There are four phases in the life cycle of a project:start,plan,execute and( ).
A.implement
B.performance
C.end
D.excute
B.performance
C.end
D.excute
参考答案
参考解析
解析:项目的生命周期有四个阶段为启动、计划、执行与结束。A执行B执行C结束D执行
更多 “There are four phases in the life cycle of a project:start,plan,execute and( ).A.implement B.performance C.end D.excute” 相关考题
考题
Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.APreliminary planning, detail planning, closeoutBImplementation, reporting, terminationCDevelopment, implementation, terminationDExecution, reporting, finishingEImplementation, termination, post-audit review
考题
During which phase of the project life cycle is the amount at stake lowest?A conceptB developmentC executionD conclusionE C and D
考题
92 Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.A. Preliminary planning, detail planning, closeoutB. Implementation, reporting, terminationC. Development, implementation, terminationD. Execution, reporting, finishingE. Implementation, termination, post-audit review
考题
185 Life Cycle Costing:A. is the concept of including all costs within the total life of a project.B. is an activity devoted to optimizing cost/performanceC. is an activity of appraising the cost and technical performance of a completed project.D. is a process of predicting the life of a project.E. None of the above
考题
67 Life Cycle Costing:A. is the concept of including all costs within the total life of a project.B. is an activity devoted to optimizing cost/performanceC. is an activity of appraising the cost and technical performance of a completed project.D. is a process of predicting the life of a project.E. None of the above.
考题
● Project life cycles provide a better means of measurement of progress and control. The four phases of a project are conceptual development, _____, _____, and _____.A Preliminary planning, detail planning, closeoutB Implementation, reporting, terminationC Development, implementation, terminationD Execution, reporting, finishingE Implementation, termination, post-audit review
考题
● Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?A 5%B 10%C 15%D 25%E 50%
考题
● A project life cycle is a collection of generally sequential project (73)whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic (74)for managing the project, regardless of the specific work involved.(73)A. phasesB. processesC. segmentsD. pieces(74)A. planB. fractionC. mainD. framework
考题
● The project life-cycle can be described as(72).(72)A.project concept, project planning, project execution, and project close-outB.project planning, work authorization, and project reportingC.project planning, project control, project definition, WBS development, and project terminationD.project concept, project execution, and project reporting
考题
The(67)defines the phases that connect the beginning of a project to its end.A.scheduleB.project life cycleC.temporaryD.milestone
考题
A project life cycle is a collection of generally sequential project (73) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic (74) for managing the project, regardless of the specific work involved.A.phasesB.processesC.segmentsD.pieces
考题
根据材料回答3~4题: A project life cycle is a collection of generally sequential project(73)whose name and number are determined by the control needs of the organization or organizations involved in the project.The life cycle provides the basic(74)for managing the project,regardless ofthe specific work involve D. A.phases B.processes C.segments D.pieces
考题
The (71) defines the phases that connect the beginning of a project to its end.A.milestoneB.scheduleC.temporaryD.project life cycle
考题
The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycleIt is().A.developmentB.conceptC.system analysisD.implementation
考题
Which of the following statements is correct?A.The definition phase results in the Software Requirements Specification.B.Testing is optional in software life cycle.C.CASE tools can only aid in the design phase of a software life cycle.D.A change during a later phase does not require the documentation of all earlier phases to be updated.
考题
A project life cycle is a collection of generally sequential project ()whose name and number are determined by the control needs of the organization or organizations involved in the project.
The life cycle provides the basic for managing the project, regardless of the specific work involved.A.phases
B.processes
C.segments
D. pieces
考题
A project life cycle is a collection of generally sequential project whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic () for managing the project, regardless of the specific work involved.A. plan
B. fraction
C. main
D.framework
考题
The project life-cycle can be described as().A.project concept, project planning, project execution, and project close-out
B.project planning, work authorization, and project reporting
C.project planning, project control, project definition, WBS development, and project termination
D.project concept, project execution, and project reporting
考题
The development process in the software ______ involves four phases: analysis, design, implementation, and testing.
A.maintenance]
B.1ife] cycle]
C.programming
D.upgrading
考题
The life cycle ofa project is a description of the various phases of the project from the beginning to the end.One of the followings is not a phase of the traditional project life cycle,itis_( )A.devclopment
B.concept
C.system analysis
D.implementation
考题
The life cycle of a project is a description of the various phases of the project from the beginning to the end. One of the followings is not a phase of the traditional project life cycle, It is( ).A.development
B.concept
C.system analysis
D.implementation
考题
The life cycle of aproject is a description of the various phases of the project from thebeginning to the end. One of the followings is not a phase of the traditionalproject life cycle, It is( ). A.development
B.concept
C.system analysis
D.implementation
考题
The life cycle provides the basic ()for managing the project, regardless of the specific work involved. A.plan
B.fraction
C.main
D.framework
考题
A project life cycle is a collection of generally sequential project ()whose name and number are determined by the control needs of the organization or organizations involved in the project. A.phases
B.processes
C.segments
D.pieces
考题
A project life cycle is a collection of generally sequential project()(1) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic ()(2) for managing the project, regardless of the specific work involved.
空白(2)处应选择()A、planB、fractionC、mainD、framework
考题
The() defines the phases that connect the beginning of a project to its end.A、scheduleB、project life cycleC、temporaryD、milestone
考题
单选题The()defines the phases that connect the beginning of a project to its end.A
scheduleB
project life cycleC
temporaryD
milestone