the initiation of the predecessor activity.A.PDMB.CPMC.PERTD.AOA ” 相关考题
考题 The Work Breakdown Structure (WBS) is the basis for communicating:A.Project scope, cost control, schedule, qualityB.Project objectives, dependencies, plan, cost controlC.Project scope, schedule, staffing, cost controlD.Project scope, quality, schedule, dependenciesE.Project budget, schedule, risk factors, work assignments.

考题 120 The Work Breakdown Structure (WBS) is the basis for communicating:A. Project scope, cost control, schedule, qualityB. Project objectives, dependencies, plan, cost controlC. Project scope, schedule, staffing, cost controlD. Project scope, quality, schedule, dependenciesE. Project budget, schedule, risk factors, work assignments

考题 2 The Work Breakdown Structure (WBS) is the basis for communicating:A. Project scope, cost control, schedule, qualityB. Project objectives, dependencies, plan, cost controlC. Project scope, schedule, staffing, cost controlD. Project scope, quality, schedule, dependenciesE. Project budget, schedule, risk factors, work assignments

考题 ● The Work Breakdown Structure (WBS) is the basis for communicating:A Project scope, cost control, schedule, qualityB Project objectives, dependencies, plan, cost controlC Project scope, schedule, staffing, cost controlD Project scope, quality, schedule, dependenciesE Project budget, schedule, risk factors, work assignments.

考题 在播放视屏时,需要保持屏幕一直亮着,需要哪个权限?() A.uses-permission android:name="android.permission.INTERNET"/B.uses-permission android:name="android.permission.WAKE_LOCK"/C.uses-permission android:name="android.permission.SCREEN_LOCK"/D.uses-permission android:name="android.permission.DIM_LOCK"/

考题 WhenyourSolarissystemisbooted,astartupscriptinitializestherpcbindservice.Whichscriptisit?() A./lib/svc/method/net-physicalB./etc/rcS.d/S30networkC.svc:/network/rpc/bind:defaultD./lib/svc/method/rpc-bind

考题 In?project?net work?diagram,the?number?of?critical?path?is()。A.none B.only?one C.only?two D.one?or?more

考题 以下属于调用摄像头硬件的权限的是:()A.<uses-permission android:name="android.permission.CAMERA"/>B.<uses-permission android:name="android.permission.MOUNT_UNMOUNT_FILESYSTEMS" />C.<uses-permission android:name="android.permission.WRITE_EXTERNAL_STORAGE"/>D.<uses-permission android:name="android.permission.INTERNET"/>

考题 3、注册一个短信到来的广播事件需要在清单文件配置什么权限()A.<uses-permission android:name="android.permission.SMS"/>B.<uses-permission android:name="android.permission.SEND_SMS"/>C.<uses-permission android:name="android.permission.RECEIVE_SMS"/>D.<uses-permission android:name="android.permission.RECEIVE_SEND_SMS"/>

考题 下面哪个是添加网络权限的代码A.<uses-permission android:name="android.permission.INTERNET"/>B.<uses-permission android:name="android.permission.ACCEPT_HANDOVER"/>C.<uses-permission android:name="android.permission.ACCESS_CHECKIN_PROPERTIES"/>D.<uses-permission android:name="android.permission.ACCESS_FINE_LOCATION"/>