Parametric estimates are based on variables such as:

A.Detailed planning and cost restraints.

B.Physical characteristics and historical data.

C.The WBS and similar projects.

D.Project objectives and manpower allocations.

E.Precise measurements and multiple inputs.


参考答案

更多 “ Parametric estimates are based on variables such as:A.Detailed planning and cost restraints.B.Physical characteristics and historical data.C.The WBS and similar projects.D.Project objectives and manpower allocations.E.Precise measurements and multiple inputs. ” 相关考题
考题 Statistical cost estimating techniques (based upon history), are called _____ estimates and are a _____ approach.A . Definitive, bottom up.B . Analogy, top down.C . Parametric, bottom up.D . Parametric, top down.E . Analogy, bottom up.

考题 The three most common types of project cost estimates are:A . Order of magnitude, parametric, and budget.B . Parametric, definitive and top down.C . Order of magnitude, definitive and bottom up.D . Order of magnitude, budget and definitive.E . Analogy, parametric and top down.

考题 Which of the following constitute Juran's "quality trilogy":A . planning, inspection, control.B . planning, improvement, control.C . planning, organization, control.D . product, price, customer.E . design, build, deliver.

考题 123 Which of the following constitute Juran's "quality trilogy":A. planning, inspection, control.B. planning, improvement, control.C. planning, organization, control.D. product, price, customer.E. design, build, deliver.

考题 140 The three most common types of project cost estimates are:A. Order of magnitude, parametric, and budget.B. Parametric, definitive and top down.C. Order of magnitude, definitive and bottom up.D. Order of magnitude, budget and definitive.E. Analogy, parametric and top down

考题 168 Statistical cost estimating techniques (based upon history), are called _____ estimates and are a _____ approach.A. Definitive, bottom up.B. Analogy, top down.C. Parametric, bottom up.D. Parametric, top down.E. Analogy, bottom up

考题 5 Which of the following constitute Juran's "quality trilogy":A. planning, inspection, control.B. planning, improvement, control.C. planning, organization, control.D. product, price, customer.E. design, build, deliver.

考题 22 The three most common types of project cost estimates are:A. Order of magnitude, parametric, and budget.B. Parametric, definitive and top down.C. Order of magnitude, definitive and bottom up.D. Order of magnitude, budget and definitive.E. Analogy, parametric and top down

考题 50 Statistical cost estimating techniques (based upon history), are called _____ estimates and are a _____ approach.A. Definitive, bottom up.B. Analogy, top down.C. Parametric, bottom up.D. Parametric, top down.E. Analogy, bottom up.

考题 A variety of tools is available to help the analyst to discover the users' true needs.These tools are grouped into three broad techniques that are based on the degree of change anticipated in the to-be system . Business process(71) is used when the basic business Requirements outlined in the system request focus on employing computer technology in some aspect of the business process. Two popular activities used in the technique are(72). Business process(73)means that the basic business requirements target moderate changes to the organization' s operations. (74)are three popular activities in the technique. Business process (75)means changing the current way of doing business and making major changes to take advantage of new ideas and new technology.A. Duration analysis,activity-baseD.costing anD.informal bench marking B.Outcome analysis, technology analysis anD.activity elimination C.Problem analysis, root cause analysis anD.critical path analysis D.Cost-benefit analysis, schedule analysis anD.risk analysis