the ( ) is primarily concerned with acceptance of the deliverables.while quality control is primarily concerned with correctness of the deliverables and meeting the quality requirements specified for the deliverables.

A.verify scope
B.define scope
C.quality assurance
D.validate scope

参考答案

参考解析
解析:翻译:验证范围主要涉及的是交付验收。而质量控制主要关注的是项目可交付成果的正确性和满足规定的质量要求交付。A.验证范围 B.定义范围 C.质量保证 D.确认范围
更多 “the ( ) is primarily concerned with acceptance of the deliverables.while quality control is primarily concerned with correctness of the deliverables and meeting the quality requirements specified for the deliverables. A.verify scope B.define scope C.quality assurance D.validate scope ” 相关考题
考题 Cost of quality is:A . associated with non-conformance to specifications and requirements.B . primarily caused by poor workmanship of workers who are building or manufacturing the product.C . used to determine whether a quality management program is suitable for a given project.D . negligible for most large projects.E . A and B

考题 Quality management:A . is another name for careful inspections.B . is inversely related to productivity.C . is primarily the responsiblity of management.D . is primarily the responsibility of the workers.E . is essentially a motivational technique.

考题 ● The project (73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.(73)A. work performance informationB. scope statementC. change requestsD. process analysis

考题 83 Quality management:A. is another name for careful inspections.B. is inversely related to productivity.C. is primarily the responsiblity of management.D. is primarily the responsibility of the workers.E. is essentially a motivational technique.

考题 89 Cost of quality is:A. associated with non-conformance to specifications and requirements.B. primarily caused by poor workmanship of workers who are building or manufacturing the product. C. used to determine whether a quality management program is suitable for a given project. D. negligible for most large projects.E. A and B

考题 165 Quality management:A. is another name for careful inspections.B. is inversely related to productivity.C. is primarily the responsiblity of management.D. is primarily the responsibility of the workers.E. is essentially a motivational technique

考题 ● (73)is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.(73)A. Quality assurance (QA)B. Quality planningC. Quality control (QC)D. Quality costs

考题 The project()is a key input to quality planning since it documents major project deliverables,the project objectives that serve to define important stakeholder requirements,thresholds,and acceptance criteriaA.work performance informationB.scope statementC.change requestsD.process analysis

考题 ______is the application of planned,systematic quality activities to ensure that the project will employ all processes needed to meet requirements.A.euality assurance(QA)B.Quality planningC.Quality control(QC)D.Quality costs

考题 ● ()is the application ion of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.()A. Quality assurance (QA) B. Quality planningC. Quality control (QC) D. Quality costs

考题 ●Quality management(74).(74) A. is another name for careful inspectionsB. is inversely related to productivityC. is primarily the responsibility of managementD. is primarily the responsibility of the workers

考题 The project(73)is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.A.work performance informationB.scope statementC.change requestsD.process analysis

考题 Managerial accounting is primarily concerned with the recording and reporting of economic data and activities of an entity for use by owners, creditors, governmental agencies, and the public.()

考题 A goal of the()process is to determine the correctness of deliverables. A.Perform. Quality AssuranceB.Plan Quality ManagementC.Control QualityD.Perform. Quality Improvement

考题 ()seeks to build confidence that a future output or an unfinished output, will be completed in a manner that meets the specified requirements and expectations.A.Quality assuranceB.Quality planC.Quality controlD.Quality metrics

考题 the () is primarily concerned with acceptance of the deliverables.while quality control is primarily concerned with correctness of the deliverables and meeting the quality requirements specified for the deliverablesA.verify scopeB.define scopeC.quality assuranceD.validate scope

考题 In all projects,needs must be tempered by schedule,cost and resource constraints.Project success depends primarily on (74)A.the quality of the schedule and cost control analysisB.customer satisfactionC.customer compromise in defining its needsD.exceeding customer requirements through gold-plating

考题 A goal of the ( ) process is to determine the correctness of deliverables.A.Perform Quality Assurance B.Plan Quality Management C.Control Quality D.Perform Quality Improvement

考题 ( ) is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.A.Quality assurance(QA) B.Quality planning C.Quality control(QC) D.Quality costs

考题 ()is the application of planned,systematic quality activities to ensure thatthe project will employ all processes needed to meet requirements.A.Quality assurance(QA) B.Quality planning C.Quality control(QC) D.Quality costs

考题 Project success depends primarily on() 。A.The quality of the schedule and cost control analysis B.Customer satisfaction C.Customer compromise in defining its needs D.Exceeding customer requirements through gold-plating

考题 ()seeks to build confidence that a future output or an unfinished output, will be completed in a manner that meets the specified requirements and expectations. A.Quality assurance B.Quality plan C.Quality control D.Quality metrics

考题 A goal of the( )process is to determine the crrectnes of deliverables.A.Perform Quality Asurance B.Plan Quality Management C.Control Quality D.Perform Quality Improvement

考题 The()process differs from the()process in that the former is primarily concerned with acceptance of the deliverables,while the latter is primarily concerned with acceptance of the deliverables,while the latter is primarily concerned with correctness of the deliverables.A.perform Quality Assurance B.Validate Scope C.Control Quality D.Define Scope

考题 ( )seeks to buildconfidence that a future output or an unfinished output, will be completed in amanner that meets the specified requirements and expectations. A.Quality assurance B.Quality plan C.Quality control D.Quality metrics

考题 单选题The author of the passage is primarily concerned with _____.A summarizing a thesisB recommending a different approachC comparing points of viewD making a series of predictions

考题 单选题The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.A work performance informationB scope statementC changerequestsD process analysis