The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false.
A

The communication management plan is contained in or is a subsidiary plan of, the project management plan.

B

The  communication  management  plan  can  be  formal  or informal, highly detailed or broadly framed, and based on the needs of the project.

C

The  communication  manamgement  plan  organize  and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.

D

The communication management plan can include guidelines project status meetings,project team meetings,e-meetines,and e-mail


参考答案

参考解析
解析: 沟通管理计划用于确定项目千系人的信息需求和沟通方法,以下关于沟通管理计划的叙述中,错误的是:沟通管理计划定期收集、对比和分析基准与实际数据,以便了解和沟通项目进展与绩效情况。 A:沟通管理计划是项目管理计划的一部分或子计划 B:沟通管理计划可以根据项目需求是正式或非正式的、非常详细或高度概括的。 C://沟通管理计划定期收集、对比和分析基准与实际数据,以便了解和沟通项目进展与绩效情况。 D://沟通管理计划可包括关于状态会议、项目团队回忆、网络会议和电子邮件等的指南。
更多 “单选题The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false.A The communication management plan is contained in or is a subsidiary plan of, the project management plan.B The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the project.C The communication manamgement plan organize and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.D The communication management plan can include guidelines project status meetings,project team meetings,e-meetines,and e-mail” 相关考题
考题 ● Project (74) Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.A.IntegrationB.TimeC.PlanningD.Communication

考题 Input into the Communications Management Plan includes the following information from the stakeholder analysis:A Information needsB Information contentC Frequency of distributionD Method of distributionE All of the above

考题 75 Input into the Communications Management Plan includes the following information from the stakeholder analysis:A. Information needsB. Information contentC. Frequency of distributionD. Method of distributionE. All of the above

考题 The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false. A. The communication management plan is contained in or is a subsidiary plan of, the project management plan.B. The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the project.C. The communication manamgement plan organize and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.D. The communication management plan can include guidelines project status meetings,project team meetings,e-meetines,and e-mail

考题 The failure of the plan was due ( ) bad management. A、ofB、toC、with

考题 Object-oriented analysis (OOA) is a semiformal specification technique for the object-oriented paradigm. Object-oriented analysis consists of three steps. The first step is(71) . It determines how the various results are computed by the product and presents this information in the form. of a(72) and associated scenarios. The second is(73) , which determines the classes and their attributes, then determines the interrelationships and interaction among the classes. The last step is(74) , which determines the actions performed by or to each class or subclass and presents this information in the form. of (75) .A.static modelingB.dynamic modelingC.use-case modelingD.behavioral modeling

考题 The Develop Project Management Plan Process includes the actions necessary to define,prepare,integrate,and coordinate all constituent plans into a(75). A.Project Scope Statement B.Project Management Plan C.Forecasts D.Project Charter

考题 Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval,and ultimate disposition of project information.() A.Integration B.Time C.Planning D.Communication

考题 ●The quality management plan should describe how the project management team will implement its quality (73).(73) A. improvementB. controlC. policyD. information

考题 An educational plan is an official document that authoritatively determines the content and principles of teaching and learning.()

考题 The Simple Network Management Protocol(SNMP)is an(66)protocol that facilitates the exchange of management information between(67). It is part of the Transmission Control Protocol/Internet Protocol(TCP/IP)protocol suite. SNMP enables network(68)to manage network performance, find and sole network problems, and plan for(69)An SNMP -managed network consists of three key components: managed devices ,(70),and network -management systems .A.Physical LayerB.Link LayerC.Network LayerD.Transport Layer

考题 The communication management plandetermines the information and communications needs of the stakeholders. In thefollowing statements related to communication management plan, (73) is false.A.The communication management plan is contained in, or is a subsidiary plan of, the project management planB.The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the projectC.The communication management plan organize and summarize the information gathered, and present the results of any analysis as compared to the performance measurement baselineD.The communication management plan can include guidelines for project status meetings, project team meetings, e-meetings, and e-mails

考题 The quality management plan should describe how the project management team will implement its quality(73).A. improvementB. controlC. policyD. information

考题 The Simple Network Management Protocol (SNMP)is an(71)protocol that facilitates the exchange of management information between(72). It is part of the Transmission Control Protocol/Internet Protocol (TCP/IP) protocol suite. SNMP enables network(73)to manage network performance, find and sole network problems, and plan for(74). An SNMP-man-aged network consists of three key components: managed devices,(75), and network-management systems.A.Physical LayerB.Link LayerC.Network LayerD.Transport Layer

考题 The quality management plan should describe how the project management team will implement its quality(73).A.improvementB.controlC.policyD.information

考题 The schedule management plan is a component of the project management plan The schedule management plan may be formal or informal, highly detailed or broadly framed, based upon the()of the project, and includes appropriate control thresholds.A.goalsB.valuesC.needsD.Level

考题 The schedule management plan is a component of the project management plan The schedule management plan maybe formal or informal,highly detailed or broadly framed,based up on the( )of the project,and includes appropriate control thresholds. A.goals B.values C.needs D.Level

考题 The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false. A.The communication management plan is contained in or is A.subsidiary plan of, the project management plan. B.The communication management plan can be formal or informal, highly detaileD.or broadly framed, and based on the needs of the project. C.The communication manamgement plan organize and summarize the information gathered, and present the results of any analysis as comparedthe performance measurement baseline. D.The communication management plan can include guidelines project status meetings, project team meetings, e-meetines, and e-mail.

考题 The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false. A、The communication management plan is contained in or is a subsidiary plan of, the project management plan.B、The communication management plan can be formal or informal, highly detailed or broadly framed, and based on the needs of the project.C、The communication manamgement plan organize and summarize the information gathered,and present the results of any analysis as comparedthe performance measurement baseline.D、The communication management plan can include guidelines project status meetings,project team meetings,e-meetines,and e-mail

考题 Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage,retrieval, and ultimate disposition ofproject information.A、IntegrationB、TimeC、PlanningD、Communication

考题 Management of Information is one of the seven requirements in Global minimum essential requirements(GMER)in medical education, which requires a medical practitioner to be able to()A、search,collect,organize and interpret health and biomedical information from different databases and sources.B、retrieve patient-specific information from a clinical data system.C、use information and communication technology to assist in diagnostic,therapeutic and preventive measures,and for surveillance and monitoring health status.D、understand the application and limitations of information technology.

考题 In optical channel transport unit overhead (OTU OH), what are general communication channels 1 and 2(GCC1/GCC2) used for?()A、for trail trace identificationB、as the backward defect indicatorC、to transmit information between OTU termination pointsD、to extend command and management functions over several framesE、General communication channels 1 and 2 (GCC1/GCC2) do not belong to OTU OH

考题 信息安全管理体系(information Securlty Management System.简称ISMS)要求建立过程体系,该过程体系是在如下()基础上构建的。A、IATF(Information Assurance Technical Framework)B、P2DR(Policy,Protection,Detection,Response)C、PDCERF(Preparation,Detection,Containment,Eradication,Recovery,Follow-up)D、PDCA(Plan,Do,Check,Act)

考题 问答题Practice 4   (The candidate chooses one topic and speaks about it for one minute.)  A Motivation: the importance of motivating staff at all levels of a company  B Financial Management: how to achieve savings on production costs.  C Communication: the factors involved in determining staff access to confidential information.

考题 单选题In optical channel transport unit overhead (OTU OH), what are general communication channels 1 and 2(GCC1/GCC2) used for?()A for trail trace identificationB as the backward defect indicatorC to transmit information between OTU termination pointsD to extend command and management functions over several framesE General communication channels 1 and 2 (GCC1/GCC2) do not belong to OTU OH

考题 单选题What is the use of work assets on safety plans? ()A  The work asset determines to which assets and locations a safety plan can be applied.B  Only safety plans with associated work assets can be used in combination with job plans.  C  The safety plan can only be applied to work orders with the same asset or location associated.D  The work assets combined with the work on a job plan dictate which safety information is required.

考题 单选题The interaction of these seven elements is()determines the outcome in any instance of speech communication.A whatB thatC howD which

考题 单选题You purchase a wildcard certificate.You plan to use the certificate for Outlook Anywhere. You need to configure an Exchange organization to use the certificate.What should you do first?()A From the Exchange Management Shell, modify the properties of the WEB Outlook Provider.B From the Exchange Management Shell, modify the properties of the EXPR Outlook Provider.C From the Internet Information Services (IIS) Manager, modify the properties of the RPC virtual directory.D From the Internet Information Services (IIS) Manager, modify the properties of the Autodiscover virtual directory.