During this phase,the analyst must become fully aware of the ( )。

A.main symptom
B.root problem
C.final blueprint
D.datA.specification

参考答案

参考解析
解析:在这个分析阶段,系统分析师一定要充分注意到问题的根源。
A.主要症状 B.根本问题 C.最终蓝图 D.数据规范
更多 “ During this phase,the analyst must become fully aware of the ( )。 A.main symptom B.root problem C.final blueprint D.datA.specification ” 相关考题
考题 Typically, during which phase in a project life cycle are most of the project expenses incurred.A . Concept phaseB . Development of design phaseC . Execution phase.D . Termination phase.E . None of the above

考题 148 Network schedules are prepared during the _____ phase and updated during the _____ phase. A. Conceptual, execution.B. Development, implementation.C. Development, close-out.D. Implementation, close-out.E. Planning, finishing

考题 We prefer that the plan () before being put into execution. A.is fully discussedB.must be fully discussedC.be fully discussedD.will be fully discussed

考题 ● Many of the activities performed during the preliminary investigation are still being conducted in (71) , but in much greater depth than before. During this phase, the analyst must become fully aware of the (72) and must develop enough knowledge about the (73) and the existing systems to enable an effective solution to be proposed and implemented. Besides the (74) for process and data of current system, the deliverable from this phase also includes the (75) for the proposed system.(71)A. analysis phaseB. design phaseC. implementation phaseD. maintenance phase(72)A. main symptomB. root problemC. final blueprintD. data specification(73)A. hardware environmentB. testing environmentC. software environmentD. business environment(74)A. logical modelsB. physical modelsC. design modelsD. implementation models(75)A. hardware and software specificationB. system performance specificationC. formal requirements definitionD. general problem statement

考题 Many of the activities performed during the preliminary investigation are still being conducted in(71) , but in much greater depth than before. During this phase, the analyst must become fully aware of the(72) and must develop enough knowledge about the(73) and the existing systems to enable an effective solution to be proposed and implemented. Besides the(74) for process and data of current system, the deliverable from this phase also includes the(75) for the proposed system.A.analysis phaseB.design phaseC.implementation phaseD.maintenance phase

考题 In the event of any quarantinable diseases break out during its currency,this Certificate of Pratique shall become ________ ,and must be surrendered on demand to a quarantine officer.A.void and nullB.null and voidC.uselessD.unusable

考题 During an annual FCC inspection ______.A.All required documents and publications may have to be producedB.Licensed GMDSS radio operators may be required to demonstrate equipment competenciesC.All required equipment must be fully operationalD.All of the above

考题 Many of the activities performed during the preliminary investigation are still being conducted in( ), but in much greater depth than before. During this phase, the analyst must become fully aware of the ( )and must develop enough knowledge about the ( ) and the existing systems to enable an effective solution to be proposed and implemented. Besides the (4)for process and data of current system, the deliverable from this phase also includes the ( )for the proposed system. (4)应选( )。 A. logical moD.els B. physical moD.els C. D.esign moD.els D.. implementation moD.els

考题 During the systems planning phase. a systems analyst conducts a( )activity to study the systems request and recommend specific action. After obtaining an authonzation to proceed. the analyst interacts with(请作答此空) to gather facts about the problem of opportunity, project scope and constraints, project benefits, and estimated development time and costs. In many cases. thesystems request does not reveal the underying problem, but only a symptom. A popular technique for investigating causesand effects is called ( )The analyst has analyzed the problem or opportunity. defined the project scope and constraints, and performed ( )to evaluate project usability, costs, benefits, and time constraints. The end product of the activity is ( ) .The main content must include an estimate of time .staffing requrements, costs, benefits, and expected results for the next phase of the SDLCA.system users B.system owner C.managers anD.users D.business analysts

考题 Many of the activities performed during the preliminary investigation are still being conducted in ____, but in much greater depth than before.A.analysis phase B.design phase C.implementation phase D.maintenance phase

考题 During this phase, the analyst must become fully aware of the __请作答该选项__ and must develop enough knowledge about the ____ and the existing systems to enable an effective solution to be proposed and implementeD.A.main symptom B.root problem C.final blueprint D.datA.specification

考题 The purpose of the systems analysis phase is to build a logical model of the new system.The first step is(71),where you investigate business processes and document what the new system must do to satisfy users. This step continues the investigation that began during the(72). You use the fact-finding results to build business models,data and process models,and object models. The deliverable for the systems analysis phase is the(73),which describes management and user requirements,costs and benefits,and outlines alternative development strategies.The purpose of the systems design phase is to create a physical model that will satisfy all documented requirements for the system. During the systems design phase,you need to determine the(74),which programmers will use to transform the logical design into program modules and code. The deliverable for this phase is the(75),which is presented to management and users for review and approval.A.system charter B.system scope definition C.system blueprint D.system requirements document

考题 The purpose of the systems analysis phase is to build a logical model of the new system.The first step is(71),where you investigate business processes and document what the new system must do to satisfy users. This step continues the investigation that began during the(72). You use the fact-finding results to build business models,data and process models,and object models. The deliverable for the systems analysis phase is the(73),which describes management and user requirements,costs and benefits,and outlines alternative development strategies.The purpose of the systems design phase is to create a physical model that will satisfy all documented requirements for the system. During the systems design phase,you need to determine the(74),which programmers will use to transform the logical design into program modules and code. The deliverable for this phase is the(75),which is presented to management and users for review and approval.A.systems planning phase B.systems modeling phase C.systems analysis phase D.systems design phase

考题 During this phase, the analyst must become fully aware of the ____ and must develop enough knowledge about the __请作答该选项__ and the existing systems to enable an effective solution to be proposed and implementeD.A.hardware environment B.testing environment C.software environment D.business environment

考题 During this phase,the analyst must must develop enough knowledge about the ( )and the existing systems to enable an effective solution to be proposed and implemented. A.hardware environment B.testing environment C.software environment D.business environment

考题 The most crucial time for project risk assessment is ( ) . A.when a problem surfaces B.during the planning phase C.during the close-out phase D.after the project schedule has been published

考题 Many of the activities performed during the preliminary investigation are still being conducted in ( ), but in much greater depth than before. A.analysis phase B.design phase C.implementation phase D.maintenance phase

考题 During which phase of the boot process is the rootvg volume group varied on and the root file system (hd4) checked?()  A、Boot phase 1B、Boot phase 2C、Boot phase 3D、Boot phase 4

考题 During which boot phase is the rootvg first activated()A、Phase 1B、Phase 2C、Phase 3D、POST Phase

考题 单选题During an annual FCC inspection().A All required documents and publications may have to be producedB Licensed GMDSS radio operators may be required to demonstrate equipment competenciesC All required equipment must be fully operationalD All of the above

考题 单选题During which boot phase is the rootvg first activated()A Phase 1B Phase 2C Phase 3D POST Phase

考题 单选题Many of the activities performed during the preliminary investigation are still being conducted in(1),but in much greater depth than before. During this phase, the analyst must become fully aware of the(2)and must develop enough knowledge about the(3)and the existing systems to enable an effective solution to be proposed and implemented. Besides the(4)for process and data of current system, the deliverable from this phase also includes the(5)for the proposed system.A hardware and software specificationB system performance specificationC formal requirements definitionD general problem statement

考题 单选题Hydraulic cranes must be properly warmed-up before being operated because ().A warm-up allows the hydraulic system to become charged with oilB warm-up allows the relief valves to be properly testedC hydraulic strainers operate only during the warm-up periodD hydraulic fluid must be at the proper viscosity

考题 单选题I’m not fully aware()what happened at the loading port.A atB toC ofD about

考题 单选题The word appreciate in line 7 most nearly means ______.A admireB be grateful forC be fully aware ofD increase in valueE test

考题 单选题The patient was fully _____ during the operation.A liberalB sensibleC awareD conscious

考题 单选题Many of the activities performed during the preliminary investigation are still being conducted in(1),but in much greater depth than before. During this phase, the analyst must become fully aware of the(2)and must develop enough knowledge about the(3)and the existing systems to enable an effective solution to be proposed and implemented. Besides the(4)for process and data of current system, the deliverable from this phase also includes the(5)for the proposed system.A logical modelsB physical modelsC design modelsD implementation models