12 The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.

A. Conceptual, charter/baseline.

B. Conceptual, master schedule.

C. Development, charter/baseline.

D. Development, master schedule.

E. Development, masterplan


参考答案

更多 “ 12 The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.A. Conceptual, charter/baseline.B. Conceptual, master schedule.C. Development, charter/baseline.D. Development, master schedule.E. Development, masterplan ” 相关考题
考题 In preparing a good project definition, experienced project managers will:AConcentrate mainly on the end product rather than costs or benefits. These come later.BRealize that only the "tip of the iceberg" may be showing. As a project manager, you must get beneath it.CUnderstand that a project definition/plan is a dynamic rather than static tool, and thus subject to change.DTry to convert objectives into quantifiable terms.EAll of the above

考题 Creation of project objectives:A.allows for data collection and analysis and progress reporting against which standards of performance can be measured.B.is accomplished by selection of measurable variables against which performance can be judged.C.is required before funding of the project by the project sponsor.D.all of the above.E.A and B only

考题 The project charter:A.Expresses upper management commitment to the project.B.Provides that authority by which the project will be run.C.Establishes that organizational structure with the project.D.Specifies overall objectives and timeframe. of the project.E.All of the above.

考题 The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.A.Conceptual, charter/baseline.B.Conceptual, master schedule.C.Development, charter/baseline.D.Development, master schedule.E.Development, masterplan.

考题 The process of choosing/documenting the best approach to achieve the project objectives is part of:A.The scope baseline.B.Scope authorizationC.Scope definitionD.Scope planning.E.All of the above.

考题 The quality objectives are approved in the conceptual stage of the project by the:A . Project EngineerB . Project ManagerC . Functional ManagerD . Quality Assurance ManagerE . Project Owner

考题 Of the following, who has the ultimate responsibility for meeting project quality objectives?A . Project EngineerB . Project ManagerC . Functional ManagerD . Quality Assurance ManagerE . Project Owner

考题 The purpose of project Risk Management is to:A Identify those factors that will adversely impact project objectives.B Assess the impact of adverse project factors.C Assess the probability of adverse project factors.D A and CE All of the above.

考题 78 The process of choosing/documenting the best approach to achieve the project objectives is part of: A. The scope baseline.B. Scope authorizationC. Scope definitionD. Scope planning.E. All of the above.

考题 130 The identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives are indentified in the _____ phase of the project but first documented in the project _____.A. Conceptual, charter/baseline.B. Conceptual, master schedule.C. Development, charter/baseline.D. Development, master schedule.E. Development, masterplan

考题 35 The project charter:A. Expresses upper management commitment to the project.B. Provides that authority by which the project will be run.C. Establishes that organizational structure with the project.D. Specifies overall objectives and timeframe. of the project.E. All of the above

考题 85 The purpose of project Risk Management is to:A. Identify those factors that will adversely impact project objectives.B. Assess the impact of adverse project factors.C. Assess the probability of adverse project factors.D. A and CE. All of the above

考题 112 Of the following, who has the ultimate responsibility for meeting project quality objectives?A. Project EngineerB. Project ManagerC. Functional ManagerD. Quality Assurance ManagerE. Project Owner

考题 120 The Work Breakdown Structure (WBS) is the basis for communicating:A. Project scope, cost control, schedule, qualityB. Project objectives, dependencies, plan, cost controlC. Project scope, schedule, staffing, cost controlD. Project scope, quality, schedule, dependenciesE. Project budget, schedule, risk factors, work assignments

考题 121 The quality objectives are approved in the conceptual stage of the project by the:A. Project EngineerB. Project ManagerC. Functional ManagerD. Quality Assurance ManagerE. Project Owner

考题 193 Creation of project objectives:A. allows for data collection and analysis and progress reporting against which standards of performance can be measured.B. is accomplished by selection of measurable variables against which performance can be judged. C. is required before funding of the project by the project sponsor.D. all of the above.E. A and B only

考题 97 In preparing a good project definition, experienced project managers will:A. Concentrate mainly on the end product rather than costs or benefits. These come later.B. Realize that only the "tip of the iceberg" may be showing. As a project manager, you must get beneath it.C. Understand that a project definition/plan is a dynamic rather than static tool, and thus subject to change.D. Try to convert objectives into quantifiable terms.E. All of the above

考题 109 Problems can occur in properly defining a project because:A. Project goals may not be agreeable to all partiesB. The plan was "too loose," thus allowing priorities to changeC. Low turnover of project personnelD. Too much communication between the client and project personnelE. The project objectives were quantified

考题 160 The process of choosing/documenting the best approach to achieve the project objectives is part of:A. The scope baseline.B. Scope authorizationC. Scope definitionD. Scope planning.E. All of the above

考题 ● Problems can occur in properly defining a project because:A Project goals may not be agreeable to all partiesB The plan was "too loose," thus allowing priorities to changeC Low turnover of project personnelD Too much communication between the client and project personnelE The project objectives were quantified

考题 ● In preparing a good project definition, experienced project managers will:A Concentrate mainly on the end product rather than costs or benefits. These come later.B Realize that only the "tip of the iceberg" may be showing. As a project manager, you must get beneath it.C Understand that a project definition/plan is a dynamic rather than static tool, and thus subject to change.D Try to convert objectives into quantifiable terms.E All of the above

考题 ● The Work Breakdown Structure (WBS) is the basis for communicating:A Project scope, cost control, schedule, qualityB Project objectives, dependencies, plan, cost controlC Project scope, schedule, staffing, cost controlD Project scope, quality, schedule, dependenciesE Project budget, schedule, risk factors, work assignments.

考题 ● The project charter:A Expresses upper management commitment to the project.B Provides that authority by which the project will be run.C Establishes that organizational structure with the project.D Specifies overall objectives and timeframe. of the project.E All of the above.

考题 ● The process of choosing/documenting the best approach to achieve the project objectives is part of:A The scope baseline.B Scope authorizationC Scope definitionD Scope planning.E All of the above.

考题 The( )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables. A、project scope statementB、work packageC、WBSD、project scope plan

考题 The()is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.A.Project scope statement B.Work package C.WBS D.Project scope plan

考题 Project Quality Management processes include all the activities of the()that determine quality policies, objectives and responsibilities so that the project will satisfy theneeds for which it was undertaken.A、ProjectB、project management teamC、performingorganizationD、customer