网友您好, 请在下方输入框内输入要搜索的题目:

题目内容 (请给出正确答案)
单选题
A customer is buying 10 new Power 720 servers and will integrate them into their existing data center which also has two Power 595s and five Power 750s, taking the total number of systems to 17. All currently installed systems are managed by a single HMC.All the machines will have dual VIO Servers for redundancy, and 10 client LPARs. How can they manage the new machines for the least cost?()
A

Purchase a second HMC and use this to manage the new servers.

B

Connect all of the new servers to the existing private HMC network.

C

Configure a second private network on their existing HMC for the new servers.

D

Connect 9 of the new servers to the existing HMC and use Integrated Virtualization Manager on the 10th.


参考答案

参考解析
解析: 暂无解析
更多 “单选题A customer is buying 10 new Power 720 servers and will integrate them into their existing data center which also has two Power 595s and five Power 750s, taking the total number of systems to 17. All currently installed systems are managed by a single HMC.All the machines will have dual VIO Servers for redundancy, and 10 client LPARs. How can they manage the new machines for the least cost?()A Purchase a second HMC and use this to manage the new servers.B Connect all of the new servers to the existing private HMC network.C Configure a second private network on their existing HMC for the new servers.D Connect 9 of the new servers to the existing HMC and use Integrated Virtualization Manager on the 10th.” 相关考题
考题 A customer has a mixed environment of AIX on POWER4 and POWER5, and x86 based systems running a supported distribution of Linux. There is a total of 7 partitions and three standalone x86 servers. The customer wants to consolidate their applications using a single 4-core POWER6 server.  What is the minimum PowerVM edition that supports the customer requirement?()A、 PowerVM Lx86B、 PowerVM Express EditionC、 PowerVM Standard EditionD、 PowerVM Enterprise Edition

考题 A customer has ten RS/6000 Model M80, two pSeries 690 Model 681, five POWER5 510 and two POWER6 560 machines installed and running commercial applications. They want to do a server consolidation study in order to replace the existing systems with POWER7 systems. What performance metric is recommended when evaluating the replacement system?()A、IBM CPWB、IBM rPerfC、SPECint_rate2006D、IDEAS International RPE2

考题 A data center has had a power outage. Which of the following should the administrator do FIRST once the power is restored? ()A、 Identify which systems are the most critical and bring them up by level of importance.B、 Retrieve the latest backup tapes for immediate system restore using the GFS rotation.C、 Identify the least critical systems and then power those systems on first.D、 Determine the cause of the power outage and install UPS systems to prevent its reoccurrence.

考题 A customer wants to run VMWare ESX on an x445 with a large number of virtual machines running Windows 2003 Server as a Disaster Recovery (DR) Site for the production environment.  Which of the following questions would most impact the memory configuration?()A、What version of VMWare ESX Server is being considered?B、Do the systems currently use Double Data Rate (DDR) memory?C、What is the total number of processors installed in the production systems?D、What is the total amount of memory currently being used across all the production systems?

考题 A customer has several single partition POWER5 and POWER6 processor-based systems housed in regional data centers and wants to consolidate into a single Power 770. They must minimize overall cost and the number of adapters, while ensuring a reliable infrastructure. Which solution addresses the customer requirements?()A、Move the storage into a common SAN and virtualize the I/O using a single VIO Server with dual NIC connectors and dual HBAsB、Move the existing physical network and storage adapters to the new system and virtualize the I/O using a single VIO Server.C、Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, each with dual NIC connectors and dual HBAs.D、Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, one with dual NIC connectors and the other with dual HBAs.

考题 A customer has 5 older POWER5 systems and they want to consolidate them onto a POWER6 system. What information is important to analyze when deciding how to design the new machine using the System Planning Tool?()A、 vmstat and iostat data from the older machines B、 The number of CPUs that were installed in the original machines C、 Data from Workload Estimator (WLE) and IBM Performance Management (PM) D、 Performance data that is collected from the new system after it has been put into production

考题 A customer plans to consolidate several systems onto POWER7. Their immediate requirement is to have a single Power 770, and they will buy a second Power 770 at a later stage. They want to keep their existing three POWER5 570s and three POWER6 520s which are all managed by an HMC (7310-CR3). Which of these statements is true and would minimize the cost?()A、All the machines can be connected to the existing HMC, as long as it is updated to code level 7.7.1 or laterB、The Power 770 requires an HMC (7042-CR5 or later), so they must buy one. All of the systems can be managed by this new HMCC、They should buy a new HMC for the Power 770 system, and leave the POWER5 and POWER6 based systems connected to the existing oneD、The Power 770 requires an HMC, so they should connect the Power 770 to the HMC and convert the POWER5 and POWER6 based servers to IVM

考题 A customer has a new Power 720 with PowerVM Standard Edition.  They plan to migrate their single-partition POWER5 550 to the new Power 720.   How can the customer migrate from the POWER5 550 to the Power 720 with minimal effort and down time?()A、Perform Live Partition Mobility between the two systems.B、Move the boot disks from the old system to the new system.C、Use Tivoli Storage Manager to back up the POWER5 550 and restore on the Power 720.D、Upgrade AIX to the latest level on the POWER5 550 and clone using the mksysb command.

考题 A customer is buying 10 new Power 720 servers and will integrate them into their existing data center which also has two Power 595s and five Power 750s, taking the total number of systems to 17. All currently installed systems are managed by a single HMC.All the machines will have dual VIO Servers for redundancy, and 10 client LPARs. How can they manage the new machines for the least cost?()A、Purchase a second HMC and use this to manage the new servers.B、Connect all of the new servers to the existing private HMC network.C、Configure a second private network on their existing HMC for the new servers.D、Connect 9 of the new servers to the existing HMC and use Integrated Virtualization Manager on the 10th.

考题 A customer currently has five partitioned POWER4 systems and is adding new systems.  When the pSeries technical specialist introduces the first p5 system with CoD into this environment, how should the HMC be handled?()A、Order a new HMC to support the p5 system.B、Attach the new p5 system to the existing HMC.C、Upgrade the existing HMC to accommodate both the POWER4 and p5 systems.D、Do nothing.  This system does not require an HMC.

考题 A customer has the following equipment installed in their data center:  (1)an IBM BladeCenter H chassis (2)two power supplies  (3)six HS22V blades (4)three Nortel 1/10 GB ESMs The retail customer purchased a new HX5 with MAX5.  Which of the following must be added to install the HX5 with MAX5?()A、Two additional power suppliesB、Fibre Channel (FC) switches and SAN storageC、A Nortel 1/10 GB ESMD、SSD for the HX5

考题 A customer’s data center has all POWER4+ systems, and they plan to add three new p5-570 systems.  They will be purchasing a new 7310-CR2 HMC to support the POWER5 systems.  What is a key requirement that they need to plan for with the new HMC?()A、A desk, as it not rack mountableB、Ethernet connections to the POWER5 systemsC、Serial connections to the POWER5 systemsD、USB connections for the keyboard and mouse

考题 A customer wants to run a Domino e-mail application,a Business Intelligence database,and a batch processing application on Linux.The workloads have different behaviors and do not have peaks at the same time. What is a benefit of running these applications on a Power Systems server instead of running on separate x86 servers?()A、Each Linux application can run in a Workload Partition, reducing the management efforts.B、Total cost of Linux applications on Power Systems is more cost effective than on x86 because of platform licensing.C、Memory cloning can be used on the Power Systems to have a single image of the Linux kernel shared by all partitions.D、Using micro-partitions on Power Systems allow the workloads to share the processing resources, increasing the overall system utilization.

考题 单选题Company.com has recently received a new p5-570 in the data center and wants to Micro-Partition the server. The customer already has an existing HMC connected to a p690. Which of the following actions should the technical specialist take?()A Order a POWER5 HMCB Connect to the existing HMCC Install an 8-port asynchronous card in the managed server to connect to the existing HMCD Install an additional network card to the existing HMC and connect to the POWER5 service processor

考题 单选题A customer plans to consolidate several systems onto POWER7. Their immediate requirement is to have a single Power 770, and they will buy a second Power 770 at a later stage. They want to keep their existing three POWER5 570s and three POWER6 520s which are all managed by an HMC (7310-CR3). Which of these statements is true and would minimize the cost?()A All the machines can be connected to the existing HMC, as long as it is updated to code level 7.7.1 or laterB The Power 770 requires an HMC (7042-CR5 or later), so they must buy one. All of the systems can be managed by this new HMCC They should buy a new HMC for the Power 770 system, and leave the POWER5 and POWER6 based systems connected to the existing oneD The Power 770 requires an HMC, so they should connect the Power 770 to the HMC and convert the POWER5 and POWER6 based servers to IVM

考题 单选题A data center has had a power outage. Which of the following should the administrator do FIRST once the power is restored?()A Identify which systems are the most critical and bring them up by level of importance.B Retrieve the latest backup tapes for immediate system restore using the GFS rotation.C Identify the least critical systems and then power those systems on first.D Determine the cause of the power outage and install UPS systems to prevent its reoccurrence.

考题 单选题A customer has 5 older POWER5 systems and they want to consolidate them onto a POWER6 system. What information is important to analyze when deciding how to design the new machine using the System Planning Tool?()A  vmstat and iostat data from the older machinesB  The number of CPUs that were installed in the original machinesC  Data from Workload Estimator (WLE) and IBM Performance Management (PM)D  Performance data that is collected from the new system after it has been put into production

考题 单选题A customer has the following equipment installed in their data center:  (1)an IBM BladeCenter H chassis (2)two power supplies  (3)six HS22V blades (4)three Nortel 1/10 GB ESMs The retail customer purchased a new HX5 with MAX5.  Which of the following must be added to install the HX5 with MAX5?()A Two additional power suppliesB Fibre Channel (FC) switches and SAN storageC A Nortel 1/10 GB ESMD SSD for the HX5

考题 单选题A customer has ten RS/6000 Model M80, two pSeries 690 Model 681, five POWER5 510 and two POWER6 560 machines installed and running commercial applications. They want to do a server consolidation study in order to replace the existing systems with POWER7 systems. What performance metric is recommended when evaluating the replacement system?()A IBM CPWB IBM rPerfC SPECint_rate2006D IDEAS International RPE2

考题 单选题A customer has 5 older POWER5 systems and they want to consolidate them onto a POWER6 system. What information is important to analyze when deciding how to design the new machine using the System Planning Tool?()A  vmstat and iostat data from the older machines B  The number of CPUs that were installed in the original machines C  Data from Workload Estimator (WLE) and IBM Performance Management (PM) D  Performance data that is collected from the new system after it has been put into production

考题 单选题A customer has a mixed environment of AIX on POWER4 and POWER5, and x86 based systems running a supported distribution of Linux. There is a total of 7 partitions and three standalone x86 servers. The customer wants to consolidate their applications using a single 4-core POWER6 server.  What is the minimum PowerVM edition that supports the customer requirement?()A  PowerVM Lx86B  PowerVM Express EditionC  PowerVM Standard EditionD  PowerVM Enterprise Edition

考题 单选题A customer has a new Power 720 with PowerVM Standard Edition.  They plan to migrate their single-partition POWER5 550 to the new Power 720.   How can the customer migrate from the POWER5 550 to the Power 720 with minimal effort and down time?()A Perform Live Partition Mobility between the two systems.B Move the boot disks from the old system to the new system.C Use Tivoli Storage Manager to back up the POWER5 550 and restore on the Power 720.D Upgrade AIX to the latest level on the POWER5 550 and clone using the mksysb command.

考题 单选题A customer currently has five partitioned POWER4 systems and is adding new systems.  When the pSeries technical specialist introduces the first p5 system with CoD into this environment, how should the HMC be handled?()A Order a new HMC to support the p5 system.B Attach the new p5 system to the existing HMC.C Upgrade the existing HMC to accommodate both the POWER4 and p5 systems.D Do nothing.  This system does not require an HMC.

考题 单选题A data center has had a power outage. Which of the following should the administrator do FIRST once the power is restored? ()A  Identify which systems are the most critical and bring them up by level of importance.B  Retrieve the latest backup tapes for immediate system restore using the GFS rotation.C  Identify the least critical systems and then power those systems on first.D  Determine the cause of the power outage and install UPS systems to prevent its reoccurrence.

考题 单选题A customer has several single partition POWER5 and POWER6 processor-based systems housed in regional data centers and wants to consolidate into a single Power 770. They must minimize overall cost and the number of adapters, while ensuring a reliable infrastructure. Which solution addresses the customer requirements?()A Move the storage into a common SAN and virtualize the I/O using a single VIO Server with dual NIC connectors and dual HBAsB Move the existing physical network and storage adapters to the new system and virtualize the I/O using a single VIO Server.C Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, each with dual NIC connectors and dual HBAs.D Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, one with dual NIC connectors and the other with dual HBAs.

考题 单选题A customer wants to run VMWare ESX on an x445 with a large number of virtual machines running Windows 2003 Server as a Disaster Recovery (DR) Site for the production environment.  Which of the following questions would most impact the memory configuration?()A What version of VMWare ESX Server is being considered?B Do the systems currently use Double Data Rate (DDR) memory?C What is the total number of processors installed in the production systems?D What is the total amount of memory currently being used across all the production systems?

考题 单选题A customer’s data center has all POWER4+ systems, and they plan to add three new p5-570 systems.  They will be purchasing a new 7310-CR2 HMC to support the POWER5 systems.  What is a key requirement that they need to plan for with the new HMC?()A A desk, as it not rack mountableB Ethernet connections to the POWER5 systemsC Serial connections to the POWER5 systemsD USB connections for the keyboard and mouse