150 The Cost Performance Index (CPI) measures:

A. cost of work performed vs planned costs.

B. work performed vs cost of work performed.

C. work performed vs planned work.

D. direct costs vs indirect costs.

E. floating costs vs. sunk costs


参考答案

更多 “ 150 The Cost Performance Index (CPI) measures:A. cost of work performed vs planned costs.B. work performed vs cost of work performed.C. work performed vs planned work.D. direct costs vs indirect costs.E. floating costs vs. sunk costs ” 相关考题
考题 The Cost Performance Index (CPI) measures:A.cost of work performed vs planned costs.B.work performed vs cost of work performed.C.work performed vs planned work.D.direct costs vs indirect costs.E.floating costs vs. sunk costs.

考题 68 The Cost Performance Index (CPI) measures:A. cost of work performed vs planned costs.B. work performed vs cost of work performed.C. work performed vs planned work.D. direct costs vs indirect costs.E. floating costs vs. sunk costs.

考题 Iam_______tobelievethathewon‘tcomebacktoseehiswifeagain.A.inclinedB.puzzledC.accompaniedD.performed

考题 CPI()。 A.Value added taxB.Shipping orderC.Cable transferD.Free on BoardE.Central Business DistrictF.World Trade OrganizationG.Pay on deliveryH.Letter of CreditI.Gross Domestic ProductJ.Balance of tradeK.Wholly Foreign-owned EnterprisesL.Consumer Price IndexM.Cost, Insurance and FreightN.Greenwich Mean TimeO.Bunker Surcharge

考题 It is reported that he never ____ an operation (手术) without washing his hands. A、railwayB、trackC、gayD、performed

考题 Nomatterhowfrequently_____,theworksofBeethovenalwaysattractlargeaudiences.(A)performing(C)tobeperformed(B)performed(D)beingperformed

考题 WhichinventorymanagementfeatureofWebSphereCommerceAcceleratorshouldauserwiththeBuyer(sell-side)roleusetorecordinventorythathasbeenorderedfromavendor,sothatbackorderscanbeallocatedagainstthisinventory?()A.AdHocB.ExpectedC.FutureD.OrderedE.Planned

考题 Our meeting was quite accidental.A:occasional B:unexpected C:usual D:planned

考题 The cost performance index(CPI) is the ratio of earned value to ( ) and can be used to estimate the projected cost of completing the project. A. cost variance B.planneD.cost C.PlanneD.value D.actual cost