What components are required to support the collaborative workspace feature?()
A
LDAP
B
QuickPlace
C
SameTime
D
Domino
E
IIS
参考答案
参考解析
解析:
暂无解析
更多 “多选题What components are required to support the collaborative workspace feature?()ALDAPBQuickPlaceCSameTimeDDominoEIIS” 相关考题
考题
2 The activities of an organisation have to be managed and co-ordinated to ensure that its objectives are met. The organisation’s structure is designed to support this.Required:(a) What is meant by the term ‘organisational structure,’ often shown as an organisation chart? (5 marks)
考题
What is the type and scope of the LSA required to support traffic engineering in an OSPFenvironment?()
A. Type 9, AS scopeB. Type 10, AS scopeC. Type 10, Area scopeD. Type 9, Area scope
考题
In an XIV Storage System, what is the minimum number of modules required to support iSCSI connectivity?()
A.6 modulesB.9 modulesC.11 modulesD.15 modules
考题
What components are required to directly connect two PCs so they are able to participate in a simple peer-to-per network?()
A. Straight-through cableB. Compatible network interfacesC. Networking protocolD. HubE. Crossover cableF. router
考题
What is the primary purpose of SMB Smart Designs? ()A、 assists in locating appropriate resourcesB、 provides training on products, tools, and solutionsC、 provides a direct support path for any partner issueD、 provides validated commercial solutionsE、 provides a step-by-step outline of implementation tasks required
考题
What components are required to directly connect two PCs so they are able to participate in a simple peer-to-per network?()A、Straight-through cableB、Compatible network interfacesC、Networking protocolD、HubE、Crossover cableF、router
考题
What are three components of Cisco Technical Support Services?()A、Application Software UpdatesB、Cisco Advisory ServicesC、Advanced Hardware ReplacementD、Software SupportE、Cisco.comF、Warranty for hardware
考题
What operating system is required to support Active Memory Expansion?()A、AIX 6.1B、AIX 5.3C、Red Hat 10D、SUSE LINUX 11
考题
What is required for proper implementation of jumbo frame support on a Cisco Nexus 2000 Series Fabric Extender?() A、 The interface configured as FEX fabric requires the MTU to be set to jumbo.B、 The service policy must be applied to the system QoS.C、 The device defaults to jumbo frame support; no changes are required.D、 The switchport in the FEX interface must be set to MTU 9216.
考题
What components are required to support the collaborative workspace feature?()A、LDAPB、QuickPlaceC、SameTimeD、DominoE、IIS
考题
Company.com with an EtherChannel implementation is considering an HACMP solution. What considerations must be addressed in planning this configuration?() A、 Hardware address takeover must be configured.B、 IPAT via IP aliasing is required for EtherChannel.C、 EtherChannel must be defined as a separate network.D、 HACMP does not support the fallover of EtherChannel.
考题
In an XIV Storage System, what is the minimum number of modules required to support iSCSI connectivity?()A、6 modulesB、9 modulesC、11 modulesD、15 modules
考题
To enhance the availability of an application running under HACMP, a decision was made to use The application monitoring facility. The application consists of several components and can take several minutes to initialize. The components use socket communication and can be initialized in any order as long as it is a serial order. The customer’s concern is that if the application stop and start scripts are used during application monitoring recovery,it may take an extraordinary length of time to reset all of the application components. What can be done to ensure the best recover time?() A、 Use a process monitor that restarts the named processes in the original start order.B、 Use the defined application start and stop scripts to control the application if there is a failure.C、 Use multiple application monitors for this resource group to enable the monitoring of the specific components of the resource group.D、 Use application cleanup and restart scripts designed to determine the state of the various components of the application and start only the parts required.
考题
多选题What components are required to directly connect two PCs so they are able to participate in a simple peer-to-per network?()AStraight-through cableBCompatible network interfacesCNetworking protocolDHubECrossover cableFrouter
考题
单选题What is the primary purpose of SMB Smart Designs? ()A
assists in locating appropriate resourcesB
provides training on products, tools, and solutionsC
provides a direct support path for any partner issueD
provides validated commercial solutionsE
provides a step-by-step outline of implementation tasks required
考题
单选题setting redundant components in subsystem to handle with the risks brought by the defaults of original components,what kind of risk response strategy is this?()A
risk avoidanceB
risk acceptanceC
risk mitigationD
contingency plan
考题
多选题What are three components of Cisco Technical Support Services?()AApplication Software UpdatesBCisco Advisory ServicesCAdvanced Hardware ReplacementDSoftware SupportECisco.comFWarranty for hardware
考题
单选题In an XIV Storage System, what is the minimum number of modules required to support iSCSI connectivity?()A
6 modulesB
9 modulesC
11 modulesD
15 modules
考题
单选题What is required for proper implementation of jumbo frame support on a Cisco Nexus 2000 Series Fabric Extender?()A
The interface configured as FEX fabric requires the MTU to be set to jumbo.B
The service policy must be applied to the system QoS.C
The device defaults to jumbo frame support; no changes are required.D
The switchport in the FEX interface must be set to MTU 9216.
考题
多选题Which three of these service components are in the implement phase?()AStagingBBusiness Requirements DevelopmentCPost Implementation Support Handoff MeetingDDetailed Design DevelopmentEStaff TrainingFIncident Management
考题
单选题What is the minimum number of p5-570 building blocks required to support 16 RIO drawers?()A
1B
2C
3D
4
考题
单选题What is one key objective of the operations readiness assessment performed in the plan phase?Select exactly 1 answer(s) from the following:()。A
align business requirements with technical requirementsB
create a plan to recycle used equipmentC
evaluate the readiness of a customers current operations and network management infrastructure to support a new technologyD
install and test system components in a non-production environment
考题
多选题Which two are true about authentication?()AForm-based logins should NOT be used with HTTPS.BWhen using Basic Authentication the target server is NOT authenticated.CJ2EE compliant web containers are NOT required to support the HTTPS protocol.DWeb containers are required to support unauthenticated access to unprotected web resources.
考题
单选题An icebreaker displaying a flag hoist which consists of the code letters “WO” (Whiskey Oscar) is indicating that().A
icebreaker support is finishedB
icebreaker support is commencingC
the icebreaker is iceboundD
the icebreaker is beset
热门标签
最新试卷