Which of the following can deploy system plans generated by the IBM System Planning Tool (SPT)?()

  • A、 The Hardware Management Console (HMC) and Integrated Virtualization Manager (IVM).
  • B、 The Hardware Management Console (HMC) and Advanced System Manager Interface (ASMI).
  • C、 Integrated Virtualization Manager (IVM) and Advanced System Manager Interface (ASMI).
  • D、 Integrated Virtualization Manager (IVM) and BladeCenter Advanced Management Module (AMM).

参考答案

更多 “Which of the following can deploy system plans generated by the IBM System Planning Tool (SPT)?()A、 The Hardware Management Console (HMC) and Integrated Virtualization Manager (IVM).B、 The Hardware Management Console (HMC) and Advanced System Manager Interface (ASMI).C、 Integrated Virtualization Manager (IVM) and Advanced System Manager Interface (ASMI).D、 Integrated Virtualization Manager (IVM) and BladeCenter Advanced Management Module (AMM).” 相关考题
考题 Which of the following tools can be used to configure the IBM System Storage DS8000? () A. IBM Systems DirectorB. Unisphere Management SuiteC. IBM System Storage Productivity Center (SSPC)D. IBM Standalone Solutions Configuration Tool (SSCT)

考题 Using the following information: Performance data from an existing system that a new system will replace; Performance estimates that anticipate future workloads; Micro-partitioning and logical partitioning implementations. Which of the following allows a technical sales representative to create a system design which can be imported into an HMC?()A、IBMeConfigB、IBM Performance MonitorC、IBM Workload Estimator (WLE)D、IBM System Planning Tool (SPT)

考题 Which of the following would be the correct location to access when enabling Driver Signature Verification?()A、On the hardware tab in System Properties.B、In the Security Center applet in Control Panel.C、In Device Manager under the File menu and options.D、In Computer Management.

考题 Which of the following tools can be used to configure the IBM System Storage DS8000? ()A、IBM Systems DirectorB、Unisphere Management SuiteC、IBM System Storage Productivity Center (SSPC)D、IBM Standalone Solutions Configuration Tool (SSCT)

考题 A customer has an entry level Power System that is currently partitioned and managed by a Hardware Management Console (HMC). For operational reasons, it must be disconnected from the HMC and configured as a new development system.  How should the customer proceed to implement PowerVM Express and Integrated Virtualization Manager (IVM) on this Power System? ()A、 Install a VIO server as an additional partition and DLPAR the resources from the existing partition to the VIO server.B、 Create a service partition and install a VIO server. This will automatically move resources to the VIO server on reboot of the managed system.C、 Delete all the existing LPARs, create a new LPAR and assign all the system resources to this LPAR and then install the VIO server on this LPAR.D、 Reset the machine to Manufacturing Default Configuration and install the VIO server on the resulting partition created, which will own all system resources.

考题 An administrator wants to query the CPU resources of the managed system 9117-MMA*6512345 from the Hardware Management Console (HMC) command line.  Which of the following HMC commands could achieve this?()A、 lssysres -r cpu -m 9117-MMA*6512345 -r sysB、 lssyscfg -r proc -m 9117-MMA*6512345 -r sysC、 lshwres -r proc -m 9117-MMA*6512345 --level sysD、 lshwcfg -r proc -m 9117-MMA*6512345 --level sys

考题 A Power Systems customer would like to upgrade their HMC to the latest version of software tosupport a new hardware feature. What resource will help identify dependencies for firmware and system software for their upgrade?()A、ITSO RedbooksB、Facts and FeaturesC、System Planning ToolD、Fix Level Recommendation Tool

考题 Prior to implementing an LPAR system, which of the following needs to be done?()A、A graphics monitor must be attached to the serverB、Cluster System Management (CSM) software must be installedC、The LPAR system must have an Hardware Management Console (HMC) connectedD、Each LPAR must be configured with a CDROM for operating system installation

考题 Which of the following functions can be performed using the Integrated Virtualization Manager?()A、Concurrent firmware updatesB、Management of virtual storageC、Hot add/remove of I/O drawersD、Management of Capacity on Demand

考题 Which of the following statements is true regarding implementing Live Partition Mobility on two existing POWER6 based systems?()A、The systems must use internal storage for boot purposes. B、All virtualized ethernet adapters must be numbered below 10. C、The mobile partition's network and disk access must be virtualized. D、Each system must be controlled by a different Hardware Management Console (HMC). 

考题 Which of the following can be used to re-deploy a system configuration in a disaster recovery scenario?()A、System planB、System profileC、Critical console dataD、VIO server partition profile

考题 Which one of these statements is true regarding hot pluggable PCIe and PCI-X slots in a Power 550?()A、Cards can be added and then enabled via Hardware Management Console (HMC) GUI or command line. B、The HMC allows access to the Advanced System Management Interface (ASMI), where the slots can be managed. C、If the empty slot was already allocated to an LPAR, the LPAR can use the card after the cfgmgr script has been run. D、The Hardware Management Console (HMC) GUI can guide a customer through the process of adding a card to an empty slot. 

考题 Which of the following interfaces is required to implement Workload Partition Mobility? ()A、 Workload Partitions Manager for AIXB、 Hardware Management Console (HMC) GUIC、 Integrated Virtualization Manager (IVM)D、 Advanced System Management Interface (ASMI)

考题 Which of the following is a feature of Integrated Virtualization Manager (IVM)? ()A、 It has a GUI interface for upgrading system firmware. B、 It creates and manages AIX/Linux and VIOS type LPARs. C、 It can be managed by the Hardware Management Console (HMC). D、 It supports Live Partition Mobility on POWER6 systems and above.

考题 Company.com would like to have the processor resources on their system efficiently shared between logical partitions, but does not require management of memory or I/O resources. Which of the following would accomplish this requirement?()A、HMC command lineB、Uncapped processorsC、Partition Load ManagerD、Enterprise Workload Manager

考题 Which IBM System Director task will give you the ability to update firmware and device drivers on System x servers?()A、 Remote Supervisor Adapter (RSA II)B、 Integrated Management Module (IMM)C、 Update ManagerD、 Tivoli Provisioning Manager for OSDeployment (TPMfOSD)

考题 A service fails to start. Which of the following places can a technician go to find the services console?()A、System configuration utilityB、Device ManagementC、Task ManagerD、Computer Management

考题 单选题Prior to implementing an LPAR system, which of the following needs to be done?()A A graphics monitor must be attached to the serverB Cluster System Management (CSM) software must be installedC The LPAR system must have an Hardware Management Console (HMC) connectedD Each LPAR must be configured with a CDROM for operating system installation

考题 单选题Which of the following can deploy system plans generated by the IBM System Planning Tool (SPT)?()A  The Hardware Management Console (HMC) and Integrated Virtualization Manager (IVM).B  The Hardware Management Console (HMC) and Advanced System Manager Interface (ASMI).C  Integrated Virtualization Manager (IVM) and Advanced System Manager Interface (ASMI).D  Integrated Virtualization Manager (IVM) and BladeCenter Advanced Management Module (AMM).

考题 单选题Which one of these statements is true regarding hot pluggable PCIe and PCI-X slots in a Power 550?()A Cards can be added and then enabled via Hardware Management Console (HMC) GUI or command line. B The HMC allows access to the Advanced System Management Interface (ASMI), where the slots can be managed. C If the empty slot was already allocated to an LPAR, the LPAR can use the card after the cfgmgr script has been run. D The Hardware Management Console (HMC) GUI can guide a customer through the process of adding a card to an empty slot. 

考题 单选题Which of the following statements is true regarding implementing Live Partition Mobility on two existing POWER6 based systems?()A The systems must use internal storage for boot purposes. B All virtualized ethernet adapters must be numbered below 10. C The mobile partition's network and disk access must be virtualized. D Each system must be controlled by a different Hardware Management Console (HMC). 

考题 单选题Which of the following interfaces is required to implement Workload Partition Mobility? ()A  Workload Partitions Manager for AIXB  Hardware Management Console (HMC) GUIC  Integrated Virtualization Manager (IVM)D  Advanced System Management Interface (ASMI)

考题 单选题Which of the following statements is true regarding implementing Live Partition Mobility on two existing POWER6 based systems? ()A  The systems must use internal storage for boot purposes.B  All virtualized Ethernet adapters must be numbered below 10.C  The mobile partition’s network and disk access must be virtualized.D  Each system must be controlled by a different Hardware Management Console (HMC).

考题 单选题Which of the following is a feature of Integrated Virtualization Manager (IVM)? ()A  It has a GUI interface for upgrading system firmware. B  It creates and manages AIX/Linux and VIOS type LPARs. C  It can be managed by the Hardware Management Console (HMC). D  It supports Live Partition Mobility on POWER6 systems and above.

考题 单选题An administrator wants to query the CPU resources of the managed system 9117-MMA*6512345 from the Hardware Management Console (HMC) command line.  Which of the following HMC commands could achieve this?()A  lssysres -r cpu -m 9117-MMA*6512345 -r sysB  lssyscfg -r proc -m 9117-MMA*6512345 -r sysC  lshwres -r proc -m 9117-MMA*6512345 --level sysD  lshwcfg -r proc -m 9117-MMA*6512345 --level sys

考题 单选题Using the following information: Performance data from an existing system that a new system will replace; Performance estimates that anticipate future workloads; Micro-partitioning and logical partitioning implementations.  Which of the following allows a technical sales representative to create a system design which can be imported into an HMC?()A IBM eConfigB IBM Performance MonitorC IBM Workload Estimator (WLE)D IBM System Planning Tool (SPT)

考题 单选题A customer has an entry level Power System that is currently partitioned and managed by a Hardware Management Console (HMC). For operational reasons, it must be disconnected from the HMC and configured as a new development system.  How should the customer proceed to implement PowerVM Express and Integrated Virtualization Manager (IVM) on this Power System? ()A  Install a VIO server as an additional partition and DLPAR the resources from the existing partition to the VIO server.B  Create a service partition and install a VIO server. This will automatically move resources to the VIO server on reboot of the managed system.C  Delete all the existing LPARs, create a new LPAR and assign all the system resources to this LPAR and then install the VIO server on this LPAR.D  Reset the machine to Manufacturing Default Configuration and install the VIO server on the resulting partition created, which will own all system resources.