Establishing a project ( ) involves listen milestones, activities, and deliverables with intended start and finish dates, of which the scheduling of employees may be an element


A.cost management plan
B.risk management plan
C.soope management plan
D.management schedule


参考答案

参考解析
解析:
更多 “Establishing a project ( ) involves listen milestones, activities, and deliverables with intended start and finish dates, of which the scheduling of employees may be an element A.cost management plan B.risk management plan C.soope management plan D.management schedule ” 相关考题
考题 Which of the following is indicative of negative float?A.The late start date is earlier than the early start date.B.The critical path supports the imposed end date.C.The early finish date is equal to the late finish date.D.When leads are employed in the schedule.E.The project is sinking.

考题 Free float is the amount of time that an activity may be delayed with out affecting the _____.A.Early start of the succeeding activities.B.Late start of the succeeding activities.C.Project finish.D.Cost of the project.E.None of the above.

考题 It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control?A . Direct labor dollarsB . Direct labor hours.C . Overhead rates.D . Procurement costs.E . None of the above.

考题 ● Which of the following is indicative of negative float?A The late start date is earlier than the early start date.B The critical path supports the imposed end date.C The early finish date is equal to the late finish date.D When leads are employed in the schedule.E The project is sinking.

考题 ● Free float is the amount of time that an activity may be delayed with out affecting the _____.A Early start of the succeeding activities.B Late start of the succeeding activities.C Project finish.D Cost of the project.E None of the above.

考题 Define Activities is the process of identifying the specific actions to be performed to produce the (71).A.project elementsB.work draftsC.work packageD.project deliverables

考题 Project work packages are typically decomposed into smaller components called activities to provide a basis for (72) ,scheduling, executing, and monitoring and controlling the project work.A.reviewingB.estimatingC.auditingD.expecting

考题 Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to(75) progress.A.analyzeB.trackC.levelD.extend

考题 ● Define Activities is the process of identifying the specific actions tobe performed to produce the (71).(71)A. project elementsB. work draftsC. work packageD. project deliverables

考题 ●Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to (75) progress.(75)A. analyzeB. trackC. levelD. extend

考题 ● Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components? (74)(74)A. Scope PlanningB. Scope VerificationC. Scope Change ControlD. Scope Definition

考题 A()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.A.gantt chartB.project histogramC.milestone chartD.project flowchart

考题 In project management,a ( ) is a list of a project’s milestones,activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource allocation,budget and duration, linked by dependencies and scheduled events.A.scheduleB.WBSC.SOWD.charter

考题 A__(74)__is a type of bar chart that illustrates a project schedulA.It illustrates the start and finish dates of the terminal elements and summary elements of a project.B.Gantt chartC.project histogramD.milestone chartE.project flowchart

考题 Establishing a project management timetable involves listing milestones,activities,and()with intended start and finish dates,of which the scheduling of employees may be an elementA.relationshipsB.resourcesC.stakeholdersD.deliverables

考题 In project management , a (1) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (2) ,budget and duration, linked by dependencies and scheduled events.A.scheduleB.activityC.planD.contractor@@@SXB@@@A.findingB.balanceC.allocationD.distribution

考题 Establishing a project ( ) involves listing milestones, activities, and deliverables with intended start and finish dates, of which the scheduling of employees may be an element.A.cost management planB.risk management planC.scope management planD.management schedule

考题 Establishing a project ( ) involves listen milestones, activities, and deliverables with intendstart and finish dates^of which the scheduling of employees may be an element.A.cost management planB.risk managementC.scope management planD.management schedule

考题 Establishing a project(74)involves listen mile stones,activities,and deliverables with intend start and finish dates of which the scheduling of employees may be an element.A.cost management plan B.risk management C.scope management plan D.management schedule

考题 In project management, a ( ) is a listing of a project’s milestones ,activities, and deliverables, usually with intended start and finish dates。A.schedule B.activity C.Plan D.contractor

考题 ( ) is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project. A.gantt chart B.project histogram C.milestone chart D.project flowchart

考题 Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to ( ) progress. A.analyze B.track C.level D.extenD.

考题 Establishing a project management timetable involves listing milestones,activities,and( )with intended start and finish dates,of which the scheduling of employees may be an element. A.relationships B.resources C.stakeholders D.deliverables

考题 In project management, a ( )is a list of a project’s milestones, activities, and deliverables, usually with intended start and finish date. Those items are often estimated in terms of resource allocation, budget and duration, linked by dependencies and scheduled events. A、scheduleB、WBSC、SOWD、charter

考题 ()is a type of bar chart that illustrates a project schedule. It illustrates the start and finish dates of the terminal elements and summary elements of a project.A、gantt chartB、project histogramC、milestone chartD、project flowchart

考题 单选题In project management , a (73) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (74) ,budget and duration, linked by dependencies and scheduled events.A scheduleB activityC planD contractor

考题 单选题Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.A analyzeB trackC levelD extend