The leader ordered that the task_____________ as soon as possible.

A、finishes

B、is finished

C、finish

D、be finished


参考答案

更多 “ The leader ordered that the task_____________ as soon as possible.A、finishesB、is finishedC、finishD、be finished ” 相关考题
考题 In the PDM, common constraints include:A.Start-to-startB.Finish-to-startC.Finish-to-finishD.B and C onlyE.A, B, and C.

考题 PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity. A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

考题 PDM includes four types of dependencies or precedence relation ships:(73)The completion of the successor activity depends upon the initiation of the predecessor activity.A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

考题 PDM includes four types of dependencies or precedence relationships.( ),the initiation of the successor activity,depends upon the initiation ofthe predecessor activity. A.Start-to-Start B.Finish-to-Finish C.Start-to-Finish D.Finish-to—Start

考题 By the time Robert()writing the first draft of his paper, most of the other students will be completing their final draft.A、finishesB、has finishedC、finishedD、finishing

考题 PDM includes four types of dependencies or precedence relationships…(73),the initiation of the successor activity,depends upon the initiation of the predecessor activity.A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

考题 PDM includes four types of dependencies or precedence relationships: ...(18). The completion of the successor activity depends upon the initiation of the predecessor activity.A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

考题 ● Precedence Diagramming Method (PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called __(75)__.(75)A.Finish-to-StartB.Finish-to-FinishC.Start-to-StartD.Start-to-Finish

考题 Precedence Diagramming Method(PDM) is a method used in activity sequencing. There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called ( ). A.Finish-to-Start B.Finish-to-Finish C.Start-to-Start D.Start-to-Finish