网友您好, 请在下方输入框内输入要搜索的题目:

题目内容 (请给出正确答案)

● The completion and approval of one or more () characterizes a project phase.()A.deliverables B.products C.projects D.programs


参考答案

更多 “ ● The completion and approval of one or more () characterizes a project phase.()A.deliverables B.products C.projects D.programs ” 相关考题
考题 The time necessary to complete a project is called the _______ of a project.A.Implementation TimeB.Life CycleC.Operation TimeD.Critical PathE.Completion Phase

考题 Approval to proceed is normally made at the end of the _____ phase of a typical project.AconceptualBdevelopmentCimplementationDexecutionEclose-out

考题 A comprehensive definition of scope management would be:A.Managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.B.Approval of the scope baseline.C.Approval of the detailed project charter.D.Configuration control.E.Approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.

考题 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:A . Baseline costsB . Budgeted costs.C . Estimates upon completion costsD . Scheduled costsE . None of the above

考题 A negative cost variance and positive schedule variance means:A The project is under budget and ahead of scheduleB The project is over budget and behind scheduleC The project is over budget and ahead of scheduleD The project will be overrun but ahead of schedule at completion

考题 To determine whether or not the employee correctly understands the message, the project manager needs to:A reduce the filteringB eliminate barriersC obtain feedbackD use more than one mediumE use all of the above.

考题 23 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:A. Baseline costsB Budgeted costs.C. Estimates upon completion costsD. Scheduled costsE. None of the above

考题 105 Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the:A. Baseline costsB. Budgeted costs.C. Estimates upon completion costsD. Scheduled costsE. None of the above

考题 66 The time necessary to complete a project is called the _______ of a project.A. Implementation TimeB. Life CycleC. Operation TimeD. Critical PathE. Completion Phase

考题 96 A negative cost variance and positive schedule variance means:A. The project is under budget and ahead of scheduleB. The project is over budget and behind scheduleC. The project is over budget and ahead of scheduleD. The project will be overrun but ahead of schedule at completion

考题 ● The time necessary to complete a project is called the _______ of a project.A Implementation TimeB Life CycleC Operation TimeD Critical PathE Completion Phase

考题 ● A comprehensive definition of scope management would be:A Managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.B Approval of the scope baseline.C Approval of the detailed project charter.D Configuration control.E Approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.

考题 ●To determine whether or not the employee correctly understands the message, the project manager needs to(75).(75) A. reduce the filteringB. eliminate barriersC. obtain feedbackD. use more than one medium

考题 ● In multi-phase projects, the () Project process closes out the portion of the project scope and associated activities applicable to a given phase.()A.Scope B.Plan C.Close D.Control

考题 are individuals and organizations that are actively involved in the project,or whose interests may be affected as a result of project execution or project completion.A.Project managerB.Project team memberC.SponsorD.Proiect stakeholders

考题 are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.A.ControlsB.BaselinesC.Project stakeholdersD.Project managers

考题 The Perform. Integrated Change Control process is conducted from project lnception through completion and is the ultimate responsibility of the(75)A.change control boardB. project management officeC.project managerD.configuration management officer

考题 The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.A.project charterB.project scope goalC.project budgetD.project scope statement

考题 The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ( ) . A.Chang control board B.Project management office C.Project manager D.Configuration management officer

考题 During the implementation of the project,the user's environment(business environment,organizational structure,etc.)may change,and the demand for the project may also change.For the changing needs of the project scope,()is the person with real approval power.A.user B.project manager C.CCB D.Project investor

考题 In project network diagram ,the number of critical path is ( ).A.none B.only one C.only two D.one or more

考题 In?project?net work?diagram,the?number?of?critical?path?is()。A.none B.only?one C.only?two D.one?or?more

考题 The scope management plan is how the team will prepare the( )a document that includes descriptions of create the WBS,verify completion of the project deliverables,and control requests for changes to the project scope. A.project charter B.project scope goal C.project budget D.project scope statement

考题 () are individuals and organizations that are actively involved in the project, orwhose interests may be affected as a result of project execution or project completion; they mayalso exert influence over the project and its results. A.Controls B.Baselines C.Project stakeholders D.Project managers

考题 () are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.A、Project managersB、Project team membersC、SponsorsD、Project stakeholders

考题 The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()A、Data flow modelB、The project critical pathC、Resource loading chartD、WBS (Work Breakdown Structure)

考题 单选题() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.A Project managersB Project team membersC SponsorsD Project stakeholders