Which of the following best describes Simultaneous Multi-threading (SMT)?()
A

A POWER5 microprocessor feature that allocates two processors to each application

B

A Workload Manager feature that allows two processing threads to be executing on a single processor

C

An AIX v5.2 feature that allows two processing threads to be executing on a single processor concurrently

D

A POWER5 microprocessor feature that allows two processing threads to be executing on a single processor concurrently


参考答案

参考解析
解析: 暂无解析
更多 “单选题Which of the following best describes Simultaneous Multi-threading (SMT)?()A A POWER5 microprocessor feature that allocates two processors to each applicationB A Workload Manager feature that allows two processing threads to be executing on a single processorC An AIX v5.2 feature that allows two processing threads to be executing on a single processor concurrentlyD A POWER5 microprocessor feature that allows two processing threads to be executing on a single processor concurrently” 相关考题
考题 单选题After visiting several customers, the pSeries technical specialist returns to the office late in the day and makes a list of the various customer requests.  The specialist decided to complete at least one task before leaving for the day.  Which of the following is most important to complete immediately?()A Send a flyer on new p5-520. B Provide shipment delivery status.C Order a new system per the purchase order.D Retrieve and send a whitepaper on SCSI performance.

考题 单选题A customer plans to purchase a p5-570 that will run in SMP mode to host a large financial database on AIX 5.2.  The application is sized for an 8-way 1.65-GHz machine.  They do not currently have an existing HMC that supports p5 machines. This organization experiences unpredictable short-term spikes in processor utilization.  To mitigate the risk to their business, they are interested in IBM’s CoD offering.  In addition to the 8-way system, what else should the pSeries technical specialist recommend to the customer?()A Another p5-570 building blockB Capacity Backup p5-570 building blockC Another p5-570 building block and at least one HMCD Capacity Backup p5-570 building block and at least one HMC

考题 单选题Which of the following best describes what is meant by Linux Affinity on AIX?()A The ability to install a Linux system on an AIX systemB The ability to install an AIX system on a Linux systemC The ability to compile and run a Linux application on AIXD The ability to compile and run an AIX application on Linux

考题 单选题After visiting several customers, the pSeries technical specialist returns to the office late in the day and makes a list of the various customer requests.  The specialist decided to complete at least one task before leaving for the day.  Which of the following is most important to complete immediately?()A Send a flyer on new p5-520. B Provide shipment delivery status.C Order a new system per the purchase order.D Retrieve and send a whitepaper on SCSI performance.

考题 单选题The pSeries technical specialist has been asked to verify a solution that has six servers connecting to a 7316-TF3 rack-mounted flat-panel console.   Each server will connect into the 4202 Keyboard/Video/Mouse (LCM Switch).   What is the minimum number of KVM Conversion Cable Options (FC 4268) required to complete this installation?()A 1B 2C 6D 8

考题 单选题The account team is putting together a very complex solution for the customer.  During the solution design phase, many of the customer’s requirements have changed and additional requirements are being identified.  What should the pSeries technical specialist do to ensure the greatest possible customer satisfaction?()A Use eConfig to configure and validate each pSeries and p5 system.B Engage Advanced Technical Support to review any outstanding technical issues.C Confirm with the customer that the solution design meets their requirements.D Perform a Pre-Install Solution Assurance Review to validate required power requirements.

考题 单选题Due to slow response times, a customer purchased additional memory. After the memory was installed,response time was not improved.  They complained to the pSeries technical specialist. Which of the following questions should be asked of this customer?()A Who recommended the memory purchase?B Have more users been added since the memory purchase?C Why were additional CPUs not ordered at the same time as the memory?D Did a performance analysis of peak periods show a memory bottleneck?

考题 单选题A state agency has recently deployed a new application on an 8-way p5-570 that is critical to the agency’s operation.  There is no manual method to perform the business process.  The state government has just mandated that all state agencies have disaster recovery plans that allow the agencies to recover critical applications in acceptable periods of time with no loss of performance. Based on this new business requirement, what is this agency most likely to need?()A HACMP and four processors for the p5-570B HACMP and eight processors for the p5-570C HACMP-XD and a 4-way p5-570 in a second locationD HACMP-XD and a 8-way p5-570 in a second location

考题 单选题A customer is planning to migrate a financial application to a 12-way p5-570 system with 96GB of memory.  The application data is stored on an ESS Model 800 attached to a p670 server with AIX 5.2.  They will have a short outage window to perform the data migration.  What is the quickest way to move all the data stored on the attached ESS from the p670 to the new p5-570?()A Use rsync to synchronize the data across servers.B Use exportvg and importvg to move the data to the target system.C Use NFS to copy the data from the source system to the target system.D Backup the data from the source system and restore to the target system.

考题 单选题A customer is getting ready to install a new pSeries system into their data center.  They are concerned about providing the appropriate clearance around their 7014-T42 to allow for maintenance.  What reference material should the pSeries technical specialist provide to the customer?()A Sales ManualB Announcement LetterC Site and Hardware Planning InformationD Adapter, Devices, and Cable Information for Multiple Bus Systems