网友您好, 请在下方输入框内输入要搜索的题目:

题目内容 (请给出正确答案)
单选题
A customer has a Power 770 running an SAP ERP workload on AIX 7. It has a single partition with 12 cores and 48GB of memory and the CPU is underutilized at 46% with 1000 users. Memory utilization is at 80%. The number of users will increase to 1700, increasing memory utilization by 37%. Which of the following supports this requirement?()
A

Active Memory Server

B

Active Memory Sharing

C

Active Memory Pooling

D

Active Memory Expansion


参考答案

参考解析
解析: 暂无解析
更多 “单选题A customer has a Power 770 running an SAP ERP workload on AIX 7. It has a single partition with 12 cores and 48GB of memory and the CPU is underutilized at 46% with 1000 users. Memory utilization is at 80%. The number of users will increase to 1700, increasing memory utilization by 37%. Which of the following supports this requirement?()A Active Memory ServerB Active Memory SharingC Active Memory PoolingD Active Memory Expansion” 相关考题
考题 AcustomerhasaPower770runninganSAPERPworkloadonAIX7.Ithasasinglepartitionwith12cores and48GBofmemoryandtheCPUisunderutilizedat46%with1000users.Memoryutilizationisat80%.The numberofuserswillincreaseto1700,increasingmemoryutilizationby37%.Whichofthefollowingsupports thisrequirement?()A.ActiveMemoryServerB.ActiveMemorySharingC.ActiveMemoryPoolingD.ActiveMemoryExpansion

考题 A customer has many RS/6000s and POWER4 systems running different AIX applications.  What should the customer do to best position themselves for the migration to POWER5?()A、Upgrade OS to AIX 5.2.B、Implement Micro-Partitioning.C、Upgrade HMC to support POWER5.D、Install Partition Load Manager.

考题 A small IT department is deploying Power 720 servers exploiting virtualization technologies.  Each Power 720 will have two partitions, one with 6 cores and one with 2 cores, and both partitions having 32GB of memory each. Live Partition Mobility is being considered at some point in the future. What is the minimum AIX Edition required to support the customer?()A、AIX Basic EditionB、AIX Express EditionC、AIX Standard EditionD、AIX Enterprise Edition

考题 A customer has two Power 770 systems with 4 enclosures each.  Thirty two cores and 1TB of memory are activated on each system.  Each system has 3 database partitions and each partition has 10 cores and 300GB of memory.   Which solution will provide automated recovery of unplanned outages at least cost?()A、Purchase PowerVM Enterprise Edition.Use System Director to automate Live Partition Mobility to recover from partition failureB、Create additional shared processor partitions as standby nodes.Use PowerHA SystemMirror to activate and use CoD resources when a failover occursC、Purchase an additional 32-core Power 750 with PowerHA SystemMirror Standard Edition.Use the new system as standby node with the XD component of PowerHAD、Purchase an additional Power 770 system.Locate production and standby database partitions on each system.Use DB2 pureScale to provide automated partition monitoring and failover

考题 Companycom has the following: 8 x 1.65GHz CPUs 16GB Memory 4 LPARs LPAR 1: Test/Dev 1 CPU, 2GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 2: QA 1 CPU, 2GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 3: Prod 3 CPUs, 6GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 4: Web App 3 CPUs, 6GB Memory, 1 Fibre Channel HBA, SUSE Linux Utilization over a 30 day period LPAR 1: Average utilization was 15%, Peak utilization was 100% LPAR 2: Average utilization was 25%, Peak utilization was 100% LPAR 3: Average utilization was 50%, Peak utilization was 90% LPAR 4: Average utilization was 35%, Peak utilization was 100% If the customer has a requirement for all four LPARs moved to a p5 590 and to have dedicated CPU resources. Which of the following would best describe the profile requirements?()A、LPARs 1 and 2, SMT on, min CPU 1.0, max CPU 1.0, desired CPU 1.0 LPARs 3 and 4, SMT on, min CPU 1.0, max CPU 3.0, desired CPU 2.0 B、LPARs 1 and 2, SMT on, min CPU 1.0, max CPU 1.0, desired CPU 1.0 LPARs 3 and 4, SMT on, min CPU 2.0, max CPU 3.0, desired CPU 3.0 C、LPARs 1 and 2, SMT on, min CPU 1.0, max CPU 3.0, desired CPU 3.0 LPARs 3 and 4, SMT on, min CPU 1.0, max CPU 3.0, desired CPU 2.0 D、LPARs 1 and 2, SMT off, min CPU 1.0, max CPU 1.0, desired CPU 1.0 LPARs 3 and 4, SMT off, min CPU 1.0, max CPU 3.0, desired CPU 3.0

考题 A customer has an 8-way p650 running an application for about 200 users.  In the past, the requiredamount of memory and processors has increased proportionally to the number of new users.  The customer plans to increase users by 10% each year for the next three years.  Next year, a database will be added to the workload to support the users directly rather than being on a separate machine. What is the most likely result of this projected growth?()A、Disk usage will increase in proportion to memory.B、The new database will demand much more memory.C、Memory demand will increase 10% for the next year.D、Processor demand will increase about 10% for the next year.

考题 A customer has a 16-core Power 570 with 64 GB RAM. They have 2 VIO servers and 4 LPARs, all running very heavy database applications. Storage is virtualized. The storage is SAN based and configured via MultiPath IO on the LPARs. The users are complaining about poor  performance. The VIO servers are reporting low CPU load and little memory usage. The LPARs show 100% disk busy time and are running very slowly, approximately 6-10MB/sec. The SAN reports LUN utilization of less that 20% busy time.  What should be done to resolve this problem? ()A、 Configure MPIO load balancing on the LPARs.B、 Increase the SCSI queue depth per hdisk device.C、 Increase the number of virtual SCSI devices per LPAR by 2.D、 Increase the path priority on both virtual SCSI devices on the LPARs.

考题 The database on a p5-570 Micro-Partition has grown and backups are not meeting the Service Level Agreement. There are several partitions using the Virtual I/O Server to access the storage array. The database backup has high CPU utilization while the others have low CPU utilization. What adjustment can the technical specialist make to ensure that the Service Level Agreement is achieved?()A、Add memory to the database partition to improve response time.B、Add additional Host Bus Adapters to the server to improve IO throughput.C、Modify CPU allocations to favor the database partition.D、Increase CPU allocations to the Virtual I/O Server.

考题 Which of the following is a correct statement about Workload Partitions (WPARs)?()A、WPARs use dedicated cores and shared memory.B、WPARs are restricted to using dedicated resources.C、WPARs share the resources of a single AIX instance.D、WPARs use shared cores, memory, and dedicated network adapters.

考题 A customer has a Power 770 running an SAP ERP workload on AIX 7. It has a single partition with 12 cores and 48GB of memory and the CPU is underutilized at 46% with 1000 users. Memory utilization is at 80%. The number of users will increase to 1700, increasing memory utilization by 37%. Which of the following supports this requirement?()A、Active Memory ServerB、Active Memory SharingC、Active Memory PoolingD、Active Memory Expansion

考题 The workload requirement for a Web server running in Micro-Partitioned p5-550 has increased 300 percent over the past six months. The initial partition definitions assigned 0.5 processing units and one virtual processor to the Web server partition. Three months previously, an additional 0.5 CPU was added to the Web server partition. When the technical specialist attempted to allocate a further 0.5 CPU to this partition, no additional performance was achieved. Which of the following actions would most likely resolve the problem?()A、Add another virtual Ethernet.B、Change the partition to be uncapped.C、Change the number of virtual processors to 2.D、Increase the amount of memory assigned to the partition by 300 percent.

考题 Company.com has a single pSeries server with two shared processor logical partitions. The first partition has peak resource requirements during weekdays. The second partition has peak resource requirements during weekends. During the peak times, the total workload between the partitions does NOT exceed the capacity of the server. However, the partitions are not able to utilize the full capacity of the system during peak times, because the necessary CPU and memory resources are not always allocated to the busiest partition. Which of the following options would best balance these resources?()A、Configure AIX Workload ManagerB、Configure Partition Load ManagerC、Configure eServer Workload ManagerD、Use DLPAR from the HMC

考题 A Power 720 has AIX 6.1 and Linux partitions.During normal workloads there is more than enough memory available to the LPARs.  During month-end processing one partition becomes memory constrained.      What can help overcome this situation?()A、Active Memory Sharing (AMS)B、Active Memory Expansion (AME)C、Integrated Virtual Memory (IVM)D、Memory Capacity on Demand (CoD)

考题 A customer is in the initial stages of implementing a server consolidation project.  The Information Technology staff has identified several Microsoft Windows servers that are running single applications on older hardware and averaging under 20% utilization.  Part of their server consolidation goal is to lower the number of servers, decrease the operating system license cost, and increase utilization per server.  Which of the following IBM Director extensions could be used to satisfy all of these requirements?()A、Aurema Application Workload ManagerB、Remote Deployment ManagerC、Virtual Machine ManagerD、Capacity Manager

考题 A customer has a system with a number of LPARs, one of which is running a supported version of Linux. Which CLI command can an administrator use to display the CPU and memory resource allocation of the Linux partition? ()A、cat /proc/usr/lparchk B、cat /proc/ppc64/lparcfg C、/var/adm/tools/res_list D、/var/adm/tools/lparalloc

考题 Companycom is considering a partitioned solution with one of the LPARs utilizing 12 CPUs. Multiple applications will be loaded on this large LPAR. However, the customer wants to ensure some tasks will have higher priority access to the CPU and memory resources. Which of the following solutions would best satisfy the requirement?()A、LoadlevelerB、AIX Workload ManagerC、Partition Load ManagerD、Tivoli Provisioning Manager

考题 单选题A customer has a system with a number of LPARs, one of which is running a supported version of Linux. Which CLI command can an administrator use to display the CPU and memory resource allocation of the Linux partition? ()A cat /proc/usr/lparchk B cat /proc/ppc64/lparcfg C /var/adm/tools/res_list D /var/adm/tools/lparalloc

考题 单选题A customer has a Power 770 running an SAP ERP workload on AIX 7. It has a single partition with 12 cores and 48GB of memory and the CPU is underutilized at 46% with 1000 users. Memory utilization is at 80%. The number of users will increase to 1700, increasing memory utilization by 37%. Which of the following supports this requirement?()A Active Memory ServerB Active Memory SharingC Active Memory PoolingD Active Memory Expansion

考题 单选题A customer is in the initial stages of implementing a server consolidation project.  The Information Technology staff has identified several Microsoft Windows servers that are running single applications on older hardware and averaging under 20% utilization.  Part of their server consolidation goal is to lower the number of servers, decrease the operating system license cost, and increase utilization per server.  Which of the following IBM Director extensions could be used to satisfy all of these requirements?()A Aurema Application Workload ManagerB Remote Deployment ManagerC Virtual Machine ManagerD Capacity Manager

考题 单选题A customer has a 16-core Power 570 with 64 GB RAM. They have 2 VIO servers and 4 LPARs, all running very heavy database applications. Storage is virtualized. The storage is SAN based and configured via MultiPath IO on the LPARs. The users are complaining about poor  performance. The VIO servers are reporting low CPU load and little memory usage. The LPARs show 100% disk busy time and are running very slowly, approximately 6-10MB/sec. The SAN reports LUN utilization of less that 20% busy time.  What should be done to resolve this problem? ()A  Configure MPIO load balancing on the LPARs.B  Increase the SCSI queue depth per hdisk device.C  Increase the number of virtual SCSI devices per LPAR by 2.D  Increase the path priority on both virtual SCSI devices on the LPARs.

考题 单选题A customer has two Power 770 systems with 4 enclosures each.  Thirty two cores and 1TB of memory are activated on each system.  Each system has 3 database partitions and each partition has 10 cores and 300GB of memory.   Which solution will provide automated recovery of unplanned outages at least cost?()A Purchase PowerVM Enterprise Edition.Use System Director to automate Live Partition Mobility to recover from partition failureB Create additional shared processor partitions as standby nodes.Use PowerHA SystemMirror to activate and use CoD resources when a failover occursC Purchase an additional 32-core Power 750 with PowerHA SystemMirror Standard Edition.Use the new system as standby node with the XD component of PowerHAD Purchase an additional Power 770 system.Locate production and standby database partitions on each system.Use DB2 pureScale to provide automated partition monitoring and failover

考题 单选题A customer has an 8-way p650 running an application for about 200 users.  In the past, the requiredamount of memory and processors has increased proportionally to the number of new users.  The customer plans to increase users by 10% each year for the next three years.  Next year, a database will be added to the workload to support the users directly rather than being on a separate machine. What is the most likely result of this projected growth?()A Disk usage will increase in proportion to memory.B The new database will demand much more memory.C Memory demand will increase 10% for the next year.D Processor demand will increase about 10% for the next year.

考题 单选题A small IT department is deploying Power 720 servers exploiting virtualization technologies.  Each Power 720 will have two partitions, one with 6 cores and one with 2 cores, and both partitions having 32GB of memory each. Live Partition Mobility is being considered at some point in the future. What is the minimum AIX Edition required to support the customer?()A AIX Basic EditionB AIX Express EditionC AIX Standard EditionD AIX Enterprise Edition

考题 单选题A customer has many RS/6000s and POWER4 systems running different AIX applications.  What should the customer do to best position themselves for the migration to POWER5?()A Upgrade OS to AIX 5.2.B Implement Micro-Partitioning.C Upgrade HMC to support POWER5.D Install Partition Load Manager.

考题 单选题Company.com has a single pSeries server with two shared processor logical partitions. The first partition has peak resource requirements during weekdays. The second partition has peak resource requirements during weekends. During the peak times, the total workload between the partitions does NOT exceed the capacity of the server. However, the partitions are not able to utilize the full capacity of the system during peak times, because the necessary CPU and memory resources are not always allocated to the busiest partition. Which of the following options would best balance these resources?()A Configure AIX Workload ManagerB Configure Partition Load ManagerC Configure eServer Workload ManagerD Use DLPAR from the HMC

考题 单选题Companycom has the following: 8 x 1.65GHz CPUs 16GB Memory 4 LPARs LPAR 1: Test/Dev 1 CPU, 2GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 2: QA 1 CPU, 2GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 3: Prod 3 CPUs, 6GB Memory, 1 Fibre Channel HBA, AIX 5.3 LPAR 4: Web App 3 CPUs, 6GB Memory, 1 Fibre Channel HBA, SUSE Linux Utilization over a 30 day period LPAR 1: Average utilization was 15%, Peak utilization was 100% LPAR 2: Average utilization was 25%, Peak utilization was 100% LPAR 3: Average utilization was 50%, Peak utilization was 90% LPAR 4: Average utilization was 35%, Peak utilization was 100% If the customer has a requirement for all four LPARs moved to a p5 590 and to have dedicated CPU resources. Which of the following would best describe the profile requirements?()A LPARs 1 and 2, SMT on, min CPU 1.0, max CPU 1.0, desired CPU 1.0 LPARs 3 and 4, SMT on, min CPU 1.0, max CPU 3.0, desired CPU 2.0 B LPARs 1 and 2, SMT on, min CPU 1.0, max CPU 1.0, desired CPU 1.0 LPARs 3 and 4, SMT on, min CPU 2.0, max CPU 3.0, desired CPU 3.0 C LPARs 1 and 2, SMT on, min CPU 1.0, max CPU 3.0, desired CPU 3.0 LPARs 3 and 4, SMT on, min CPU 1.0, max CPU 3.0, desired CPU 2.0 D LPARs 1 and 2, SMT off, min CPU 1.0, max CPU 1.0, desired CPU 1.0 LPARs 3 and 4, SMT off, min CPU 1.0, max CPU 3.0, desired CPU 3.0

考题 单选题Which of the following is a correct statement about Workload Partitions (WPARs)?()A WPARs use dedicated cores and shared memory.B WPARs are restricted to using dedicated resources.C WPARs share the resources of a single AIX instance.D WPARs use shared cores, memory, and dedicated network adapters.

考题 单选题A Power 720 has AIX 6.1 and Linux partitions.During normal workloads there is more than enough memory available to the LPARs.  During month-end processing one partition becomes memory constrained.      What can help overcome this situation?()A Active Memory Sharing (AMS)B Active Memory Expansion (AME)C Integrated Virtual Memory (IVM)D Memory Capacity on Demand (CoD)