A network planning diagram shows a large internetwork with many routers. The configurations show that OSPF has been enabled on all interfaces, I P addresses correctly configured, and OSPF workinG. For which of the following cases would you expect a router to create and flood a Type 2 LSA?()
- A、When OSPF is enabled on a LAN interface, and the router is the only router connected to the subnet.
- B、 When OSPF is enabled on a point - to -point serial link, and that router has both the higher router ID and higher interface IP address on the link.
- C、When OSPF is enabled on a Frame Relay point - to - point subinterface, has the lower RID and lower subinterfa ce IP address, and otherwise uses default OSPF configuration on the interface.
- D、When OSPF is enabled on a working LAN interface on a router, and the router has been elected BDR.
- E、None of the other answers is correct.
参考答案
更多 “ A network planning diagram shows a large internetwork with many routers. The configurations show that OSPF has been enabled on all interfaces, I P addresses correctly configured, and OSPF workinG. For which of the following cases would you expect a router to create and flood a Type 2 LSA?()A、When OSPF is enabled on a LAN interface, and the router is the only router connected to the subnet.B、 When OSPF is enabled on a point - to -point serial link, and that router has both the higher router ID and higher interface IP address on the link.C、When OSPF is enabled on a Frame Relay point - to - point subinterface, has the lower RID and lower subinterfa ce IP address, and otherwise uses default OSPF configuration on the interface.D、When OSPF is enabled on a working LAN interface on a router, and the router has been elected BDR.E、None of the other answers is correct.” 相关考题
考题
The purpose of a dummy activity in an activity-on-arrow diagram is to:A.Identify a task that could be replaced by another.B.Take the slack time into account.C.Show a task that is not necessarily needed.D.Denote a milestone.E.Show a dependency relationship.
考题
● The purpose of a dummy activity in an activity-on-arrow diagram is to:A Identify a task that could be replaced by another.B Take the slack time into account.C Show a task that is not necessarily needed.D Denote a milestone.E Show a dependency relationship.
考题
● (73) is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist betweenthem.(73)A.PERTB.AOAC.WBSD.PDM
考题
is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships:(67), the initiation of the successor activity, depends upon the completion of the predecessor activity.(68), the initiation of the successor activity, depends upon the initiation of the predecessor activity.A.PDMB.CPMC.PERTD.AOA
考题
is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles,referred to as nodes,to represent activities and connects them with arrows that show the logical relationships that exist between them. A.PERT B.AOA C.WBS D.PDM
考题
Which IOS user EXEC command will allow a network technician to determine which router in the path to an unreachable network host should be examined more closely for the cause of the network failure?A. EzonexamB telnetB. EzonexamB pingC. EzonexamB traceD. EzonexamB show ip routeE. EzonexamB show interfaceF. EzonexamB show cdp neighbors
考题
A technician would use a physical network diagram to determine:()
A. the cause of routing errors.B. the number of switches on the network.C. the number of users on the network.D. where network latency will occur.
考题
is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between them.A.PERTB.AOAC.WBSD.PDM
考题
During planning you sit down and estimate the time needed for each task and total them to come up with the project estimate This duration is what you commit to complete the project. What is wrong with the scenario? ()A.The team did not create the estimate and estimating tales too long using that methodB.The team did not create the estimate and a network diagram was not usedC.The estimate is too long and should be created by managementD.The project estimate should be the same as the customer's required completion date
考题
A technician at TestKing needs to update the network documentation. One of the tasks includes documenting the name of the IOS image file of each router in the network.Which commands could be used to find this information?()A. Router# show protocolsB. Router# show versionC. Router# show imageD. Router# show IOSE. Router# show flash
考题
A mobile offshore drilling unit will show the day-shape in DIAGRAM 10 to indicate that it is ______.A.at anchorB.being towedC.agroundD.drilling
考题
Which of the following activities is the best for training detailed reading?A.Drawing a diagram to show the text structure.
B.Giving the text an appropriate title.
C.Transforming information from the text to a diagram.
D.Finding out all the unfamiliar words.
考题
In project network diagram ,the number of critical path is ( ).A.none
B.only one
C.only two
D.one or more
考题
The Unified Modeling Language is a standard graphical language for modeling object-oriented software. ( ) can show the behavior of systems in terms of how objects interact with each other. A.Class diagram
B.Component diagram
C.Sequence diagram
D.Use case diagram
考题
TestKing.com has a large corporate network that uses multiple routing protocols.Hosts in a portion of the network that uses EIGRP have become unreachable.Which router command will allow you, the network technician, to view the status of these routes?()A、TestKing# show eigrp entriesB、TestKing# show protocolsC、TestKing# debug eigrp routesD、TestKing# show ip route eigrpE、TestKing# show route eigrp
考题
Cisco IOS NetFlow gathers data that can be used in which three of these? ()A、 accountingB、 authenticationC、 authorizationD、 network monitoringE、 network planning
考题
Which command helps a network administrator to manage memory by displaying flash memory andNVRAM utilization?()A、show secureB、show file systemsC、show flashD、show version
考题
Which IOS user EXEC command will allow a network technician to determine which router in the path to an unreachable network host should be examined more closely for the cause of the network failure?()A、TestKingB telnetB、TestKingB pingC、TestKingB traceD、TestKingB show ip routeE、TestKingB show interfaceF、TestKingB show cdp neighbors
考题
(1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity.
空白(1)处填()A、PDMB、CPMC、PERTD、AOA
考题
A technician would use a physical network diagram to determine:()A、the cause of routing errors.B、the number of switches on the network.C、the number of users on the network.D、where network latency will occur.
考题
单选题Which of the following should be included in the network diagram?()A
Server room access logB
Server typesC
OEM contact informationD
Temperature reading
考题
单选题A mobile offshore drilling unit will show the day-shape in DIAGRAM 10 to indicate that it is ().A
at anchorB
being towedC
agroundD
drilling
考题
单选题Which IOS user EXEC command will allow a network technician to determine which router in the path to an unreachable network host should be examined more closely for the cause of the network failure?()A
TestKingB telnetB
TestKingB pingC
TestKingB traceD
TestKingB show ip routeE
TestKingB show interfaceF
TestKingB show cdp neighbors
考题
单选题A technician at TestKing needs to update the network documentation. One of the tasks includes documenting the name of the IOS image file of each router in the network.Which commands could be used to find this information?()A
Router# show protocolsB
Router# show versionC
Router# show imageD
Router# show IOSE
Router# show flash
考题
单选题Which of the following activities is the best for training detailed reading?A
Drawing a diagram to show the text structure.B
Giving the text an appropriate title.C
Transforming information fiom the text to a diagram.D
Finding out all the unfamiliar words.
考题
单选题TestKing.com has a large corporate network that uses multiple routing protocols.Hosts in a portion of the network that uses EIGRP have become unreachable.Which router command will allow you, the network technician, to view the status of these routes?()A
TestKing# show eigrp entriesB
TestKing# show protocolsC
TestKing# debug eigrp routesD
TestKing# show ip route eigrpE
TestKing# show route eigrp
考题
单选题A technician would use a physical network diagram to determine:()A
the cause of routing errors.B
the number of switches on the network.C
the number of users on the network.D
where network latency will occur.