The budget associated with scope changes that have been approved but not planned for yet, is referred to a(n) _____ budget.
A . Unauditable.
B . Undistributed.
C . Preauthorized.
D . Contingency.
E . In-process.
参考答案
更多 “ The budget associated with scope changes that have been approved but not planned for yet, is referred to a(n) _____ budget.A . Unauditable.B . Undistributed.C . Preauthorized.D . Contingency.E . In-process. ” 相关考题
考题
Why()the old block of flats()demolished next month?
A、are…beingB、is…beingC、has…beenD、have…been
考题
What a waste! Why do you () the water () all the time ?
A、have…flowingB、have…flowC、have…to flowD、have…flowed
考题
When he was a boy he ________ his talent for writing.A、demonstratedB、clarifiedC、illustratedD、approved
考题
The authorities have refused to __________ him a visa to visit the US.
A.arrange
B.agree
C.approve
D.grant
考题
The proposal was endorsed by the majority of members.A:rejected
B:submitted
C:considered
D:approved
考题
The cost performance index(CPI) is the ratio of earned value to ( ) and can be used to estimate the projected cost of completing the project. A. cost variance
B.planneD.cost
C.PlanneD.value
D.actual cost
热门标签
最新试卷