Which of the following is the MOST important consideration when looking at distance requirements when planning a hot site?()

  • A、Avoiding more expensive bandwidth costs for data lines between regions
  • B、Avoiding a regional disaster that affects both the main site and the hot site
  • C、Avoiding a second location that has high latency between sites
  • D、Avoiding a location that is too expensive

参考答案

更多 “Which of the following is the MOST important consideration when looking at distance requirements when planning a hot site?()A、Avoiding more expensive bandwidth costs for data lines between regionsB、Avoiding a regional disaster that affects both the main site and the hot siteC、Avoiding a second location that has high latency between sitesD、Avoiding a location that is too expensive” 相关考题
考题 Which of the following is the MOST important physical consideration when deploying a new server?() A. Humidity monitors, Biometrics, and fire suppressionB. Cooling, rack space, and power requirementsC. Service level agreements, uninterruptible power supply (UPS) deployment, and CCTVD. Biometrics, fire suppression, and power requirements

考题 An administrator is creating a redundant environment for a current data center. A backup site must be available if the entire data center site should become unavailable. To reduce costs, this backup site does not need to be up and running at all times ready for failover. It must contain equipment and the ability to restore data from the data center.Which of the following site types should be considered to meet these requirements?()A. Hot siteB. Warm siteC. Cold siteD. Active failover site

考题 A customer has two single cluster IBM TS7700 Virtualization Engines at the same site. The customer wants to move one to a remote site and set up a grid configuration with the two clusters. The customer has fibre between the two sites. What is the most important factor to consider when planning the new configuration?()A. operator trainingB. cache size of the two clustersC. fibre bandwidth capability between the sitesD. number of stacked tape drives attached to each cluster

考题 When planning the loading or discharging of a VLCC(100,000 DWT+)what is the most important consideration ________.A.Draft and trimB.Limits of the bending momentsC.Rate of dischargingD.Rate of loading

考题 When determining a customer’s technical requirements for a Cisco Unified Communications solution, which important tool can be used to determine the bandwidth used by different codecs with various protocols over different media?()A、Network Codec Aggregator ToolB、Bandwidth Estimator ToolC、Unified Communication Bandwidth ToolD、Voice Bandwidth CalculatorE、Voice Codec Bandwidth Calculator

考题 Which of the following is the MOST important data retention consideration when creating a backup system?()A、Utilizing disk-to-disk clustering and hot site replicationB、If the GFS backup system will cover all potential data breachesC、The process to move the data backup to an offsite locationD、The individual laws and legal requirements of the data

考题 When considering SAN to SAN replication between sites, which of the following is the MOST important concern?()A、 WAN link speedB、 Block sizeC、 Disk sizeD、 File system type

考题 Which of the following is the MOST important consideration when implementing a data retentio program?()A、 The data destruction requirementsB、 The user awareness training programC、 The laws and legal requirements of the dataD、 The companys individual data retention policies

考题 Which of the following is the MOST important consideration when purchasing a new server for a mission critical application?()A、RAID 0 compliantB、Notifying all stakeholders of the server upgradeC、Service Level AgreementD、KVM access

考题 When doing capacity planning for the Virtual I/O Server,what is the most important  consideration?()A、The I/O workload needs of the client LPARsB、The processing requirements of the client LPARsC、The memory requirements of the client LPARsD、The virtual Ethernet requirements between client LPARs

考题 An administrator is creating a new data retention policy. Which of the following is the MOST important consideration?()A、Compile technical requirements for new policyB、Comply with applicable laws and regulationsC、Destroy the old data retention policyD、Have hard copies of the new policy stored offsite

考题 A customer has two single cluster IBM TS7700 Virtualization Engines at the same site. The customer wants to move one to a remote site and set up a grid configuration with the two clusters. The customer has fibre between the two sites. What is the most important factor to consider when planning the new configuration?()A、operator trainingB、cache size of the two clustersC、fibre bandwidth capability between the sitesD、number of stacked tape drives attached to each cluster

考题 An administrator is creating a redundant environment for a current data center. A backup site must be available if the entire data center site should become unavailable. To reduce costs, this backup site does not need to be up and running at all times ready for failover. It must contain equipment and the ability to restore data from the data center.  Which of the following site types should be considered to meet these requirements? ()A、 Hot siteB、 Warm siteC、 Cold siteD、 Active failover site

考题 Which of the following is the MOST important physical consideration when deploying a new server?()A、 Humidity monitors, Biometrics, and fire suppressionB、 Cooling, rack space, and power requirements冷C、 Service level agreements, uninterruptible power supply (UPS) deployment, and CCTVD、 Biometrics, fire suppression, and power requirements

考题 Which of the following is the MOST important physical consideration when deploying a new server?()A、Humidity monitors, Biometrics, and fire suppressionB、Cooling, rack space, and power requirementsC、Service level agreements, uninterruptible power supply (UPS) deployment, and CCTVD、Biometrics, fire suppression, and power requirements

考题 A customer is planning on establishing a Global Mirror between two Storwize V7000 storagearrays. The customer is planning to lease an IP WAN connection between sites for the tasks andis running a SAP (database) application on Oracle. Which of the following planning considerationsis most important?()A、the distance between sites needs to be less than 100 kilometersB、consistency groups should be created to maintain write order on the remote mirrorC、ensure sufficient bandwidth exists on the link based on average application workloadsD、ensuring a low round trip latency of less than 30ms on the WAN connection is required

考题 A customer has an IBM System Storage DS8700 at their primary site and an XIV system at their recovery site, which is 9.5 kilometers away. They want to replicate data for disaster recovery backup.  Which factor is a primary consideration when proposing a solution for this customer()A、compatibility of copy functionsB、difference in capacities in the two systemsC、cache size discrepancies between the two systemsD、the necessity of using two storage management products

考题 A new Disaster Recovery site has been established using Metro Mirror to hold synchronous data at both sites. After the Metro Mirror is started, one of the most important applications, a DB2 database, slows down. An analysis shows that the I/O rate (especially write I/Os) is less than 40% compared to the former rates.  What is the best explanation for this behavior()A、the bandwidth of the PPRC connection between the two sites is too smallB、the DS8000 SFI at the remote site was shipped with slower disksC、I/O rates vary, depending on the distance between the two sites and the rates cannot be changed easily, due to latencyD、the DB2 database does not work with Metro Mirror without an additional license

考题 单选题Which of the following is the MOST important consideration when looking at distance requirements when planning a hot site?()A Avoiding more expensive bandwidth costs for data lines between regionsB Avoiding a regional disaster that affects both the main site and the hot siteC Avoiding a second location that has high latency between sitesD Avoiding a location that is too expensive

考题 单选题Which of the following is the MOST important physical consideration when deploying a new server?()A  Humidity monitors, Biometrics, and fire suppressionB  Cooling, rack space, and power requirements冷C  Service level agreements, uninterruptible power supply (UPS) deployment, and CCTVD  Biometrics, fire suppression, and power requirements

考题 单选题Which of the following is the MOST important consideration when implementing a data retentio program?()A  The data destruction requirementsB  The user awareness training programC  The laws and legal requirements of the dataD  The companys individual data retention policies

考题 单选题When determining a customer’s technical requirements for a Cisco Unified Communications solution, which important tool can be used to determine the bandwidth used by different codecs with various protocols over different media?()A Network Codec Aggregator ToolB Bandwidth Estimator ToolC Unified Communication Bandwidth ToolD Voice Bandwidth CalculatorE Voice Codec Bandwidth Calculator

考题 单选题Which of the following is the MOST important data retention consideration when creating a backup system?()A Utilizing disk-to-disk clustering and hot site replicationB If the GFS backup system will cover all potential data breachesC The process to move the data backup to an offsite locationD The individual laws and legal requirements of the data

考题 单选题When planning the loading or discharging of a VLCC (100,000 DWT+) what is the most important consideration?()A Draft and trimB Limits of the bending momentsC Rate of dischargingD Rate of loading

考题 单选题When considering SAN to SAN replication between sites, which of the following is the MOST important concern?()A  WAN link speedB  Block sizeC  Disk sizeD  File system type

考题 单选题A customer has an IBM System Storage DS8700 at their primary site and an XIV system at their recovery site, which is 9.5 kilometers away. They want to replicate data for disaster recovery backup.  Which factor is a primary consideration when proposing a solution for this customer()A compatibility of copy functionsB difference in capacities in the two systemsC cache size discrepancies between the two systemsD the necessity of using two storage management products

考题 单选题When doing capacity planning for the Virtual I/O Server,what is the most important  consideration?()A The I/O workload needs of the client LPARsB The processing requirements of the client LPARsC The memory requirements of the client LPARsD The virtual Ethernet requirements between client LPARs