网友您好, 请在下方输入框内输入要搜索的题目:

题目内容 (请给出正确答案)

An LPAR has hung during a reboot, reporting a 0552 LED code. What does this signify?()

  • A、varyon of the paging device failed.
  • B、fsck of the root (/) filesystem failed.
  • C、varyon of the root volume group failed.
  • D、IPL device could not be opened or a read failed.

参考答案

更多 “ An LPAR has hung during a reboot, reporting a 0552 LED code. What does this signify?()A、varyon of the paging device failed.B、fsck of the root (/) filesystem failed.C、varyon of the root volume group failed.D、IPL device could not be opened or a read failed.” 相关考题
考题 A client has a temporary deployment of a new static application that needs to run for a short period of time and is not going to change.How can this deployment be achieved with a minimum of effort and time?()A.Run a system WPAR and deploy the application.B.Create a new LPAR and deploy the application.C.Create an application WPAR to deploy the application.D.Create an LPAR hosted by a VIO server and deploy the application.

考题 The only decent hotel in town had hung out a “Full House” sign, so their only choice ( ) at a small inn.A.is to put up B.has been to put up C.will be put up D.was to put up

考题 A client is experiencing issues after cloning an LPAR using alt_disk_install. DLPAR functions are not available for the new LPAR. Also, there is a lot of network traffic to the HMC. What is the most probable cause of this problem?()A、DLPAR functions are not available for cloned partitionsB、The new partition has the same node number as the original LPARC、Additional filesets need to be reinstalled after the alt_disk_install cloningD、The speed and duplex settings on the Ethernet adapter on the new LPAR is misconfigured

考题 An administrator has implemented the following LPARs on a Power 570 with 32 GB memory with 512 MB remaining for allocation: LPAR 1 memory : min = 10 GB des = 15 GB max = 24 GB  LPAR 2memory : min = 10 GB des = 15 GB max = 24 GB The administrator receives a request to add 2 GB to LPAR 1. The only way to do this is by moving memory from LPAR 2 to LPAR 1. The administrator attempts to move the memory, but the operation fails. The administrator can  however allocate 512 MB that is free to LPAR 1 on the 570.  What is the most likely cause of this failure when dynamically moving memory?()A、 Maxperm% is set too low on LPAR 2B、 Insufficient paging space on LPAR 1C、 Service IBM.DRM is unavailable on LPAR 1D、 Insufficient pinnable memory frames available on LPAR 2

考题 A system administrator has been instructed to attach storage in their client LPARs, in a Power 770, with fibre channel adapters using N_port ID virtualization (NPIV). Which of the following partitions has the minimum requirements to utilize virtual fibre channel?()A、LPAR-A with 1Gb FC HBA and SAN connectionB、LPAR-B with 2Gb FC HBA and SAN connectionC、LPAR-C with 4Gb FC HBA and SAN connectionD、LPAR-D with 8Gb FC HBA and SAN connection

考题 A patch has been applied to the operating system.  After rebooting, the system is hung.  Which of the following commands should have been performed to prevent the system from hanging?()A、 lppchk, bosboot B、 lslpp -l, oslevel C、 installp -C, lppchk D、 bosboot, synclvodm 

考题 An AIX LPAR has been reconfigured to use direct-attached disks. What is the best way to fully remove and delete the Virtual IO volumes?()A、On the AIX LPAR: rmdev -dl hdisk#, rmdev -dl vscsi#B、On the VIO Server: rmdev -dev rootvg_disk, rmlv rootlv_nameC、On the AIX LPAR: rmdev -dl hdisk#, rmdev -dl vscsi# On the VIO Server: rmdev -dev rootvg_disk, rmlv rootlv_nameD、On the VIO Server: rmdev -dev rootvg_disk, rmlv rootlv_name On the AIX LPAR: rmdev -dl hdisk#, rmdev -dl vscsi#

考题 An LPAR has hung during a reboot, reporting a 0552LED code. What does this signify?()A、varyon of the paging device failed.B、fsck of the root (/) filesystem failed.C、varyon of the root volume group failed.D、IPL device could not be opened or a read failed.

考题 A customer has raised a question about a recently installed LPAR. What command would the administrator run to obtain information about the processor entitlement?()A、lscfg -vpsB、prtconf -cC、lparstat -iD、lsdev -C -c processor

考题 A client has an existing Logical Partition (LPAR) on a p650 running AIX 5.2 and will be porting this LPAR to a p5 590. A mksysb has been run to tape, and a compatible tape drive is available and allocated to the target LPAR on the p5 590. What additional resource needs to be available on the p5 590?()A、A CD or DVD with installation mediaB、An internal SCSI adapter in the target LPARC、An Ethernet adapter for access to an FTP serverD、Advanced Power Virtualization feature of the p5 590

考题 Company.com has two POWER5 servers. They want the two servers’ virtual Ethernets to appear on the same IP subnet. Which of the following will connect the client virtual Ethernet adapters to the physical Ethernet switch connecting the two servers?()A、Configure a Shared Ethernet Adapter on the Virtual I/O Server.B、Use the same virtual LAN ID on each LPAR.C、Set up IP routing through an LPAR on each system.D、Set up an IP firewall through an LPAR on each system.

考题 A customer has an LPAR with 4 dedicated cores on a POWER7 server with SMT4 enabled. How many logical processors are presented to an application running on this LPAR?()A、4B、8C、16D、32

考题 A POWER6 595 LPAR has two dedicated processors. The LPAR is active and running AIX 6.1. What must be done to donate any unusedprocessing capacity to the shared processor pool?()A、In the HMC Properties, select the options to allow processor sharing when the partition is inactive and active.B、In the LPAR Properties, select the options to allow processor sharing when the partition is inactive and active.C、In the LPAR Profile Properties, select the options to allow processor sharing when the partition is inactive and active.D、In the 595 Managed System Properties, select the options to allow processor sharing when partitions are inactive and active.

考题 An administrator has installed 1 VIO Server and 5 client LPARs on a 16-core Power 570 with the following CPU requirements: Virtual Processors Processing Units Min Desired Max Min Desired Max VIOS1 1 2 4 0.1 1.0 2.0 LPAR1 4 4 4 4.0 4.0 4.0 LPAR2 2 5 8 1.0 5.0 6.0 LPAR3 1 3 4 0.1 0.3 1.0 LPAR4 3 6 9 0.5 3.0 6.0 LPAR5 1 3 6 1.0 3.0 .06 If the administrator activates the LPARs in the above order,  what will be the result? ()A、 All LPARs will start except LPAR5.B、 All LPARs will start with desired capacity.C、 All LPARs will start but LPAR5 will have its minimum capacity assigned.D、 All LPARs will start but LPAR5 will have less than its desired capacity.

考题 A user has an application server LPAR with a physical Ethernet adapter. They want to have a database LPAR also connected to the application LPAR via virtual Ethernet. Their security policies require a firewall between the application LPAR and database LPAR. Which of the following virtual Ethernet configurations satisfies the customer’s requirements?()A、The application server,firewall,and database server on the same VLANB、The application server and firewall on one VLAN,and the database server on a second VLANC、The application server on one VLAN,and the database server and firewall on a second VLAND、The application server and firewall on one VLAN,and the firewall and database server on a second VLAN

考题 System configurations on the HMC have been backed up correctly. After a restore, the partitions are defined with different characteristics than the running systems. What is the most probable cause of this problem?()A、The LPAR Configuration backup is corruptB、The LPAR Configuration has been altered using DLPARC、The LPAR Configuration backup was performed on a different HMCD、The LPAR Configuration has been altered through the Advanced System Management Interface (ASMI) on the server after the backup was performed

考题 单选题A client has an existing Logical Partition (LPAR) on a p650 running AIX 5.2 and will be porting this LPAR to a p5 590. A mksysb has been run to tape, and a compatible tape drive is available and allocated to the target LPAR on the p5 590. What additional resource needs to be available on the p5 590?()A A CD or DVD with installation mediaB An internal SCSI adapter in the target LPARC An Ethernet adapter for access to an FTP serverD Advanced Power Virtualization feature of the p5 590

考题 单选题One of the workers has hung the curtains that had been laying on the floor.A hasB hungC hadD laying

考题 单选题Companycom has just purchased a p5 570 with AIX 5.3. The customer would like to add a training LPAR to the system, but no processors are available. All of the partitions are using dedicated resources. The test LPAR is using one processor and has a 90% CPU idle rate. What can be done to setup this training LPAR quickly without disabling their current environment?()A Use AIX 5.3 which supports micro-partitioning for both the test and training LPARSB Use DLPAR to move resources from the test LPAR to training when training is activeC Install Partition Load Manager to share resources between the test and training environmentsD Install Advanced Power Virtualization and then use micro-partitioning for both the test and training LPARs

考题 单选题A client has a temporary deployment of a new static application that needs to run for a short period of time and is not going to change. How can this deployment be achieved with a minimum of effort and time?()A Run a system WPAR and deploy the application.B Create a new LPAR and deploy the application.C Create an application WPAR to deploy the application.D Create an LPAR hosted by a VIO server and deploy the application.

考题 单选题An administrator has implemented the following LPARs on a Power 570 with 32 GB memory with 512 MB remaining for allocation: LPAR 1 memory : min = 10 GB des = 15 GB max = 24 GB  LPAR 2memory : min = 10 GB des = 15 GB max = 24 GB The administrator receives a request to add 2 GB to LPAR 1. The only way to do this is by moving memory from LPAR 2 to LPAR 1. The administrator attempts to move the memory, but the operation fails. The administrator can  however allocate 512 MB that is free to LPAR 1 on the 570.  What is the most likely cause of this failure when dynamically moving memory?()A  Maxperm% is set too low on LPAR 2B  Insufficient paging space on LPAR 1C  Service IBM.DRM is unavailable on LPAR 1D  Insufficient pinnable memory frames available on LPAR 2

考题 单选题System configurations on the HMC have been backed up correctly. After a restore, the partitions are defined with different characteristics than the running systems. What is the most probable cause of this problem?()A The LPAR Configuration backup is corruptB The LPAR Configuration has been altered using DLPARC The LPAR Configuration backup was performed on a different HMCD The LPAR Configuration has been altered through the Advanced System Management Interface (ASMI) on the server after the backup was performed

考题 单选题A user has an application server LPAR with a physical Ethernet adapter. They want to have a database LPAR also connected to the application LPAR via virtual Ethernet. Their security policies require a firewall between the application LPAR and database LPAR. Which of the following virtual Ethernet configurations satisfies the customer’s requirements?()A The application server,firewall,and database server on the same VLANB The application server and firewall on one VLAN,and the database server on a second VLANC The application server on one VLAN,and the database server and firewall on a second VLAND The application server and firewall on one VLAN,and the firewall and database server on a second VLAN

考题 单选题A customer has an LPAR with 4 dedicated cores on a POWER7 server with SMT4 enabled. How many logical processors are presented to an application running on this LPAR?()A 4B 8C 16D 32

考题 单选题Companycom has a p5 590 that has their production LPAR, their Tivoli Storage Manager (TSM) LPAR, and several other LPARs. What method would provide connectivity between the production LPAR, and the TSM LPAR, but be isolated from the other LPARs in the system without utilizing a Virtual IO Server or physical adapter resources?()A Use shared memory and semaphores to transfer the data to the TSM LPARB Provide gigabit Ethernet adapters in each LPAR and run a crossover cableC Create a Virtual Ethernet between the production server and the TSM LPARsD Create a Virtual Ethernet between the TSM server LPAR and the non-production LPARs

考题 单选题An AIX LPAR has been reconfigured to use direct-attached disks. What is the best way to fully remove and delete the Virtual IO volumes?()A On the AIX LPAR: rmdev -dl hdisk#, rmdev -dl vscsi#B On the VIO Server: rmdev -dev rootvg_disk, rmlv rootlv_nameC On the AIX LPAR: rmdev -dl hdisk#, rmdev -dl vscsi# On the VIO Server: rmdev -dev rootvg_disk, rmlv rootlv_nameD On the VIO Server: rmdev -dev rootvg_disk, rmlv rootlv_name On the AIX LPAR: rmdev -dl hdisk#, rmdev -dl vscsi#

考题 单选题A client is experiencing issues after cloning an LPAR using alt_disk_install. DLPAR functions are not available for the new LPAR. Also, there is a lot of network traffic to the HMC. What is the most probable cause of this problem?()A DLPAR functions are not available for cloned partitionsB The new partition has the same node number as the original LPARC Additional filesets need to be reinstalled after the alt_disk_install cloningD The speed and duplex settings on the Ethernet adapter on the new LPAR is misconfigured