网友您好, 请在下方输入框内输入要搜索的题目:

题目内容 (请给出正确答案)
单选题
Why is it important to have a final meeting on a project that has been cancelled?()
A

Document lessons learned

B

Assign responsibility

C

Close budget

D

Begin new project


参考答案

参考解析
解析: 暂无解析
更多 “单选题Why is it important to have a final meeting on a project that has been cancelled?()A Document lessons learnedB Assign responsibilityC Close budgetD Begin new project” 相关考题
考题 You have summarized the project and note that , hours have been scheduled, , hours have been earned and , hours paid. The correct conclusion is:A.The project is operating at a favorable cost efficiency ratio.B.the project is spending more than plannedC.the project is behind scheduleD.the project is ahead of scheduleE.B and C

考题 During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:A . The project will be completed late.B . The critical path has been lengthened.C . the costs are being overrun.D . Overtime will be required to maintain the original critical path.E . None of the above.

考题 Of the following, who has the ultimate responsibility for meeting project quality objectives?A . Project EngineerB . Project ManagerC . Functional ManagerD . Quality Assurance ManagerE . Project Owner

考题 Which of the following tools and techniques can be used to collect information for the project closure reports?A Customer SurveysB BrainstormingC Document and Performance AnalysisD Lessons LearnedE All of the above

考题 The following reports are normally developed during the project closure phase?A Communications Management Plan and Lessons LearnedB Records Archive, Closure Report, lessons learned Formal Acceptance ReportC Records Archive, Closure Report, Specifications DocumentD Communications Management Plan and Closure reportE None of the above

考题 112 Of the following, who has the ultimate responsibility for meeting project quality objectives?A. Project EngineerB. Project ManagerC. Functional ManagerD. Quality Assurance ManagerE. Project Owner

考题 39 You have summarized the project and note that 28,000 hours have been scheduled, 25,000 hours have been earned and 26,000 hours paid. The correct conclusion is:A. The project is operating at a favorable cost efficiency ratio.B. the project is spending more than plannedC. the project is behind scheduleD. the project is ahead of scheduleE. B and C

考题 97 The following reports are normally developed during the project closure phase?A. Communications Management Plan and Lessons LearnedB. Records Archive, Closure Report, lessons learned Formal Acceptance ReportC. Records Archive, Closure Report, Specifications DocumentD. Communications Management Plan and Closure reportE. None of the above

考题 ● A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should(75).(75)A.assign change tasks to project membersB.call a meeting of the configuration control boardC.change the scope baselineD.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

考题 A project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should______.A.assign change tasks to project membersB.call a meeting of the configuration control boardC.change the scope baselineD.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

考题 The project requires more labor than ____ because it is extremely difficult. A.has been putB.have been putC.being put inD.to.be put in

考题 ●You have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. (75)document provides this information.(75) A. Resource assignment matrixB. Change control planC. Project charterD. Client organization chart

考题 The most crucial time for project risk assessment is (75) .A.when a problem surfacesSXB The most crucial time for project risk assessment is (75) .A.when a problem surfacesB.during the planning phaseC.during the close-out phaseD.after the project schedule has been published

考题 The most crucial time for project risk assessment is ( ).A.when a problem surfacesB.during the planning phaseC.during the close-out phaseD.after the project schedule has been published

考题 The scope management plan is how the team will prepare the()a document that includes descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.A.project charterB.project scope goalC.project budgetD.project scope statement

考题 The project requires more labor than ________.[A] has been put in[B] have been put in[C] being put in[D] to be put in

考题 A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( ) A.assign change tasks to project members B.call a meeting of the configuration control board C.change the scope baseline D. postpone the modification until a separate enhancement project is fundedafter this project is completed according to the original baseline

考题 ( )is a process developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.A.Develop Project Charter B.Manage Project Knowledge C.Monitor and Control Project work D.Close project

考题 The most crucial time for project risk assessment is ( ) . A.when a problem surfaces B.during the planning phase C.during the close-out phase D.after the project schedule has been published

考题 ( ) is a process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.A.Develop Project Charter B.Manage Project Knowledge C.Monitor anD.Control Project work D.Close project

考题 A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( ) . A.assign change tasks to project members B.call A.meeting of the configuration control board C.change the scope baseline D.postpone the modification until A.separate enhancement project is fundeD.after this project is completeD.according to the original baseline

考题 The most crucial time for project risk assessment is ( ).A、when a problem surfacesB、during the planning phaseC、during the close-out phaseD、after the project schedule has been published

考题 Why is it important to have a final meeting on a project that has been cancelled?()A、Document lessons learnedB、Assign responsibilityC、Close budgetD、Begin new project

考题 单选题Why is it important to have a final meeting on a project that has been cancelled?()A Document lessons learnedB Assign responsibilityC Close budgetD Begin new project

考题 单选题The most crucial time for project risk assessment is ( ).A when a problem surfacesB during the planning phaseC during the close-out phaseD after the project schedule has been published

考题 问答题Practice 8  ● You are a Project Team Leader. You have had to cancel your next project meeting because some of the members of your team will be abroad.  ● Write a memo to your project team:  ● informing them of the cancellation and giving the reason;  ● stating a new date and time for the meeting;  ● requesting suggestions for the agenda.  ● Write 40—50 words.

考题 单选题A solution provider has proposed a pSeries solution to a new customer.  The solution is complex with a number of technologies that are new to the customer. They have a tight timeline for implementation.  The solution provider has not been able to get a clear understanding as to how the customer will backup the system.  What would be the most appropriate action to address the risks with this solution?()A Sell SysbackB Conduct a SARC Sell SupportlineD Provide a project timeline

考题 单选题Why did Mr. Wilson write the memo?A To apply for a vacation during NovemberB To ask for an extension on the project deadlineC To get approval for a new research proposalD To explain why he will not attend a meeting