网友您好, 请在下方输入框内输入要搜索的题目:

题目内容 (请给出正确答案)

收尾管理在项目完成前不能停止,因为—— ( )

A.有用的信息可能会丢失

B.项目经理可能会被重新任命

C.项目队员到时可能要重新安置

D.卖主着急催款


参考答案

更多 “ 收尾管理在项目完成前不能停止,因为—— ( )A.有用的信息可能会丢失B.项目经理可能会被重新任命C.项目队员到时可能要重新安置D.卖主着急催款 ” 相关考题
考题 The definitive terms of a contract are written during which of the following contract phases?A Contract PhaseB Post-Award PhaseC Award PhaseD Pre-Award PhaseE Requirement Phase

考题 There are four general classes of products that the purchasing department seeks to obtain for production. Which is not one of these categories:A Raw materialsB Standard production itemsC Special itemsD Items of small valueE Semi-precious materials

考题 103 The standard types of communication include all butA. WrittenB. VerbalC. TelepathicD. NonverbalE. None of the above

考题 下列哪一种被称为沉没成本( )A.管理储备金B.风险储备金C.水下建设预算成本D.已花掉且不能再行控制的费用E.预算超支

考题 24 A quality control manager decides to increase his daily sample size from three to six. The size of the control band will:A. increaseB. decreaseC. remain unchangedD. not determinable from given dataE. None of the above

考题 项目采购管理包括以下所有各项除了 ( )A.行政管理B.利害关系者分析C.规划D.询价

考题 ● The work breakdown structure (WBS) is an excellent tool for objective control and evaluation. Which of the following is generally NOT validated through the WBS?A Time, schedule and cost.B Management coordination and organization structuring.C Work methods and accountability.D Quality of work.E Risk and impact decision-making.

考题 在计划编制时你发现完成项目的所需的时间比可以利用的时间长,这时你将如何处理?A、 和客户取得联系,告诉他们项目不能在要求的时间完成。B、 向管理层汇报项目不能在要求的时间完成C、 采赶工或快速跟进法D、 采用赶工或快速跟进法,然后将备选方案汇报管理层。