网友您好, 请在下方输入框内输入要搜索的题目:

题目内容 (请给出正确答案)

Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:

A . 1.1

B . 0.9

C . 0.956

D . 1.15

E . 0.869


参考答案

更多 “ Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:A . 1.1B . 0.9C . 0.956D . 1.15E . 0.869 ” 相关考题
考题 Using the WBS shown in the Special window, a typical work package would be:ASoftware developmentBSystems designCCodingDA, B, and CENone of the above.

考题 Using the situation stated in the Special window, what is the schedule variance for Case #8?A . 1000B . 2000C . -1000D . -2000E . 0.

考题 Using the situation stated in the Special window, what is present value of $1000 at 12% at the end of 5 years?A . ¥3,605.00B . ¥0.57C . ¥567.00D . ¥892.86E . ¥3.61

考题 Using the situation stated in the Special window, what is net present value of an annual income flow of $1600 at 14% over the next three years?A . ¥3,713.60B . ¥0.68C . ¥1,080.00D . ¥476.19E . ¥2.32

考题 Using the situation stated in the Special window, what is the total price variance for direct material?A . ¥140.00B . ¥736.00C . ¥0.02D . ¥-350.00E . ¥5,850.00

考题 Using the situation stated in the Special window, what is the total variable costs for producing one widget?A . ¥1,020B . ¥1,010C . ¥1,015D . ¥20E . None of the above.

考题 Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a taskA . 8B . 8.8C . 9.1D . 9.7E . 10.5

考题 Using the situation stated in the Special window, the labor rate cost variance is:A . ¥66,927B . ¥68,329C . ¥386D . ¥-0E . ¥18.36

考题 Using the situation stated in the Special window, the total price variance of direct material is:A . ¥80,245B . ¥-4,236C . ¥-3,479D . ¥1E . ¥83,994.00

考题 Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.A . Become worse, become worseB . Become worse, improvedC . Improved, increasedD . Improved, become worseE . None of the above are correct

考题 Using the situation stated in the Special window, WBS Element Q is _____ budget by _____ percent.A . Over, 16.66B . Under, 16.66C . Over, 10.0D . Under, 10.0E . None of the above.

考题 Using the situation stated in the Special window, the cost performance index (CPI) for WBS Element R is:A . 0.875B . 1.14C . 0.952D . 0.833E . 1.2

考题 Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?A . Element PB . Element QC . Element RD . Element SE . None of the above.

考题 Using the situation stated in the Special window, which WBS element is behind schedule but under budget?A . Element PB . Element QC . Element RD . Element SE None of the above.

考题 Using the situation stated in the Special window, what is the cost performance index for Case #9?A . 1.1B . 1.91C . 0.83D . 1.2E . None of the above

考题 101 Using the situation stated in the Special window, which WBS element is behind schedule but under budget?A. Element PB. Element QC. Element RD. Element SE. None of the above

考题 102 Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?A. Element PB. Element QC. Element RD. Element SE. None of the above

考题 103 Using the situation stated in the Special window, the cost performance index (CPI) for WBS Element R is:A. 0.875B. 1.14C. 0.952D. 0.833E. 1.20

考题 104 Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:A. 1.10B. 0.90C. 0.956D. 1.15E. 0.869

考题 106 Using the situation stated in the Special window, a comparison of the cost schedule of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.A. Become worse, become worseB. Become worse, improvedC. Improved, increasedD. Improved, become worseE. None of the above are correct

考题 109 Using the situation stated in the Special window, what is the total fixed costs for manufacturing the widgets?A. $3,000B. $27,000C. $27,270D. $1,335E. $1,000

考题 124 Using the situation stated in the Special window, what is the total variable costs for producing one widget?A. $1,020B. $1,010C. $1,015D. $20.00E. None of the above

考题 126 Using the situation stated in the Special window, what is the labor rate cost variance?A. $5500.00B. $1500.00C. -$100.00D. -$0.10E. $5600.00

考题 130 Using the situation stated in the Special window, what is the schedule variance for Case #8? A. 1000B. 2000C. -1000D. -2000E. 0

考题 132 Using the situation stated in the Special window, what is the cost performance index for Case #9?A. 1.10B. 1.91C. 0.83D. 1.20E. None of the above

考题 136 Using the situation stated in the Special window, a comparison of the cost variance of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.A. Become worse, become worseB. Become worse, improvedC. Improved, increasedD. Improved, become worseE. None of the above are correct

考题 ● Using the WBS shown in the Special window, a typical work package would be:A Software developmentB Systems designC CodingD A, B, and CE None of the above.